4491 Factors Affecting Time Performance in Building Construction Projects

Authors: Ibraheem A. K. Mahameed

Abstract:

The aim of this study is to identify the risks affecting time performance of building construction projects in the West Bank in Palestine from contractors’ viewpoint. 38 risks that might affect time performance of building construction projects were defined through a detailed literature review. These risks have been classified into 6 groups: project, managerial, consultant, financial, external, and construction items. A questionnaire survey was performed to rank the considered risks in terms of severity and frequency. The analysis of the survey indicated that the top five risks affecting time performance of building construction projects in Palestine are: award project to the lowest price, political situation, poor communication and coordination between construction parties, change orders, and financial status of contractor.

Keywords: delay, time performance, construction, building

Procedia PDF Downloads 433
4490 Achieving Sustainable Rapid Construction Using Lean Principles

Authors: Muhamad Azani Yahya, Vikneswaran Munikanan, Mohammed Alias Yusof

Abstract:

There is the need to take the holistic approach in achieving sustainable construction for a contemporary practice. Sustainable construction is the practice that involved method of human preservation of the environment, whether economically or socially through responsibility, management of resources and maintenance utilizing support. This paper shows the correlation of achieving rapid construction with sustainable concepts using lean principles. Lean principles being used widely in the manufacturing industry, but this research will demonstrate the principles into building construction. Lean principle offers the benefits of stabilizing work flow and elimination of unnecessary work. Therefore, this principle contributes to time and waste reduction. The correlation shows that pulling factor provides the improvement of progress curve and stabilizing the time-quality relation. The finding shows the lean principles offer the elements of rapid construction synchronized with the elements of sustainability.

Keywords: sustainable construction, rapid construction, time reduction, lean construction

Procedia PDF Downloads 212
4489 Causes and Effects of Delays in Construction Projects in Akure, Ondo State, South-West Nigeria

Authors: K.T Alade, A.F Lawal, A.A Omonori

Abstract:

Construction is an everlasting activity across the globe. Likewise, the problem of delay in the construction industry is a global phenomenon. Although there are several reasons that may be responsible for delay during construction, this may vary from place to place and can be reduced to the minimum when identified. This study considered the major causes and effects of delay in the execution of construction projects in Akure, Ondo State, Nigeria. Using literatures, a total number of 30 causes of construction delays were identified. The convenient sampling technique was used to select sixty respondents for a survey. The respondents comprise twenty-two (22) clients, eighteen consultants (18) and twenty (20) contractors. The analyses of the primary data revealed that the three most important causes of delay in construction projects in Akure, Ondo State Nigeria are poor site management and supervision, inadequate contractors experience and client’s financial difficulties. Based on the findings of this study, recommendations were given on how the causes and effects of delay in construction can be mitigated.

Keywords: Akure, causes, construction projects, delay, effects

Procedia PDF Downloads 476
4488 Hybrid Concrete Construction (HCC) for Sustainable Infrastructure Development in Nigeria

Authors: Muhammad Bello Ibrahim, M. Auwal Zakari, Aliyu Usman

Abstract:

Hybrid concrete construction (HCC) combines all the benefits of pre-casting with the advantages of cast in-situ construction. Merging the two, as a hybrid structure, results in even greater construction speed, value, and the overall economy. Its variety of uses has gained popularity in the United States and in Europe due to its distinctive benefits. However, the increase of its application in some countries (including Nigeria) has been relatively slow. Several researches have shown that hybrid construction offers an ultra-high performance concrete that offers superior strength, durability and aesthetics with design flexibility and within sustainability credentials, based on the available and economically visible technologies. This paper examines and documents the criterion that will help inform the process of deciding whether or not to adopt hybrid concrete construction (HCC) technology rather than more traditional alternatives. It also the present situation of design, construction and research on hybrid structures.

Keywords: hybrid concrete construction, Nigeria, sustainable infrastructure development, design flexibility

Procedia PDF Downloads 519
4487 Major Causes of Delay in Construction Projects

Authors: Y. Gholipour, E. Rezazadeh

Abstract:

Delay is one of the most serious and common problems of construction project that can affect project delivery unfavorably. This research presents the most important causes of delay in large dam projects based on a survey on some executed dam construction in Iran. In this survey a randomly selected samples of owners, consultants and contractors have been involved. The outcome of this survey revealed that scheduled payments, site management, shop drawing review process, unforeseen ground conditions and contractor experience as the most important factors affecting on delay in dam construction projects.

Keywords: delay, dam construction, project management, Iran

Procedia PDF Downloads 413
4486 Development of Construction Cost Optimization System Using Genetic Algorithm Method

Authors: Hyeon-Seung Kim, Young-Hwan Kim, Sang-Mi Park, Min-Seo Kim, Jong-Myeung Shin, Leen-Seok Kang

Abstract:

The project budget at the planned stage might be changed by the insufficient government budget or the design change. There are many cases more especially in the case of a project performed for a long period of time. If the actual construction budget is insufficient comparing with the planned budget, the construction schedule should also be changed to match the changed budget. In that case, most project managers change the planned construction schedule by a heuristic approach without a reasonable consideration on the work priority. This study suggests an optimized methodology to modify the construction schedule according to the changed budget. The genetic algorithm was used to optimize the modified construction schedule within the changed budget. And a simulation system of construction cost histogram in accordance with the construction schedule was developed in the BIM (Building Information Modeling) environment.

Keywords: 5D, BIM, GA, cost optimization

Procedia PDF Downloads 567
4485 Sensitivity Assessment of Spectral Salinity Indices over Desert Sabkha of Western UAE

Authors: Rubab Ammad, Abdelgadir Abuelgasim

Abstract:

UAE typically lies in one of the aridest regions of the world and is thus home to geologic features common to such climatic conditions including vast open deserts, sand dunes, saline soils, inland Sabkha and coastal Sabkha. Sabkha are characteristic salt flats formed in arid environment due to deposition and precipitation of salt and silt over sand surface because of low laying water table and rates of evaporation exceeding rates of precipitation. The study area, which comprises of western UAE, is heavily concentrated with inland Sabkha. Remote sensing is conventionally used to study the soil salinity of agriculturally degraded lands but not so broadly for Sabkha. The focus of this study was to identify these highly saline Sabkha areas on remotely sensed data, using salinity indices. The existing salinity indices in the literature have been designed for agricultural soils and they have not frequently used the spectral response of short-wave infra-red (SWIR1 and SWIR2) parts of electromagnetic spectrum. Using Landsat 8 OLI data and field ground truthing, this study formulated indices utilizing NIR-SWIR parts of spectrum and compared the results with existing salinity indices. Most indices depict reasonably good relationship between salinity and spectral index up until a certain value of salinity after which the reflectance reaches a saturation point. This saturation point varies with index. However, the study findings suggest a role of incorporating near infra-red and short-wave infra-red in salinity index with a potential of showing a positive relationship between salinity and reflectance up to a higher salinity value, compared to rest.

Keywords: Sabkha, salinity index, saline soils, Landsat 8, SWIR1, SWIR2, UAE desert

Procedia PDF Downloads 175
4484 Reliability Analysis in Power Distribution System

Authors: R. A. Deshpande, P. Chandhra Sekhar, V. Sankar

Abstract:

In this paper, we discussed the basic reliability evaluation techniques needed to evaluate the reliability of distribution systems which are applied in distribution system planning and operation. Basically, the reliability study can also help to predict the reliability performance of the system after quantifying the impact of adding new components to the system. The number and locations of new components needed to improve the reliability indices to certain limits are identified and studied.

Keywords: distribution system, reliability indices, urban feeder, rural feeder

Procedia PDF Downloads 744
4483 The Eco-Efficient Construction: A Review of Embodied Energy in Building Materials

Authors: Francesca Scalisi, Cesare Sposito

Abstract:

The building construction industry consumes a large amount of resources and energy, both during construction (embodied energy) and during the operational phase (operating energy). This paper presents a review of the literature on low carbon and low embodied energy materials in buildings. The embodied energy comprises the energy consumed during the extraction, processing, transportation, construction, and demolition of building materials. While designing a nearly zero energy building, it is necessary to choose and use materials, components, and technologies that allow to reduce the consumption of energy and also to reduce the emissions in the atmosphere during all the Life Cycle Assessment phases. The appropriate choice of building materials can contribute decisively to reduce the energy consumption of the building sector. The increasing worries for the environmental impact of construction materials are witnessed by a lot of studies. The mentioned worries have brought again the attention towards natural materials. The use of more sustainable construction materials and construction techniques represent a major contribution to the eco-efficiency of the construction industry and thus to a more sustainable development.

Keywords: embodied energy, embodied carbon, life cycle assessment, architecture, sustainability, material construction

Procedia PDF Downloads 300
4482 Empirical Study of Correlation between the Cost Performance Index Stability and the Project Cost Forecast Accuracy in Construction Projects

Authors: Amin AminiKhafri, James M. Dawson-Edwards, Ryan M. Simpson, Simaan M. AbouRizk

Abstract:

Earned value management (EVM) has been introduced as an integrated method to combine schedule, budget, and work breakdown structure (WBS). EVM provides various indices to demonstrate project performance including the cost performance index (CPI). CPI is also used to forecast final project cost at completion based on the cost performance during the project execution. Knowing the final project cost during execution can initiate corrective actions, which can enhance project outputs. CPI, however, is not constant during the project, and calculating the final project cost using a variable index is an inaccurate and challenging task for practitioners. Since CPI is based on the cumulative progress values and because of the learning curve effect, CPI variation dampens and stabilizes as project progress. Although various definitions for the CPI stability have been proposed in literature, many scholars have agreed upon the definition that considers a project as stable if the CPI at 20% completion varies less than 0.1 from the final CPI. While 20% completion point is recognized as the stability point for military development projects, construction projects stability have not been studied. In the current study, an empirical study was first conducted using construction project data to determine the stability point for construction projects. Early findings have demonstrated that a majority of construction projects stabilize towards completion (i.e., after 70% completion point). To investigate the effect of CPI stability on cost forecast accuracy, the correlation between CPI stability and project cost at completion forecast accuracy was also investigated. It was determined that as projects progress closer towards completion, variation of the CPI decreases and final project cost forecast accuracy increases. Most projects were found to have 90% accuracy in the final cost forecast at 70% completion point, which is inlined with findings from the CPI stability findings. It can be concluded that early stabilization of the project CPI results in more accurate cost at completion forecasts.

Keywords: cost performance index, earned value management, empirical study, final project cost

Procedia PDF Downloads 130
4481 Effects of Diabetic Duration on Platelet and Platelet Indices in Streptozotocin-Induced Diabetic Rats

Authors: Sahar Oudeh, Abbas Javaheri Vayeghan, Mahmood Ahmadi-Hamedani

Abstract:

This study aimed to investigate the effect of diabetic duration on platelet and platelet indices in streptozotocin-induced diabetic male and female rats. Thirty-two healthy adult Wistar rats (16 females and 16 males) were randomly divided into 4 groups of eight, including 1) control group (4 females and 4 males who did not undergo any treatment until the end of 28 days), 2) 7-day diabetic group (4 females and 4 males who were diabetic for 7 days and were euthanized after 7 days), 3) 14-day diabetic group (4 females and 4 males who were diabetic for 14 days and were euthanized after 14 days), and 28-day diabetic group (4 females and 4 males who were diabetic for 28 days and were euthanized after 28 days). Diabetes was induced by intraperitoneal injection of streptozotocin (65 mg/kg). After induction of diabetes in the groups, blood samples were taken from their hearts after anesthesia, and platelet counts (PLT) and platelet indices were measured by an automatic blood cell counter (Nihon Kohden, Celltac Alpha VET MEK-6550, Japan). Statistical differences among groups were analyzed using one-way analysis of variance (ANOVA) followed by Tukey’s multiple tests. The results of this study showed that PLT and mean platelet volume (MPV) significantly increased in 7 and 14-day diabetic groups compared to the control group, whereas plateletcrit (PCT) and platelet distribution rate (PDW) significantly increased in 14 and 28-day diabetic groups, respectively. Significant differences were observed between female and male rats in PCT and PLT in the 14-day diabetic group and PDW in the 28-day diabetic group. According to the results of this study, measurement and analysis of platelet indices can be used as a method for the early diagnosis of diabetes and its complications.

Keywords: diabetic duration, streptozotocin, female and male rats, platelet indices

Procedia PDF Downloads 138
4480 Methodology of Construction Equipment Optimization for Earthwork

Authors: Jaehyun Choi, Hyunjung Kim, Namho Kim

Abstract:

Earthwork is one of the critical civil construction operations that require large-quantities of resources due to its intensive dependency upon construction equipment. Therefore, efficient construction equipment management can highly contribute to productivity improvements and cost savings. Earthwork operation utilizes various combinations of construction equipment in order to meet project requirements such as time and cost. Identification of site condition and construction methods should be performed in advance in order to develop a proper execution plan. The factors to be considered include capacity of equipment assigned, the method of construction, the size of the site, and the surrounding condition. In addition, optimal combination of various construction equipment should be selected. However, in real world practice, equipment utilization plan is performed based on experience and intuition of management. The researchers evaluated the efficiency of various alternatives of construction equipment combinations by utilizing the process simulation model, validated the model from a case study project, and presented a methodology to find optimized plan among alternatives.

Keywords: earthwork operation, construction equipment, process simulation, optimization

Procedia PDF Downloads 401
4479 Plasma Lipid Profiles and Atherogenic Indices of Rats Fed Raw and Processed Jack Fruit (Artocarpus heterophyllus) Seeds Diets at Different Concentrations

Authors: O. E. Okafor, L. U. S. Ezeanyika, C. G. Nkwonta, C. J. Okonkwo

Abstract:

The effect of processing on plasma lipid profile and atherogenic indices of rats fed Artocarpus heterophyllus seed diets at different concentrations were investigated. Fifty five rats were used for this study, they were divided into eleven groups of five rats each (one control group and ten test groups), the test groups were fed raw, boiled, roasted, fermented, and soaked diets at 10 % and 40% concentrations. The study lasted for thirty five days. The diets led to significant decrease (p < 0.05) in plasma cholesterol and triacylglycerol of rats fed 10% and 40% concentrations of the diets, and a significant increase (p < 0.05) in high density lipoprotein (HDL) levels at 40% concentrations of the test diets. The diets also produced decrease in low density lipoprotein (LDL), very low density lipoprotein (VLDL), cardiac risk ratio (CRR), atherogenic index of plasma (AIP) and atherogenic coefficient (AC) at 40% concentrations except the soaked group that showed slight elevation of LDL, CRR, AC and AIP at 40% concentration. Artocarpus heterophyllus seeds could be beneficial to health because of its ability to increase plasma HDL and reduce plasma LDL, VLDL, cholesterol, triglycerides and atherogenic indices at higher diet concentration.

Keywords: artocarpus heterophyllus, atherogenic indices, concentrations, lipid profile

Procedia PDF Downloads 275
4478 Radial Distribution Network Reliability Improvement by Using Imperialist Competitive Algorithm

Authors: Azim Khodadadi, Sahar Sadaat Vakili, Ebrahim Babaei

Abstract:

This study presents a numerical method to optimize the failure rate and repair time of a typical radial distribution system. Failure rate and repair time are effective parameters in customer and energy based indices of reliability. Decrease of these parameters improves reliability indices. Thus, system stability will be boost. The penalty functions indirectly reflect the cost of investment which spent to improve these indices. Constraints on customer and energy based indices, i.e. SAIFI, SAIDI, CAIDI and AENS have been considered by using a new method which reduces optimization algorithm controlling parameters. Imperialist Competitive Algorithm (ICA) used as main optimization technique and particle swarm optimization (PSO), simulated annealing (SA) and differential evolution (DE) has been applied for further investigation. These algorithms have been implemented on a test system by MATLAB. Obtained results have been compared with each other. The optimized values of repair time and failure rate are much lower than current values which this achievement reduced investment cost and also ICA gives better answer than the other used algorithms.

Keywords: imperialist competitive algorithm, failure rate, repair time, radial distribution network

Procedia PDF Downloads 628
4477 Determining the Octanol-Water Partition Coefficient for Armchair Polyhex BN Nanotubes Using Topological Indices

Authors: Esmat Mohammadinasab

Abstract:

The aim of this paper is to investigate theoretically and establish a predictive model for determination LogP of armchair polyhex BN nanotubes by using simple descriptors. The relationship between the octanol-water partition coefficient (LogP) and quantum chemical descriptors, electric moments, and topological indices of some armchair polyhex BN nanotubes with various lengths and fixed circumference are represented. Based on density functional theory (DFT) electric moments and physico-chemical properties of those nanotubes are calculated. The DFT method performed based on the Becke’s 3-parameter formulation with the Lee-Yang-Parr functional (B3LYP) method and 3-21G standard basis sets. For the first time, the relationship between partition coefficient and different properties of polyhex BN nanotubes is investigated.

Keywords: topological indices, quantum descriptors, DFT method, nanotubes

Procedia PDF Downloads 314
4476 Identifying Project Delay Factors in the Australian Construction Industry

Authors: Syed Sohaib Bin Hasib, Hiyam Al-Kilidar

Abstract:

Meeting project deadlines is a major challenge for most construction projects. In this study, perceptions of contractors, clients, and consultants are compared relative to a list of factors derived from the review of the extant literature on project delay. 59 causes (categorized into 8 groups) of project delays were identified from the literature. A survey was devised to get insights and ranking of these factors from clients, consultants & contractors in the Australian construction industry. Findings showed that project delays in the Australian construction industry are mainly the result of skill shortages, interference in execution, and poor coordination and communication between the project stakeholders.

Keywords: construction, delay factors, time delay, australian construction industry

Procedia PDF Downloads 141
4475 Abating the Barriers to the Deployment of RFID for Construction Project Delivery in South Africa

Authors: Matthew O. Ikuabe, Ayodeji E. Oke, Clinton O. Aigbavboa, Douglas O. Aghimien

Abstract:

The use of technological innovations have been touted to be beneficial in the delivery of construction projects. Particularly, Radio Frequency Identification (RFID) technology is widely regarded to be of immense advantage for the management of construction projects. This study focused on evaluating the barriers to the use of Radio Frequency Identification (RFID) technology for the delivery of construction projects. Using Gauteng Provincein South Africa as the study area, questionnaire was used in eliciting responses from construction professionals, which made up the population of the study. Retrieved data was analysed using Mean Item Score and One-Sample t-test. Findings from the study showed that the most significant barriers to the deployment of RFID for construction project delivery are high cost and lack of awareness. Conclusively, the study made recommendations that would aid in the abatement of the barriers to the use of RFID technology for construction project delivery.

Keywords: barriers, construction, project delivery, RFID

Procedia PDF Downloads 161
4474 Comparison of the Anthropometric Obesity Indices in Prediction of Cardiovascular Disease Risk: Systematic Review and Meta-analysis

Authors: Saeed Pourhassan, Nastaran Maghbouli

Abstract:

Statement of the problem: The relationship between obesity and cardiovascular diseases has been studied widely(1). The distribution of fat tissue gained attention in relation to cardiovascular risk factors during lang-time research (2). American College of Cardiology/American Heart Association (ACC/AHA) is widely and the most reliable tool to be used as a cardiovascular risk (CVR) assessment tool(3). This study aimed to determine which anthropometric index is better in discrimination of high CVR patients from low risks using ACC/AHA score in addition to finding the best index as a CVR predictor among both genders in different races and countries. Methodology & theoretical orientation: The literature in PubMed, Scopus, Embase, Web of Science, and Google Scholar were searched by two independent investigators using the keywords "anthropometric indices," "cardiovascular risk," and "obesity." The search strategy was limited to studies published prior to Jan 2022 as full-texts in the English language. Studies using ACC/AHA risk assessment tool as CVR and those consisted at least 2 anthropometric indices (ancient ones and novel ones) are included. Study characteristics and data were extracted. The relative risks were pooled with the use of the random-effect model. Analysis was repeated in subgroups. Findings: Pooled relative risk for 7 studies with 16,348 participants were 1.56 (1.35-1.72) for BMI, 1.67(1.36-1.83) for WC [waist circumference], 1.72 (1.54-1.89) for WHR [waist-to-hip ratio], 1.60 (1.44-1.78) for WHtR [waist-to-height ratio], 1.61 (1.37-1.82) for ABSI [A body shape index] and 1.63 (1.32-1.89) for CI [Conicity index]. Considering gender, WC among females and WHR among men gained the highest RR. The heterogeneity of studies was moderate (α²: 56%), which was not decreased by subgroup analysis. Some indices such as VAI and LAP were evaluated just in one study. Conclusion & significance: This meta-analysis showed WHR could predict CVR better in comparison to BMI or WHtR. Some new indices like CI and ABSI are less accurate than WHR and WC. Among women, WC seems to be a better choice to predict cardiovascular disease risk.

Keywords: obesity, cardiovascular disease, risk assessment, anthropometric indices

Procedia PDF Downloads 79
4473 Development of Risk Assessment and Occupational Safety Management Model for Building Construction Projects

Authors: Preeda Sansakorn, Min An

Abstract:

In order to be capable of dealing with uncertainties, subjectivities, including vagueness arising in building construction projects, the application of fuzzy reasoning technique based on fuzzy set theory is proposed. This study contributes significantly to the development of a fuzzy reasoning safety risk assessment model for building construction projects that could be employed to assess the risk magnitude of each hazardous event identified during construction, and a third parameter of probability of consequence is incorporated in the model. By using the proposed safety risk analysis methodology, more reliable and less ambiguities, which provide the safety risk management project team for decision-making purposes.

Keywords: safety risk assessment, building construction safety, fuzzy reasoning, construction risk assessment model, building construction projects

Procedia PDF Downloads 455
4472 An Assessment of the Factors Affecting Green Building Technology (GBT) Adoption

Authors: Nuruddeen Usman, Usman Mohammed Gidado

Abstract:

A construction and post construction activity in buildings contributes to environmental degradation, because of the generation of solid waste during construction to the production of carbon dioxide by the occupants during utilization. These problems were caused as a result of lack of adopting green building technology during and after construction. However, this study aims at conceptualizing the factors that are affecting the adoption of green building technology with a view to suggest better ways for its successful adoption in the construction industry through developing a green building technology model. Thus, the research findings show that: Economic, social, cultural, and technological progresses are the factors affecting Green Building Technology Adoption. Therefore, identifying these factors and developing the model might help in the successful adoption of green building technology.

Keywords: green building technology, construction, post construction, degradation

Procedia PDF Downloads 621
4471 Investigations into Transition from Traditional Construction to Industrial Construction in Afghanistan

Authors: A. Latif Karimi

Abstract:

Since 2001, construction works, especially the construction of new homes and residential buildings, witnessed a dramatic boom across Afghanistan. More so, the construction industry and house builders are relied upon as important players in the country’s job market, economy and infrastructural development schemes. However, a lack of innovation, quality assurance mechanism, substandard construction and market dominance by traditional methods push all the parties in house building sector to shift for more advanced construction techniques and mass production technologies to meet the rising demands for proper accommodation. Meanwhile, rapid population growth and urbanization are widening the gap between the demand and supply of new and modern houses in urban areas like Kabul, Herat, etc. This paper investigates about current condition of construction practices in house building projects, the associated challenges, and the outcomes of transition to more reasonable and sustainable building methods. It is obvious, the introduction and use of Modern Methods of Construction (MMC) can help construction industry and house builders in Afghanistan to tackle the challenges and meet the desired standards for modern houses. This paper focuses on prefabrication, a popular MMC that is becoming more common, improving in quality and available in a variety of budgets. It is revealed that this method is the way forward to improving house building practices as it has been proven to reduce construction time, minimize waste and improve environmental performance of construction developments.

Keywords: modern houses, traditional construction, modern methods of construction, prefabrication, sustainable building

Procedia PDF Downloads 252
4470 Assessment of Spectral Indices for Soil Salinity Estimation in Irrigated Land

Authors: R. Lhissou , A. El Harti , K. Chokmani, E. Bachaoui, A. El Ghmari

Abstract:

Soil salinity is a serious environmental hazard in many countries around the world especially the arid and semi-arid countries like Morocco. Salinization causes negative effects on the ground; it affects agricultural production, infrastructure, water resources and biodiversity. Remote sensing can provide soil salinity information for large areas, and in a relatively short time. In addition, remote sensing is not limited by extremes in terrain or hazardous condition. Contrariwise, experimental methods for monitoring soil salinity by direct measurements in situ are very demanding of time and resources, and also very limited in spatial coverage. In the irrigated perimeter of Tadla plain in central Morocco, the increased use of saline groundwater and surface water, coupled with agricultural intensification leads to the deterioration of soil quality especially by salinization. In this study, we assessed several spectral indices of soil salinity cited in the literature using Landsat TM satellite images and field measurements of electrical conductivity (EC). Three Landsat TM satellite images were taken during 3 months in the dry season (September, October and November 2011). Based on field measurement data of EC collected in three field campaigns over the three dates simultaneously with acquisition dates of Landsat TM satellite images, a two assessment techniques are used to validate a soil salinity spectral indices. Firstly, the spectral indices are validated locally by pixel. The second validation technique is made using a window of size 3x3 pixels. The results of the study indicated that the second technique provides getting a more accurate validation and the assessment has shown its limits when it comes to assess across the pixel. In addition, the EC values measured from field have a good correlation with some spectral indices derived from Landsat TM data and the best results show an r² of 0.88, 0.79 and 0.65 for Salinity Index (SI) in the three dates respectively. The results have shown the usefulness of spectral indices as an auxiliary variable in the spatial estimation and mapping salinity in irrigated land.

Keywords: remote sensing, spectral indices, soil salinity, irrigated land

Procedia PDF Downloads 365
4469 BIM Application and Construction Schedule Simulation for the Horizontal Work Area

Authors: Hyeon-Seong Kim, Sang-Mi Park, Seul-Gi Kim, Seon-Ju Han, Leen-Seok Kang

Abstract:

The use of BIM, including 4D CAD system, in a construction project is gradually increasing. Since the building construction works repeatedly in the vertical space, it is relatively easy to confirm the interference effect when applying the BIM, but the interference effect for the civil engineering project is relatively small because the civil works perform non-repetitive processes in the horizontal space. For this reason, it is desirable to apply BIM to the construction phase when applying BIM to the civil engineering project, and the most active BIM tool applied to the construction phase is the 4D CAD function for the schedule management. This paper proposes the application procedure of BIM by the construction phase of civil engineering project and a linear 4D CAD construction methodology suitable for the civil engineering project in which linear work is performed.

Keywords: BIM, 4D CAD, linear 4D simulation, VR

Procedia PDF Downloads 369
4468 The Appraisal of Construction Sites Productivity: In Kendall’s Concordance

Authors: Abdulkadir Abu Lawal

Abstract:

For the dearth of reliable cardinal numerical data, the linked phenomena in productivity indices such as operational costs and company turnovers, etc. could not be investigated. This would not give us insight to the root of productivity problems at unique sites. So, ordinal ranking by professionals who were most directly involved with construction sites was applied for Kendall’s concordance. Responses gathered from independent architects, builders/engineers, and quantity surveyors were herein analyzed. They were responses based on factors that affect sites productivity, and these factors were categorized as head office factors, resource management effectiveness factors, motivational factors, and training/skill development factors. It was found that productivity is low and has to be improved in order to facilitate Nigerian efforts in bridging its infrastructure deficit. The significance of this work is underlined with the Kendall’s coefficient of concordance of 0.78, while remedial measures must be emphasized to stimulate better productivity. Further detailed study can be undertaken by using Fuzzy logic analysis on wider Delphi survey.

Keywords: factors, Kendall's coefficient of concordance, magnitude of agreement, percentage magnitude of dichotomy, ranking variables

Procedia PDF Downloads 593
4467 Managing Projects in Practice. A Perspective of Stakeholder Management in Managing Stakeholders within the UK Construction Projects

Authors: Faraz Ali Memon

Abstract:

Stakeholders are a vital part of any organisation. It includes working on the demands of different stakeholders within the projects. However, the reality of construction projects is slightly different when it comes to practice. The UK construction projects have a history of failing to complete projects on time and within the budget. The purpose of this qualitative study is to enhance knowledge of stakeholder engagement. Semi-structured interviews will be carried out using a purposive sampling technique. It includes interviewing and getting knowledge from industry practitioners from top UK construction firms on how to manage stakeholders effectively. The findings from this study will help in understanding stakeholders' impact and how the engagement of stakeholders can affect construction projects. The conclusions of this study add value to the existing body of knowledge on stakeholder management, especially in the UK, where academic studies on construction projects are few. As a contribution, this study will provide a practical guide for the practitioners to engage stakeholders within the scope of the project. In addition, this study is limited to UK construction projects. Therefore, the outcome may not be generalised to other developing and underdeveloped countries.

Keywords: stakeholders, UK construction, project management, cost and time

Procedia PDF Downloads 59
4466 Lean Construction Techniques in Construction Projects of Pakistan

Authors: Aftab Hameed Memon, Shadab Noor, Muhammad Akram Akhund

Abstract:

Lean construction is a philosophy adopted in the construction industry to increase the value of a project by reducing waste and improving construction productivity. Lean emphasizes on maximizing the value of a project with less expenditure. Globally, lean philosophy has received wider popularity in construction sector. Lean construction has supported the practitioners with several tools and techniques to implement at various stages of a construction project. Following the global trends, this study has investigated the lean practice in Pakistan. The level of implementation of different lean tools and techniques altogether with potential benefits experienced by its implementation in construction projects of Pakistan is analyzed. To achieve the targets, the opinion was sought by the practitioners involved in handling construction projects representing four stakeholders that are a client, consultant, contractors and material suppliers through a structured questionnaire. A total of 34 completed questionnaires were collected and then statistically analyzed. The findings of the analysis have highlighted that pull approach, work standardization, just in time, increase visualization tools, integrated project delivery method and fail-safe for quality are common lean techniques implemented in the local construction industry. While reduction in waste, client’s satisfaction, improved communication, visual control and proper task management are major benefits of the lean construction application.

Keywords: lean construction, lean tools and techniques, lean benefits, waste reduction, Pakistan

Procedia PDF Downloads 261
4465 The Potential Involvement of Platelet Indices in Insulin Resistance in Morbid Obese Children

Authors: Orkide Donma, Mustafa M. Donma

Abstract:

Association between insulin resistance (IR) and hematological parameters has long been a matter of interest. Within this context, body mass index (BMI), red blood cells, white blood cells and platelets were involved in this discussion. Parameters related to platelets associated with IR may be useful indicators for the identification of IR. Platelet indices such as mean platelet volume (MPV), platelet distribution width (PDW) and plateletcrit (PCT) are being questioned for their possible association with IR. The aim of this study was to investigate the association between platelet (PLT) count as well as PLT indices and the surrogate indices used to determine IR in morbid obese (MO) children. A total of 167 children participated in the study. Three groups were constituted. The number of cases was 34, 97 and 36 children in the normal BMI, MO and metabolic syndrome (MetS) groups, respectively. Sex- and age-dependent BMI-based percentile tables prepared by World Health Organization were used for the definition of morbid obesity. MetS criteria were determined. BMI values, homeostatic model assessment for IR (HOMA-IR), alanine transaminase-to-aspartate transaminase ratio (ALT/AST) and diagnostic obesity notation model assessment laboratory (DONMA-lab) index values were computed. PLT count and indices were analyzed using automated hematology analyzer. Data were collected for statistical analysis using SPSS for Windows. Arithmetic mean and standard deviation were calculated. Mean values of PLT-related parameters in both control and study groups were compared by one-way ANOVA followed by Tukey post hoc tests to determine whether a significant difference exists among the groups. The correlation analyses between PLT as well as IR indices were performed. Statistically significant difference was accepted as p-value < 0.05. Increased values were detected for PLT (p < 0.01) and PCT (p > 0.05) in MO group compared to those observed in children with N-BMI. Significant increases for PLT (p < 0.01) and PCT (p < 0.05) were observed in MetS group in comparison with the values obtained in children with N-BMI (p < 0.01). Significantly lower MPV and PDW values were obtained in MO group compared to the control group (p < 0.01). HOMA-IR (p < 0.05), DONMA-lab index (p < 0.001) and ALT/AST (p < 0.001) values in MO and MetS groups were significantly increased compared to the N-BMI group. On the other hand, DONMA-lab index values also differed between MO and MetS groups (p < 0.001). In the MO group, PLT was negatively correlated with MPV and PDW values. These correlations were not observed in the N-BMI group. None of the IR indices exhibited a correlation with PLT and PLT indices in the N-BMI group. HOMA-IR showed significant correlations both with PLT and PCT in the MO group. All of the three IR indices were well-correlated with each other in all groups. These findings point out the missing link between IR and PLT activation. In conclusion, PLT and PCT may be related to IR in addition to their identities as hemostasis markers during morbid obesity. Our findings have suggested that DONMA-lab index appears as the best surrogate marker for IR due to its discriminative feature between morbid obesity and MetS.

Keywords: children, insulin resistance, metabolic syndrome, plateletcrit, platelet indices

Procedia PDF Downloads 78
4464 Planning of Construction Material Flow Using Hybrid Simulation Modeling

Authors: A. M. Naraghi, V. Gonzalez, M. O'Sullivan, C. G. Walker, M. Poshdar, F. Ying, M. Abdelmegid

Abstract:

Discrete Event Simulation (DES) and Agent Based Simulation (ABS) are two simulation approaches that have been proposed to support decision-making in the construction industry. Despite the wide use of these simulation approaches in the construction field, their applications for production and material planning is still limited. This is largely due to the dynamic and complex nature of construction material supply chain systems. Moreover, managing the flow of construction material is not well integrated with site logistics in traditional construction planning methods. This paper presents a hybrid of DES and ABS to simulate on-site and off-site material supply processes. DES is applied to determine the best production scenarios with information of on-site production systems, while ABS is used to optimize the supply chain network. A case study of a construction piling project in New Zealand is presented illustrating the potential benefits of using the proposed hybrid simulation model in construction material flow planning. The hybrid model presented can be used to evaluate the impact of different decisions on construction supply chain management.

Keywords: construction supply-chain management, simulation modeling, decision-support tools, hybrid simulation

Procedia PDF Downloads 175
4463 Stress Variation of Underground Building Structure during Top-Down Construction

Authors: Soo-yeon Seo, Seol-ki Kim, Su-jin Jung

Abstract:

In the construction of a building, it is necessary to minimize construction period and secure enough work space for stacking of materials during the construction especially in city area. In this manner, various top-down construction methods have been developed and widely used in Korea. This paper investigates the stress variation of underground structure of a building constructed by using SPS (Strut as Permanent System) known as a top-down method in Korea through an analytical approach. Various types of earth pressure distribution related to ground condition were considered in the structural analysis of an example structure at each step of the excavation. From the analysis, the most high member force acting on beams was found when the ground type was medium sandy soil and a stress concentration was found in corner area.

Keywords: construction of building, top-down construction method, earth pressure distribution, member force, stress concentration

Procedia PDF Downloads 268
4462 A Review of the Major Factors of Cost Overrun in Construction Projects

Authors: Hassan Abdelgadir

Abstract:

Cost overruns have harmed the economies and reputations of several construction companies around the world. Many project management systems have been developed to keep track of a project's budget. However, due to several cost overrun difficulties in the construction industry, cost management is still deemed inadequate. As a result, the goal of this term paper is to identify and group prospective construction project cost overrun reasons based on their origin groups.Basically, all potential cost overrun elements were rigorously checked through 1iterature analysis before being divided into seven (7) groups of originating components, including project, contract, client, contractor, consultant, labor, and external. Each potential factor was completely defined with examples.

Keywords: construction projects, cost overruns, construction company, factors effect costoverruns

Procedia PDF Downloads 39