Search results for: commercially live project
Commenced in January 2007
Frequency: Monthly
Edition: International
Paper Count: 6393

Search results for: commercially live project

6333 Performance Evaluation of Construction Projects by Earned Value Management Method, Using Primavera P6 – A Case Study in Istanbul, Turkey

Authors: Mohammad Lemar Zalmai, Osman Hurol Turkakin, Cemil Akcay, Ekrem Manisali

Abstract:

Most of the construction projects are exposed to time and cost overruns due to various factors and this is a major problem. As a solution to this, the Earned Value Management (EVM) method is considered. EVM is a powerful and well-known method used in monitoring and controlling the project. EVM is a technique that project managers use to track the performance of their project against project baselines. EVM gives an early indication that either project is delayed or not, and the project is either over budget or under budget at any particular day by tracking it. Thus, it helps to improve the management control system of a construction project, to detect and control the problems in potential risk areas and to suggest the importance and purpose of monitoring the construction work. This paper explains the main parameters of the EVM system involved in the calculation of time and cost for construction projects. In this study, the project management software Primavera P6 is used to deals with the project monitoring process of a seven-storeyed (G+6) faculty building whose construction is in progress at Istanbul, Turkey. A comparison between the planned progress of construction activities and actual progress is performed, and the analysis results are interpreted. This case study justifies the benefits of using EVM for project cash flow analysis and forecasting.

Keywords: earned value management (EVM), construction cost management, construction planning, primavera P6, project management, project scheduling

Procedia PDF Downloads 197
6332 The Effect of Critical Activity on Critical Path and Project Duration in Precedence Diagram Method

Authors: J. Nisar, S. Halim

Abstract:

The additional relationships i.e., start-to-start, finish-to-finish, and start-to-finish, between activity in Precedence Diagram Method (PDM) provides a more flexible schedule than traditional Critical Path Method (CPM). But, changing the duration of critical activities in the PDM network will have an anomalous effect on the critical path and the project completion date. In this study, we classified the critical activities in two groups i.e., 1. activity on single critical path and 2. activity on multi-critical paths, and six classes i.e., normal, reverse, neutral, perverse, decrease-reverse and increase-normal, based on their effects on project duration in PDM. Furthermore, we determined the maximum float of time by which the duration each type of critical activities can be changed without effecting the project duration. This study would help the project manager to clearly understand the behavior of each critical activity on critical path, and he/she would be able to change the project duration by shortening or lengthening activities based on project budget and project deadline.

Keywords: construction management, critical path method, project scheduling network, precedence diagram method

Procedia PDF Downloads 188
6331 Project Management Framework and Influencing Factors

Authors: Mehrnoosh Askarizadeh

Abstract:

The increasing variations of the business world correspond with a high diversity of theoretical perspectives used in project management research. This diversity is reflected by a variety of influencing factors, which have been the subject of empirical studies. This article aims to systemize the different streams of research on the basis of a literature review and at developing a research framework influencing factors. We will identify fundamental elements of a project management theory. The framework consists of three dimensions: design, context, and goal. Its purpose is to support the combination of different perspectives and the development of strategies for further research.

Keywords: project, goal, project management, influencing factors

Procedia PDF Downloads 516
6330 Historical Geotechnical Study and Evaluation of Project Progress for the Tafila City Center Development Project

Authors: Mohmd Sarireh

Abstract:

The geotechnical study can be employed successfully to assess and follow the expected development or delay in the project construction. The development project of city center or downtown was taken as a case study for the investigation of the project conditions that might support progress or cause delay. The project was proposed to build 7447 m2 by reinforced concrete mainly to serve and support the services provided to people in Tafila. The project construction had faced challenges and obstacles such as soil collapse because of excavation of the weak soil that found in the project site. In addition, the topography of the project area showed a high slope from South-West to North. The slope through the project footprint reached to 83.3% which is considered very high slope. One year and a half proposed to finish the project construction since the 1st of March 2013 and it was planned to be finished by the 31th of August 2014, but the project needs more than one year and a half as extension according to the consultant engineer. The collecting of data was conducted through the interviews with the engineers and officials, and by analyzing the soil reports and samples taken during design and excavation. The major findings came out to weak and fractured soil and construction waste that were found at project site. Also, soil was considered very fine according to the plasticity index (PI) values, in addition to the high depths required for foundation that contribute to the collapse of soil and the increase of project cost. The current project aims to present how the unseen conditions can delay the project construction and increase the cost of the project that rises to JD8.305 Million.

Keywords: geotechnical, management, progress, risk, soil unseen conditions management

Procedia PDF Downloads 196
6329 Quality Management in Construction Project

Authors: Harsh Panchal, Saurabh Amrutkar

Abstract:

Quality management is an essential part of any project that has directly related to the performance of a project. Quality management is depended on multiple factors at different stages in a project, right from time management to construction logistics. A project is a mixture of various components that include iternary management, health and safety, crew productivity, and many more. From the survey conducted, we came to the conclusion that advancement in technology and indigenous approach to any project will result in maximum quality standards and better project performance. In this paper, we discuss various components of the factors above that lead to compromise the quality of a project and how it can be controlled in order to achieve maximum quality assurance using quality planning and total quality management. The paper also focuses on limitations and problems faced in each factor responsible for quality management and to tackle them using techniques and processes based on activities and identifying the sequence, approaching critical path, and duration. The project management concept that deals with the sequence of scope cost time give us an overview regarding the ongoing quality management, in a nutshell, giving us hints to regulate the current procedure for maximum achievable quality. It also deals with the problems faced by engineers that make the mundane work process slow, reducing the quality outcome drastically.

Keywords: management, performance, project, quality

Procedia PDF Downloads 133
6328 Outcomes of Live Renal Donors with a History of Nephrolithiasis

Authors: Bin Mohamed Ebrahim, Aminesh Singla, Henry Pleass

Abstract:

Aim: There is an ongoing gap in renal transplantation between organs available for donation and recipients on the waiting list. Live donors with pre-existing or a history of renal calculi were thought to be a relative contraindication due to safety concerns for donors. We aim to review current literature assessing outcomes of donors who were found to have a history of renal calculi. Methods: Ovid and Embase were searched between 1960 to 2021 using key terms and Medical Subject Headings (MeSH) – nephrolithiasis, renal stones, renal transplantation and renal graft. Articles included conference proceedings and journal articles and were not excluded based on patient numbers. Studies were excluded if the specific organ was not identified, duplicated reports found or if post-transplant outcomes were not recorded. Outcomes were donor’s renal function or renal calculi recurrence postoperatively. Results: Upon reviewing 344 articles, 14 manuscripts met inclusion criteria. A total of 152 live donors were identified as having pre-existing or with a history of renal calculi at pre-operative workup. The mean stone size was 2.6 4mm (1 – 16) with a mean follow-up duration of 31.8 months (1 – 96). Seven studies had both outcomes. None showed renal complications or stone recurrence. The remaining studies contained 2 out of 84 patients having recurrent nephrolithiasis. Conclusion: Data suggests minimal morbidity involved for live renal donors with a history of nephrolithiasis. This should encourage surgeons to continue recruiting such donors for kidney transplantation.

Keywords: renal transplantation, renal graft, nephrolithiasis, renal calculi, live donor

Procedia PDF Downloads 163
6327 The Urban Project and the Urban Improvement to the Test of the Participation, Case: Project of Modernization of Constantine

Authors: Mouhoubi Nedjima, Sassi Boudemagh Souad

Abstract:

In the framework of the modernization of the city of Constantine, and in order to restore its status as a regional metropolis and introduce it into the network of cities international metropolises, a major urban project was launched: project of modernization and of metropolitanization of the city of Constantine (PMMC). Our research project focuses on the management of the project for the modernization of the city of Constantine (PMMC) focusing on the management of some aspects of the urban project whose participation, with the objective assessment of the managerial approach business. Among the cases revealing taken into account in our research work on the question of participation of actors and their organizations, the operation relating to "the urban improvement in the city of the Brothers FERRAD in the district of Zouaghi". This operation with the objective of improving the living conditions of citizens has faced several challenges and obstacles that have been in major part the factors of its failure. Through this study, we examine the management process and the mode of organization of the actors of the project as well as the level of participation of the citizen to finally propose managerial solutions to conflict situations observed.

Keywords: the urban project, the urban improvement, participation, Constantine

Procedia PDF Downloads 376
6326 Bacteriological Quality of Commercially Prepared Fermented Ogi (AKAMU) Sold in Some Parts of South Eastern Nigeria

Authors: Alloysius C. Ogodo, Ositadinma C. Ugbogu, Uzochukwu G. Ekeleme

Abstract:

Food poisoning and infection by bacteria are of public health significance to both developing and developed countries. Samples of ogi (akamu) prepared from white and yellow variety of maize sold in Uturu and Okigwe were analyzed together with the laboratory prepared ogi for microbial quality using the standard microbiological methods. The analyses showed that both white and yellow variety had total bacterial counts (cfu/g) of 4.0 ×107 and 3.9 x 107 for the laboratory prepared ogi while the commercial ogi had 5.2 x 107 and 4.9 x107, 4.9 x107 and 4.5 x107, 5.4 x107 and 5.0 x107 for Eke-Okigwe, Up-gate and Nkwo-Achara market respectively. The Staphylococcal counts ranged from 2.0 x 102 to 5.0 x102 and 1.0 x 102 to 4.0 x102 for the white and yellow variety from the different markets while Staphylococcal growth was not recorded on the laboratory prepared ogi. The laboratory prepared ogi had no Coliform growth while the commercially prepared ogi had counts of 0.5 x103 to 1.6 x 103 for white variety and 0.3 x 103 to 1.1 x103 for yellow variety respectively. The Lactic acid bacterial count of 3.5x106 and 3.0x106 was recorded for the laboratory ogi while the commercially prepared ogi ranged from 3.2x106 to 4.2x106 (white variety) and 3.0 x106 to 3.9 x106 (yellow). The presence of bacteria isolates from the commercial and laboratory fermented ogi showed that Lactobacillus sp, Leuconostoc sp and Citrobacter sp were present in all the samples, Micrococcus sp and Klebsiella sp were isolated from Eke-Okigwe and ABSU-up-gate markets varieties respectively, E. coli and Staphylococcus sp were present in Eke-Okigwe and Nkwo-Achara markets while Salmonella sp were isolated from the three markets. Hence, there are chances of contracting food borne diseases from commercially prepared ogi. Therefore, there is the need for sanitary measures in the production of fermented cereals so as to minimize the rate of food borne pathogens during processing and storage.

Keywords: ogi, fermentation, bacterial quality, lactic acid bacteria, maize

Procedia PDF Downloads 382
6325 Human-Induced Vibration and Degree of Human Comfortability Analysis of Intersection Pedestrian Bridge

Authors: Yaowen Sheng, Jiuxian Liu

Abstract:

In order to analyze the pedestrian bridge dynamic characteristics and degree of comfortability, the finite element method and live load time history method is used to calculate the dynamic response of the bridge. The example bridge’s dynamic characteristics and degree of human comfortability need to be analyzed. The project background is a three-way intersection. The intersection has three side blocks. An intersection bridge is designed to help people cross the streets. The finite element model of the bridge is established by the Midas/Civil software, and the analysis of the model is done. The strength, stiffness, and stability checks are also completed. Apart from the static analysis of the bridge, the dynamic analysis of the bridge is also completed to avoid the problems resulted from vibrations. The results show that the pedestrian bridge has different dynamic characteristics compared to other normal bridges. The degree of human comfortability satisfies the requirements of Chinese and British specifications. The live load time history method can be used to calculate the dynamic response of the bridge.

Keywords: pedestrian bridge, steel box girder, human-induced vibration, finite element analysis, degree of human comfortability

Procedia PDF Downloads 137
6324 Traditional and Commercially Prepared Medicine: Factors That Affect Preferences among Elderly Adults in Indigenous Community

Authors: Rhaetian Bern D. Azaula

Abstract:

The Philippines' indigenous population, estimated to be 10%-20%, is protected by the Indigenous Peoples Rights Act (IPRA), passed in 1997. However, due to their isolation and limited access to basic services such as health education or needs for health assistance, the law's implementation remains a challenge. As traditional medicine continues to play a significant role in society as the prevention and treatment of some illnesses, it is still customary and widely used to use plants in both traditional and modern ways; however, commercially prepared drugs are progressively advanced as time goes by. Therefore, the purpose of this quantitative study is to investigate the indigenous community at Barangay Magsikap General Nakar, Quezon, and analyze the factors that affect the respondent’s preferences in an indigenous community and reasons for patronizing traditional and commercially prepared medicines and proposes updated health education strategies and instructional materials. Slovin's formula was utilized to reduce the total population representation, followed by stratified sampling for proportional allocation of respondents. The study selects respondents (1) from an Indigenous Community in Barangay Magsikap, General Nakar, Quezon, (2) aged 60 and above, and (3) who are willing to participate. The researcher utilized a checklist-based questionnaire with a Tagalog version, and a Likert Scale was utilized to assess the respondent's choices on selected items. The researcher obtained informed consent from the indigenous community's regional and local office, the chieftain of the tribe, and the respondents, ensuring confidentiality in the collection and retrieval of data. The study revealed that respondents aged 60-69, males with no formal education, are unemployed and have no income source. They prefer traditional medicines due to their affordability, availability, and cultural practices but lack safe preparation, dosages, and contraindications of used medicines. Commercially prepared medications are acknowledged, but respondents are not fully aware of proper administration instructions and dosage labels. Recommendations include disseminating approved herbal medicines and ensuring proper preparation, indications, and contraindications.

Keywords: traditional medicine, commercially prepared medicine, indigenous community, elderly adult

Procedia PDF Downloads 49
6323 Application of Agile Project Management to Construction Projects: Case Study

Authors: Ran Etgar, Sarit Freund

Abstract:

Agile project management (APM) has been developed originally for software development project. Construction projects seemed to be more apt to traditional water-fall approach than to APM. However, Construction project suffers from similar problems that necessitated the invention of APM, mainly the need to break down the project structure to small increments, thus minimizing the needed managerial planning and design. Since the classical structure of APM is not applicable the way it is to construction project, a modified version of APM was devised. This method, nicknamed 'The anchor method', exploits the fundamentals of APM (i.e., iterations, or sprints of short time frames or timeboxes, cross-functional teams, risk reduction and adaptation to changes) and adjust them to the construction world. The projects had to be structured appropriately to proactively and quickly adapt to change. The method aims to encompass human behavior and lean towards adaptivity rather than predictability. To enable smooth application of the method, a special project management software was developed, so as to provide solid administrational help and accurate data. The method is tested on a bunch of construction projects and some key performance indicators (KPIs) are collected. According to preliminary results the method is indeed very advantageous and with proper assimilation can radically change the construction project management paradigm.

Keywords: agile project management, construction, information systems, project management

Procedia PDF Downloads 104
6322 Conceptualising Project Complexity in Ghana’s Construction Industry: A Qualitative Study

Authors: Kwasi Dartey-Baah, Mias De Klerk

Abstract:

Project complexity has been cited as one of the essential areas of project management. It can be observed from environmental, social, technological, and organisational viewpoints, and its handling is critical to project success. Conceptualised in varied industries, this paper seeks to ascertain the meaning and understanding of project complexity within the Ghanaian construction industry based on the three dimensions of complexities (faith, fact, and interaction) using experts' opinions. Taking the form of a focus group discussion, the paper sought to gain an in-depth understanding of project complexity issues in Ghana’s construction industry. The method use obtained data from experts (a purposely selected group) comprising project leaders and project management academics. The findings indicated that the experts broadly agreed with the complexity items but offered varied reasons for their agreement. In the composite assessment of the complexity dimensions of (faith, fact, and interaction), it emerged that there was some agreement with the complexity dimensions of fact and interaction within Ghana’s construction industry. On the other hand, with the dimension for complexity by faith, it was noted that the experts in Ghana’s construction construed complexity by faith, not as the absence of evidence but the evidence that hinges on at least a member of the project team. It is expected that other researches on project complexity will focus on other industries to enhance the knowledge of the same within the field of project management.

Keywords: project complexity, complexity by faith, complexity by fact, complexity by interaction, construction industry, Ghana

Procedia PDF Downloads 137
6321 A Predictive Analytics Approach to Project Management: Reducing Project Failures in Web and Software Development Projects

Authors: Tazeen Fatima

Abstract:

Use of project management in web & software development projects is very significant. It has been observed that even with the application of effective project management, projects usually do not complete their lifecycle and fail. To minimize these failures, key performance indicators have been introduced in previous studies to counter project failures. However, there are always gaps and problems in the KPIs identified. Despite of incessant efforts at technical and managerial levels, projects still fail. There is no substantial approach to identify and avoid these failures in the very beginning of the project lifecycle. In this study, we aim to answer these research problems by analyzing the concept of predictive analytics which is a specialized technology and is very easy to use in this era of computation. Project organizations can use data gathering, compute power, and modern tools to render efficient Predictions. The research aims to identify such a predictive analytics approach. The core objective of the study was to reduce failures and introduce effective implementation of project management principles. Existing predictive analytics methodologies, tools and solution providers were also analyzed. Relevant data was gathered from projects and was analyzed via predictive techniques to make predictions well advance in time to render effective project management in web & software development industry.

Keywords: project management, predictive analytics, predictive analytics methodology, project failures

Procedia PDF Downloads 311
6320 Project Knowledge Harvesting: The Case of Improving Project Performance through Project Knowledge Sharing Framework

Authors: Eng Rima Al-Awadhi, Abdul Jaleel Tharayil

Abstract:

In a project-centric organization like KOC, managing the knowledge of the project is of critical importance to the success of the project and the organization. However, due to the very nature and complexity involved, each project engagement generates a lot of 'learnings' that need to be factored into while new projects are initiated and thus avoid repeating the same mistake. But, many a time these learnings are localized and remains as ‘tacit knowledge’ leading to scope re-work, schedule overrun, adjustment orders, concession requests and claims. While KOC follows an asset based organization structure, with a multi-cultural and multi-ethnic workforce and larger chunk of the work is carried out through complex, long term project engagement, diffusion of ‘learnings’ across assets while dealing with the natural entropy of the organization is of great significance. Considering the relatively higher number of mega projects, it's important that the issues raised during the project life cycle are centrally harvested, analyzed and the ‘learnings’ from these issues are shared, absorbed and are in-turn utilized to enhance and refine the existing process and practices, leading to improve the project performance. One of the many factors contributing to the successful completion of a project on time is the reduction in the number of variations or concessions triggered during the project life cycle. The project process integrated knowledge sharing framework discusses the knowledge harvesting methodology adopted, the challenges faced, learnings acquired and its impact on project performance. The framework facilitates the proactive identification of issues that may have an impact on the overall quality of the project and improve performance.

Keywords: knowledge harvesting, project integrated knowledge sharing, performance improvement, knowledge management, lessons learn

Procedia PDF Downloads 364
6319 Ranking the Factors That Influence the Construction Project Success: The Jordanian Perspective

Authors: Ghanim A. Bekr

Abstract:

Project success is what must be done for the project to be acceptable to the client, stakeholders and end-users who will be affected by the project. The study of project success and the critical success factors (CSFs) are the means adopted to improve the effectiveness of project. This research is conducted to make an attempt to identify which variables influence the success of project implementation. This study has selected, through an extensive literature review and interviews, (83) factors categorized in (7) groups that the questionnaire respondents were asked to score. The responses from 66 professionals with an average of 15 years of experience in different types of construction projects in Jordan were collected and analyzed using SPSS and most important factors for success for various success criteria are presented depending on the relative importance index to rank the categories. The research revealed the significant groups of factors are: Client related factors, Contractor’s related factors, Project Manager (PM) related factors, and Project management related factors. In addition the top ten sub factors are: Assertion of the client towards short time of the project, availability of skilled labor, Assertion of the client towards high level of the quality, capability of the client in taking risk, previous experience of the PM in similar projects, previous experience of the contractor in similar projects, decision making by the client/ the client’s representative at the right time, assertion of client towards low cost of project, experience in project management in previous projects, and flow of the information among parties. The results would be helpful to construction project professionals in taking proactive measures for successful completion of construction projects in Jordan.

Keywords: construction projects, critical success factors, Jordan, project success

Procedia PDF Downloads 132
6318 Effect of Project Control Practices on the Performance of Building Construction Companies in Uganda: A Case Study of Kampala City

Authors: Tukundane Hillary

Abstract:

This research paper analytically evaluates the project control practice levels used by the building construction companies within Kampala, Uganda. The research also assesses the outcome of project control practices on the productivity of the companies. The research was performed to ascertain the current control practices among 160 respondents from various construction companies registered with the Uganda Registration Services Bureau. This research used amalgamation from multiple literature to obtain the variables. The research adopts 34 standard control practices from four vital project control duties: planning, monitoring, analyzing, and reporting. These project control tasks were organized using mean response ratings grounded on their relevance to the construction companies. Results showed that evaluating performance with the use of curves (4.32), timely access to information and encouragement (4.55), report representation using quantitative tools 4.75, and cost value comparison application during analysis (4.76) were rated least among the control practices. On the other hand, the top project control practices included formulation of the project schedule (8.88), Project feasibility validation (8.86), Budgeting for each activity (8.84), Key project route definition (8.81), Team awareness of the budget (8.77), Setting realistic targets for projects (8.50) and Consultation from subcontractors (8.74). From the results obtained by the sample respondents specified, it can be concluded that planning is the most vital project control task practiced in the building construction industry in Uganda. In addition, this research ascertained a substantial relationship between project control practices and the performance of building construction companies. Accordingly, this research recommends that project control practices be effectively observed by both contracting and consulting companies to enhance their overall performance and governance.

Keywords: cost value, project control, cost control, time control, project performance, control practices

Procedia PDF Downloads 38
6317 A Principal-Agent Model for Sharing Mechanism in Integrated Project Delivery Context

Authors: Shan Li, Qiuwen Ma

Abstract:

Integrated project delivery (IPD) is a project delivery method distinguished by a shared risk/rewards mechanism and multiparty agreement. IPD has drawn increasingly attention from construction industry because of its efficiency of solving adversarial problems and reliability to deliver high-performing buildings. However, some evidence showed that some project participants obtained less profit from IPD projects than the typical projects. They attributed it to the unfair IPD sharing mechanism, which resulted in additional time and cost of negotiation on the sharing fractions among project participants. The study is aimed to investigate the reward distribution by constructing a principal-agent model. Based on cooperative game theory, it is examined how to distribute the shared project rewards between client and non-client parties, and identify the sharing fractions among non-client parties. It is found that at least half of the project savings should be allocated to the non-client parties to motivate them to create more project value. Second, the client should raise his sharing fractions when the integration among project participants is efficient. In addition, the client should allocate higher sharing fractions to the non-client party who is more able. This study can help the IPD project participants make fair and motivated sharing mechanisms.

Keywords: cooperative game theory, IPD, principal agent model, sharing mechanism

Procedia PDF Downloads 268
6316 Effects of Live Yeast Supplementation to Reduce Oxidative Stress and Increase Lactation Performance of Dairy Cattle during the Summer Season

Authors: Ahmad Nawid Mirzad, Akira Goto, Takuto Endo, Hitoshi Ano, Hiromu Katamoto, Takenori Yamauchi

Abstract:

The objective of this study was to evaluate the effects of live yeast supplementation on oxidative stress biomarker and antioxidant vitamin levels as well as lactation performance in Holstein Friesian cows during the summer season in Fukuoka prefecture. Sixteen lactating cows weighing 707.50 ± 13.09 kg (Mean ± SE) were used and randomly assigned to either supplemented (n = 8) or control (n = 8) group. The cows in supplemented group were administered with live yeast product at 10 g/d per cow from middle of July to middle of September for eight weeks. In treatment group, serum levels of derivatives of reactive oxygen metabolites (d-ROMs) were lower at week six. In addition, serum levels of glucose and retinol were higher at week eight and those of α-tocopherol were higher at week 2 in treatment group. During study period daily average milk yield decreased in both groups. Daily average milk yield 63 days after the onset of supplementation in treatment and control groups were 23.5 and 22.2 kg, respectively. The reduction rate of milk yield in treatment group tended to be lower (17.6 vs. 20.0%). These results suggest that live yeast supplementation may reduce oxidative stress and improve energy metabolism in lactating dairy cows during the summer season.

Keywords: cow, live yeast, milk, oxidative stress, summer season

Procedia PDF Downloads 137
6315 Managing Multiple Change Projects in Supply Chains: A Case Study of a Moroccan Multi-Technical Services Company

Authors: Abdelouahab Errida, Bouchra Lotfi, Elalami Semma

Abstract:

In this paper, we try to address the topic of multiple change management by adopting an engineered research methodology, conducted within a Moroccan company during its implementation of several change projects that aim at improving its supply chain management performance. Firstly, we present the key concepts related to our research, namely change management, multiproject management and supply chain management. Then, we try to assess how the change management and multi-project management are applied in this company. Finally, we try to propose an approach that will help managers in dealing with multiple change projects. This approach proposes to integrate change management, project management and multi-project management for managing change projects according to three organizational levels: executive level, project portfolio level and change project level.

Keywords: change management, multi-project management, project management, change portfolio, supply chain management,

Procedia PDF Downloads 198
6314 Experimental Study on Mechanical Properties of Commercially Pure Copper Processed by Severe Plastic Deformation Technique-Equal Channel Angular Extrusion

Authors: Krishnaiah Arkanti, Ramulu Malothu

Abstract:

The experiments have been conducted to study the mechanical properties of commercially pure copper processing at room temperature by severe plastic deformation using equal channel angular extrusion (ECAE) through a die of 90oangle up to 3 passes by route BC i.e. rotating the sample in the same direction by 90o after each pass. ECAE is used to produce from existing coarse grains to ultra-fine, equiaxed grains structure with high angle grain boundaries in submicron level by introducing a large amount of shear strain in the presence of hydrostatic pressure into the material without changing billet shape or dimension. Mechanical testing plays an important role in evaluating fundamental properties of engineering materials as well as in developing new materials and in controlling the quality of materials for use in design and construction. Yield stress, ultimate tensile stress and ductility are structure sensitive properties and vary with the structure of the material. Microhardness and tensile tests were carried out to evaluate the hardness, strength and ductility of the ECAE processed materials. The results reveal that the strength and hardness of commercially pure copper samples improved significantly without losing much ductility after each pass.

Keywords: equal channel angular extrusion, severe plastic deformation, copper, mechanical properties

Procedia PDF Downloads 157
6313 Nutrition Bio-Shield Superfood: Healthy and Live Herbal Supplement for Immune System Enhancement

Authors: Azam Bayat, Aref Khalkhali, Ali Reza Mahjoub

Abstract:

Healthy and viable herbal supplement were prepared from wheat by a green route. This organic biomaterial was named Nutrition Bio-shield Superfood (NBS). The NBS supplement had various vitamins, macro and micro molecules, and ingredients. In this study, 20 small Balb/C labile specimens were used in a weighing 30 ± 5 range. The samples were randomly divided into different groups, then the groups were divided into 5 groups. According to the results of this study, the mean number of white blood cells and neutrophil percentage in the experimental group receiving healthy and live dietary supplement showed a significant increase at the 5% probability level in all three groups received 50, 100 and 150 mg/ kg body weight of the mouse compared to the control group. In general, the dietary supplement increases the level of immunity.

Keywords: healthy and live herbal supplement, biomaterial, immune system, enhancement

Procedia PDF Downloads 120
6312 Overcoming the Impacts of Covid-19 Outbreak Using Value Integrated Project Delivery Model

Authors: G. Ramya

Abstract:

Value engineering is a systematic approach, widely used to optimize the design or process or product in the designing stage. It used to achieve the client's obligation by increasing the functionality and attain the targeted cost in the cost planning. Value engineering effectiveness and benefits decrease along with the progress of the project since the change in the scope of the work and design will account for more cost all along the lifecycle of the project. Integrating the value engineering with other project management activities will promote cost minimization, client satisfaction, and ensure early completion of the project in time. Previous research studies suggested that value engineering can integrate with other project delivery activities, but research studies unable to frame a model that collaborates the project management activities with the job plan of value engineering approach. I analyzed various project management activities and their synergy between each other. The project management activities and processes like a)risk analysis b)lifecycle cost analysis c)lean construction d)facility management e)Building information modelling f)Contract administration, collaborated, and project delivery model planned along with the RIBA plan of work. The key outcome of the research is a value-driven project delivery model, which will succeed in dealing with the economic impact, constraints and conflicts arise due to the COVID-19 outbreak in the Indian construction sector. Benefits associated with the structured framework is construction project delivery that ensures early contractor involvement, mutual risk sharing, and reviving the project with a cost overrun and delay back on track ,are discussed. Keywords: Value-driven project delivery model, Integration, RIBA plan of work Themes: Design Economics

Keywords: value-driven project delivery model, Integration, RIBA

Procedia PDF Downloads 99
6311 Project and Experiment-Based Fluid Dynamics Education

Authors: Etsuo Morishita

Abstract:

This paper presents the project and experiment-based fluid dynamics education in Meisei University, a private institution in Tokyo, Japan. We pay attention not only to the basic engineering courses but also to the practical aspect of engineering experience. So, we prepare courses called the Projects from I to VI. The Projects I and II are designed for the first year, III and IV are designated for the second year, V and VI are prepared for the third year, respectively. Each supervisor is responsible for two of these projects every year. When students take the Project V and VI at the third year, we automatically assume that these students will join the lab of the project for the graduation thesis. We would like to show our experience in the Project I in the summer term, 2016. In this project, we introduce a traction flight vehicle called Cat Flyer. This is a kind of a kite towed by a car for example. This is very similar to parasailing, but flight is possible even on the roads. Experiments in mechanical engineering education are also very important, and we would like to explain our course on centrifugal pump, venture, and orifice. Although these are described in detail in the text books of fluid dynamics, it is still crucial to have practical experiments as a student.

Keywords: aerodynamics, experiment, fluid dynamics, project

Procedia PDF Downloads 239
6310 The Need for Implementing Building Information Modelling (BIM) and Integrated Project Delivery (IPD) in the Construction Project: A Case Study in UAE

Authors: C. W. F. Che Wan Putra, M. Alshawi, M. S. Al Ahbabi, M. Jabakhanji

Abstract:

Much of the waste that is generated throughout the life-cycle of a building is mainly related to project stakeholders not having access to information that others have created. This results in waste and high costs. Over the past decade, however, the industry reacted to these challenges by adopting effective procurement approaches, such as partnering and design and build, to improve collaboration and communication among projects’ stakeholders. Most recently, there is a focus on creating and reusing digital project information of stakeholders throughout the life-cycle to facilitate the exchange of information among partners. This shift is based around BIM (Building Information Modelling) and collaborative environment (IPD). The power of collaborative BIM goes beyond improving efficiency. Sustainability, perhaps the most important challenge for the design and construction community, is at the intersection of BIM and collaborative project delivery, drawing strength from both. Due to these benefits, a research study has been carried out to investigate the need of BIM and IPD, on a large scale construction project which is procured on a traditional approach, i.e. design-bid-build. A qualitative research work including a semi-structured interview with project partners was conducted on a typical project in the UAE, whereby the selected project suffered from severe delays and cost overrun. This paper aims to bring about clear evidence to what most likely to happen to a typical construction project in spite of employing very good consultants, project manager and contractors and how these problems could have been avoided if BIM and IPD were deployed.

Keywords: building information modelling (BIM), integrated project delivery (IPD), collaborative environment, case study

Procedia PDF Downloads 378
6309 An Improved GA to Address Integrated Formulation of Project Scheduling and Material Ordering with Discount Options

Authors: Babak H. Tabrizi, Seyed Farid Ghaderi

Abstract:

Concurrent planning of the resource constraint project scheduling and material ordering problems have received significant attention within the last decades. Hence, the issue has been investigated here with the aim to minimize total project costs. Furthermore, the presented model considers different discount options in order to approach the real world conditions. The incorporated alternatives consist of all-unit and incremental discount strategies. On the other hand, a modified version of the genetic algorithm is applied in order to solve the model for larger sizes, in particular. Finally, the applicability and efficiency of the given model is tested by different numerical instances.

Keywords: genetic algorithm, material ordering, project management, project scheduling

Procedia PDF Downloads 277
6308 Feasibility Study of Potential and Economic of Rice Straw VSPP Power Plant in Thailand

Authors: Sansanee Sansiribhan, Anusorn Rattanathanaophat, Chirapan Nuengchaknin

Abstract:

The potential feasibility of a 9.5 MWe capacity rice straw power plant project in Thailand was studied by evaluating the rice straw resource. The result showed that Thailand had a high rice straw biomass potential at the provincial level, especially, the provinces in the central, northeastern and western Thailand, which could feasibly develop plants. The economic feasibility of project was also investigated. The financial feasibility is also evaluated based on two important factors in the project, i.e., NPV ≥ 0 and IRR ≥ 11%. It was found that the rice straw power plant project at 9.5 MWe was financially feasible with the cost of fuel in the range of 30.6-47.7 USD/t.

Keywords: power plant, project feasibility, rice straw, Thailand

Procedia PDF Downloads 314
6307 CDIO-Based Teaching Reform for Software Project Management Course

Authors: Liping Li, Wenan Tan, Na Wang

Abstract:

With the rapid development of information technology, project management has gained more and more attention recently. Based on CDIO, this paper proposes some teaching reform ideas for software project management curriculum. We first change from Teacher-centered classroom to Student-centered and adopt project-driven, scenario animation show, teaching rhythms, case study and team work practice to improve students' learning enthusiasm. Results showed these attempts have been well received and very effective; as well, students prefer to learn with this curriculum more than before the reform.

Keywords: CDIO, teaching reform, engineering education, project-driven, scenario animation simulation

Procedia PDF Downloads 407
6306 The Artificial Intelligence (AI) Impact on Project Management: A Destructive or Transformative Agent

Authors: Kwame Amoah

Abstract:

Artificial intelligence (AI) has the prospect of transforming project management, significantly improving efficiency and accuracy. By automating specific tasks with defined guidelines, AI can assist project managers in making better decisions and allocating resources efficiently, with possible risk mitigation. This study explores how AI is already impacting project management and likely future AI's impact on the field. The AI's reaction has been a divided opinion; while others picture it as a destroyer of jobs, some welcome it as an innovation advocate. Both sides agree that AI will be disruptive and revolutionize PM's functions. If current research is to go by, AI or some form will replace one-third of all learning graduate PM jobs by as early as 2030. A recent survey indicates AI spending will reach $97.9 billion by the end of 2023. Considering such a profound impact, the project management profession will also see a paradigm shift driven by AI. The study examines what the project management profession will look like in the next 5-10 years after this technological disruption. The research methods incorporate existing literature, develop trend analysis, and conduct structured interviews with project management stakeholders from North America to gauge the trend. PM professionals can harness the power of AI, ensuring a smooth transition and positive outcomes. AI adoption will maximize benefits, minimize adverse consequences, and uphold ethical standards, leading to improved project performance.

Keywords: project management, disruptive teacnologies, project management function, AL applications, artificial intelligence

Procedia PDF Downloads 53
6305 Proposal Evaluation of Critical Success Factors (CSF) in Lean Manufacturing Projects

Authors: Guilherme Gorgulho, Carlos Roberto Camello Lima

Abstract:

Critical success factors (CSF) are used to design the practice of project management that can lead directly or indirectly to the success of the project. This management includes many elements that have to be synchronized in order to ensure the project on-time delivery, quality and the lowest possible cost. The objective of this work is to develop a proposal for evaluation of the FCS in lean manufacturing projects, and apply the evaluation in a pilot project. The results show that the use of continuous improvement programs in organizations brings benefits as the process cost reduction and improve productivity.

Keywords: continuous improvement, critical success factors (csf), lean thinking, project management

Procedia PDF Downloads 332
6304 Multi-Objective Multi-Mode Resource-Constrained Project Scheduling Problem by Preemptive Fuzzy Goal Programming

Authors: Busaba Phurksaphanrat

Abstract:

This research proposes a pre-emptive fuzzy goal programming model for multi-objective multi-mode resource constrained project scheduling problem. The objectives of the problem are minimization of the total time and the total cost of the project. Objective in a multi-mode resource-constrained project scheduling problem is often a minimization of make-span. However, both time and cost should be considered at the same time with different level of important priorities. Moreover, all elements of cost functions in a project are not included in the conventional cost objective function. Incomplete total project cost causes an error in finding the project scheduling time. In this research, pre-emptive fuzzy goal programming is presented to solve the multi-objective multi-mode resource constrained project scheduling problem. It can find the compromise solution of the problem. Moreover, it is also flexible in adjusting to find a variety of alternative solutions.

Keywords: multi-mode resource constrained project scheduling problem, fuzzy set, goal programming, pre-emptive fuzzy goal programming

Procedia PDF Downloads 406