5262 Non-Chronological Approach in Crane Girder and Composite Steel Beam Installation: Case Study

Authors: Govindaraj Ramanathan

Abstract:

The time delay and the structural stability are major issues in big size projects due to several factors. Improper planning and poor coordination lead to delay in construction, which sometimes result in reworking or rebuilding. This definitely increases the cost and time of project. This situation stresses the structural engineers to plan out of the limits of contemporary technology utilizing non-chronological approach with creative ideas. One of the strategies to solve this issue is through structural integrity solutions in a cost-effective way. We have faced several problems in a project worth 470 million USD, and one such issue is crane girder installation with composite steel beams. We have applied structural integrity approach with the proper and revised planning schedule to solve the problem efficiently with minimal expenses.

Keywords: construction management, delay, non-chronological approach, composite beam, structural integrity

Procedia PDF Downloads 202
5261 The Effect of Engineering Construction in Online Consultancy

Authors: Mariam Wagih Nagib Eskandar

Abstract:

The engineering design process is the activities formulation, to help an engineer raising a plan with a specified goal and performance. The engineering design process is a multi-stage course of action including the conceptualization, research, feasibility studies, establishment of design parameters, preliminary and finally the detailed design. It is a progression from the abstract to the concrete; starting with probably abstract ideas about need, and thereafter elaborating detailed specifications of the object that would satisfy the needs, identified. Engineering design issues, problems, and solutions are discussed in this paper using qualitative approach from an information structure perspective. The objective is to identify the problems, to analyze them and propose solutions by integrating; innovation, practical experience, time and resource management, communications skills, isolating the problem in coordination with all stakeholders. Consequently, this would be beneficial for the engineering community to improve the Engineering design practices.

Keywords: education, engineering, math, performanceengineering design, architectural engineering, team-based learning, construction safetyrequirement engineering, models, practices, organizations

Procedia PDF Downloads 35
5260 Structural Rehabilitation, Retrofitting and Strengthening of Reinforced Concrete Structures

Authors: Manish Kumar

Abstract:

Reinforced cement concrete is getting extensively used for construction of different type of structures for the last one century. During this period, we have constructed many structures like buildings, bridges, industrial structures, pavement, water tanks etc. using this construction material. These structures have been created with huge investment of resources. It is essential to maintain those structures in functional condition. Since deterioration in RCC Structures is a common and natural phenomenon it is required to have a detailed plan, methodology for structural repair and rehabilitation shall be in place for dealing such issues. It is important to know exact reason of distress, type of distress and correct method of repair concrete structures. The different methods of repair are described in paper according to distress category which can be refereed for repair. Major finding of the study is that to protect our structure we need to have maintenance frequency and correct material to be chosen for repair. Also workmanship during repair needs to be taken utmost care for quality repair.

Keywords: deterioration, functional condition, reinforced cement concrete, resources

Procedia PDF Downloads 223
5259 A Study of Carbon Emissions during Building Construction

Authors: Jonggeon Lee, Sungho Tae, Sungjoon Suk, Keunhyeok Yang, George Ford, Michael E. Smith, Omidreza Shoghli

Abstract:

In recent years, research to reduce carbon emissions through quantitative assessment of building life cycle carbon emissions has been performed as it relates to the construction industry. However, most research efforts related to building carbon emissions assessment have been focused on evaluation during the operational phase of a building’s life span. Few comprehensive studies of the carbon emissions during a building’s construction phase have been performed. The purpose of this study is to propose an assessment method that quantitatively evaluates the carbon emissions of buildings during the construction phase. The study analysed the amount of carbon emissions produced by 17 construction trades, and selected four construction trades that result in high levels of carbon emissions: reinforced concrete work; sheathing work; foundation work; and form work. Building materials, and construction and transport equipment used for the selected construction trades were identified, and carbon emissions produced by the identified materials and equipment were calculated for these four construction trades. The energy consumption of construction and transport equipment was calculated by analysing fuel efficiency and equipment productivity rates. The combination of the expected levels of carbon emissions associated with the utilization of building materials and construction equipment provides means for estimating the quantity of carbon emissions related to the construction phase of a building’s life cycle. The proposed carbon emissions assessment method was validated by case studies.

Keywords: building construction phase, carbon emissions assessment, building life cycle

Procedia PDF Downloads 716
5258 Comparative Life Cycle Analysis of Selected Modular Timber Construction and Assembly Typologies

Authors: Benjamin Goldsmith, Felix Heisel

Abstract:

The building industry must reduce its emissions in order to meet 2030 neutrality targets, and modular and/or offsite construction is seen as an alternative to conventional construction methods which could help achieve this goal. Modular construction has previously been shown to be less wasteful and has a lower global warming potential (GWP). While many studies have been conducted investigating the life cycle impacts of modular and conventional construction, few studies have compared different types of modular assembly and construction in order to determine which offer the greatest environmental benefits over their whole life cycle. This study seeks to investigate three different modular construction types -infill frame, core, and podium- in order to determine environmental impacts such as GWP as well as circularity indicators. The study will focus on the emissions of the production, construction, and end-of-life phases. The circularity of the various approaches will be taken into consideration in order to acknowledge the potential benefits of the ability to reuse and/or reclaim materials, products, and assemblies. The study will conduct hypothetical case studies for the three different modular construction types, and in doing so, control the parameters of location, climate, program, and client. By looking in-depth at the GWP of the beginning and end phases of various simulated modular buildings, it will be possible to make suggestions on which type of construction has the lowest global warming potential.

Keywords: modular construction, offsite construction, life cycle analysis, global warming potential, environmental impact, circular economy

Procedia PDF Downloads 132
5257 Anti-Corruption, an Important Challenge for the Construction Industry!

Authors: Ahmed Stifi, Sascha Gentes, Fritz Gehbauer

Abstract:

The construction industry is perhaps one of the oldest industry of the world. The ancient monuments like the egyptian pyramids, the temples of Greeks and Romans like Parthenon and Pantheon, the robust bridges, old Roman theatres, the citadels and many more are the best testament to that. The industry also has a symbiotic relationship with other . Some of the heavy engineering industry provide construction machineries, chemical industry develop innovative construction materials, finance sector provides fund solutions for complex construction projects and many more. Construction Industry is not only mammoth but also very complex in nature. Because of the complexity, construction industry is prone to various tribulations which may have the propensity to hamper its growth. The comparitive study of this industry with other depicts that it is associated with a state of tardiness and delay especially when we focus on the managerial aspects and the study of triple constraint (time, cost and scope). While some institutes says the complexity associated with it as a major reason, others like lean construction, refers to the wastes produced across the construction process as the prime reason. This paper introduces corruption as one of the prime factors for such delays.To support this many international reports and studies are available depicting that construction industry is one of the most corrupt sectors worldwide, and the corruption can take place throught the project cycle comprising project selection, planning, design, funding, pre-qualification, tendering, execution, operation and maintenance, and even through the reconstrction phase. It also happens in many forms such as bribe, fraud, extortion, collusion, embezzlement and conflict of interest and the self-sufficient. As a solution to cope the corruption in construction industry, the paper introduces the integrity as a key factor and build a new integrity framework to develop and implement an integrity management system for construction companies and construction projects.

Keywords: corruption, construction industry, integrity, lean construction

Procedia PDF Downloads 345
5256 Beyond Possibilities: Re-Reading Republican Ankara

Authors: Zelal Çınar

Abstract:

This paper aims to expose the effects of the ideological program of Turkish Republic on city planning, through the first plan of Ankara. As the new capital, Ankara was planned to be the ‘showcase’ of modern Turkey. It was to represent all new ideologies and the country’s cultural similarities with the west. At the same time it was to underline the national identity and independence of Turkish republic. To this end, a new plan for the capital was designed by German city planner Carl Christopher Lörcher. Diametrically opposed with the existing fabric of the city, this plan was built on the basis of papers and plans, on ideological aims. On the contrary, this paper argues that the city is a machine of possibilities, rather than a clear, materialized system.

Keywords: architecture, ideology, modernization, urban planning

Procedia PDF Downloads 244
5255 Improving the Constructability of Highway Design Plans

Authors: R. Edward Minchin Jr.

Abstract:

The U.S. Federal Highway Administration (FHWA) Every Day Counts Program (EDC) has resulted in state DOTs putting evermore emphasis on speeding up the delivery of highway and bridge construction projects for use by the driving public. This has resulted in an increase in the use of alternative construction delivery systems such as design-build (D-B), construction manager at-risk (CMR) or construction manager/general contractor (CM/GC), and adding alternative technical concepts (ATCs) to traditional design-bid-build (DBB) contracts. ATCs have exhibited great potential for delivering substantial benefits like cost savings, increased constructability, and quicker project delivery. Previous research has found that knowledge of project constructability was lacking in state Department of Transportation (DOT) planning, programming, and environmental staffs. Many agencies have therefore relied on a set of ‘acceptable’ design solutions over the years of working with their local resource agencies. The result is that the permitting process for several government agencies has become increasingly restrictive with the result that the DOTs and their industry partners lose the ability to innovate after a permit is approved. The intent of this paper is to report on the research team’s progress in this ongoing effort furnish the United States government with a uniform set of guidelines for the application of constructability reviews during all phases of project development and delivery. The research uses surveys and interviews to determine which states have implemented formal programs to ensure that the constructor is furnished with a set of contract documents that affords said constructor with the best possible opportunity to successfully construct the project with the highest quality standards, within the contract duration and without exceeding the construction budget. Once these states are identified, workshops are held all over the nation, resulting in the team learning the best current practices and giving the team the ability to recommend new practices that will improve the process. The plan is for the FHWA to encourage or require state DOTs to use these practices on all federally funded highway and bridge construction projects. The project deliverable is a Guidebook for FHWA to use in disseminating the recommended practices to the states.

Keywords: alternative construction delivery, alternative technical concepts, constructability, construction design plans

Procedia PDF Downloads 174
5254 Cost Overrun Causes in Public Construction Projects in Saudi Arabia

Authors: Ibrahim Mahamid, A. Al-Ghonamy, M. Aichouni

Abstract:

This study is conducted to identify causes of cost deviations in public construction projects in Saudi Arabia from contractors’ perspective. 41 factors that might affect cost estimating accuracy were identified through literature review and discussion with some construction experts. The factors were tabulated in a questionnaire form and a field survey included 51 contractors from the Northern Province of Saudi Arabia was performed. The results show that the top five important causes are: wrong estimation method, long period between design and time of implementation, cost of labor, cost of machinary and absence of construction-cost data.

Keywords: cost deviation, public construction, cost estimating, Saudi Arabia, contractors

Procedia PDF Downloads 433
5253 Evaluation of Traditional Methods in Construction and Their Effects on Reinforced-Concrete Buildings Behavior

Authors: E. H. N. Gashti, M. Zarrini, M. Irannezhad, J. R. Langroudi

Abstract:

Using ETABS software, this study analyzed 23 buildings to evaluate effects of mistakes during construction phase on buildings structural behavior. For modelling, two different loadings were assumed: 1) design loading and 2) loading due to the effects of mistakes in construction phase. Research results determined that considering traditional construction methods for buildings resulted in a significant increase in dead loads and consequently intensified the displacements and base-shears of buildings under seismic loads.

Keywords: reinforced-concrete buildings, construction mistakes, base-shear, displacements, failure

Procedia PDF Downloads 239
5252 Development of Intelligent Construction Management System Using Web-Camera Image and 3D Object Image

Authors: Hyeon-Seung Kim, Bit-Na Cho, Tae-Woon Jeong, Soo-Young Yoon, Leen-Seok Kang

Abstract:

Recently, a construction project has been large in the size and complicated in the site work. The web-cameras are used to manage the construction site of such a large construction project. They can be used for monitoring the construction schedule as compared to the actual work image of the planned work schedule. Specially, because the 4D CAD system that the construction appearance is continually simulated in a 3D CAD object by work schedule is widely applied to the construction project, the comparison system between the real image of actual work appearance by web-camera and the simulated image of planned work appearance by 3D CAD object can be an intelligent construction schedule management system (ICON). The delayed activities comparing with the planned schedule can be simulated by red color in the ICON as a virtual reality object. This study developed the ICON and it was verified in a real bridge construction project in Korea. To verify the developed system, a web-camera was installed and operated in a case project for a month. Because the angle and zooming of the web-camera can be operated by Internet, a project manager can easily monitor and assume the corrective action.

Keywords: 4D CAD, web-camera, ICON (intelligent construction schedule management system), 3D object image

Procedia PDF Downloads 481
5251 An Evaluation of the Effectiveness of Health and Safety Induction Practices in the Zambian Construction Industry

Authors: Josephine Mutwale-Ziko, Nonde Lushinga, Inonge Akakandelwa

Abstract:

The study discusses the effectiveness of health and safety induction practices on construction sites against the background of the Zambian construction industry experience. The research design included the literature review of relevant literature. Questionnaires and interviews were administered to regulatory bodies, health, and safety personnel. Observation was also employed on construction sites to assess the health and safety practices being used. Health and safety in the construction industry are not something to be ignored or overlooked. The construction industry needs to take heed of the serious consequences of inadequate health and safety induction practices. The implications of inadequate health and safety induction procedures included among others threats to profitability, corporate social responsibility and increased turnover of the workforce leading to poor productivity. Adequate health and safety practices can improve the health and wellbeing of employees, reduce financial implications on firms and encourage productivity on construction sites. Despite this, accidents are still prevalent on construction sites in Zambia. The overall result of this research denotes that the implementation of health and safety induction practices is inadequate, as indicated by the negligent and non-adherent attitude to health and safety induction aspects on the sites by most stakeholders on construction sites. Therefore, health and safety induction practices are ineffective as preventive measures for reduction of accidents on construction sites in Zambia.

Keywords: accidents, health and safety, inadequate, induction

Procedia PDF Downloads 399
5250 Familiarity With Civil Engineering and Types of Construction and Its Methods

Authors: Mokhtar Nikgoo

Abstract:

Civil engineering is one of the disciplines that shows the application of science in creating construction and civil engineering. That is, everything that returns to the population of a country, such as dams, airports, roads, bridges, towers, tunnels, telecommunication towers, buildings resistant to earthquakes, floods and fires, power plants and light, cheap and quality materials for construction. And the construction is included in the scope of work of the civil engineer. Civil engineering covers a wide range of tasks. That is, for the construction of buildings, bridges, towers, tunnels, roads, silos, or sewage networks, an efficient civil engineer is needed at the beginning, in addition to complying with the technical and operational aspects, he also works economically. Because being economical is a principle in civil engineering. Is. This field at the undergraduate level has three majors: civil-building, civil-mapping and civil-water.

Keywords: civil engineering, construction, surveying, mapping, pile

Procedia PDF Downloads 46
5249 Assessment of Health and Safety Item on Construction Site in Ondo State

Authors: Ikumapayi Catherine Mayowa

Abstract:

The well-being of humans on a construction site is critical; abundant manpower had been lost through accidents which kill or make workers physically unfit to carry out construction activities, these, in turn, have multiple effects on the whole economy. Thus, it is necessary to put all safety items and regulations in place before construction activities can commence. This study was carried out in the Ondo state of Nigeria to investigate and analyze the state of health and safety of construction workers in the state. The study was done using first-hand observations, 50 construction project sites were visited in ten major towns of Ondo state, questionnaires were distributed, and the results were analyzed. The result shows that construction workers are being exposed to many construction site hazards due to lack of inadequate safety programs and lack of appropriate safety equipment for workers on site. From the data gotten from each site visited and the statistical analysis, it can be concluded that occurrences of an accident on construction sites depend significantly on the available safety facilities on the sites. The result of the regression statistics shows that the dependence of the frequency of occurrence of an accident on the availability of safety items on the site is 0.0362 which is less than 0.05 maximum significant level allowed. Therefore, a vital way of sustaining our building strategy is given a detail attention to the provision of adequate health and safety items on construction sites which will reduce the occurrence of accident, loss of manpower and death of skilled workers.

Keywords: construction sites, health, safety, welfare

Procedia PDF Downloads 299
5248 Appraisal of Incentive Schemes for Employees: A Case of Construction Smes

Authors: B. M. Arthur-Aidoo, C. O. Aigbavboa, W. D. Thwala

Abstract:

The performance of construction employees cannot be underestimated if the success of construction projects are to be achieved. This is because the construction industry has been characterised as labour oriented sector, which most of its activities being executed by labour. In the construction sector, employees are driven by incentive schemes which perform encourage and motivate workers for higher efficiency and higher output. The construction sector, however, depends mainly on its labour. In view of the sector's high dependency on its employees, that there must be a significant incentive scheme which must be established to act as a stimulus to drive high performance from employees among the various known incentive packages. This study, therefore, seeks to appraise the incentive packages adopted by construction SMEs. To establish reliable findings that will contribute to knowledge, the study utilised an exploratory approach via semi-structured interviews among sampled construction professionals with the requisite expertise on employees' incentive schemes. The study further established that although incentive schemes are classified in various ways and mediums that act as stimuli to encourage high performance among employees, some are more influential and impacts performance than others. Additionally, the study concludes that medical allowance, holiday with pay, free working tools, and training for employees were ranked the most influential incentives that promote high outputs by workers within the construction SME sector.

Keywords: appraisal, construction, employees, incentive, small and medium-sized enterprises, SMEs

Procedia PDF Downloads 101
5247 Understanding Complexity at Pre-Construction Stage in Project Planning of Construction Projects

Authors: Mehran Barani Shikhrobat, Roger Flanagan

Abstract:

The construction planning and scheduling based on using the current tools and techniques is resulted deterministic in nature (Gantt chart, CPM) or applying a very little probability of completion (PERT) for each task. However, every project embodies assumptions and influences and should start with a complete set of clearly defined goals and constraints that remain constant throughout the duration of the project. Construction planners continue to apply the traditional methods and tools of “hard” project management that were developed for “ideal projects,” neglecting the potential influence of complexity on the design and construction process. The aim of this research is to investigate the emergence and growth of complexity in project planning and to provide a model to consider the influence of complexity on the total project duration at the post-contract award pre-construction stage of a project. The literature review showed that complexity originates from different sources of environment, technical, and workflow interactions. They can be divided into two categories of complexity factors, first, project tasks, and second, project organisation management. Project tasks may originate from performance, lack of resources, or environmental changes for a specific task. Complexity factors that relate to organisation and management refer to workflow and interdependence of different parts. The literature review highlighted the ineffectiveness of traditional tools and techniques in planning for complexity. However, this research focus on understanding the fundamental causes of the complexity of construction projects were investigated through a questionnaire with industry experts. The results were used to develop a model that considers the core complexity factors and their interactions. System dynamics were used to investigate the model to consider the influence of complexity on project planning. Feedback from experts revealed 20 major complexity factors that impact project planning. The factors are divided into five categories known as core complexity factors. To understand the weight of each factor in comparison, the Analytical Hierarchy Process (AHP) analysis method is used. The comparison showed that externalities are ranked as the biggest influence across the complexity factors. The research underlines that there are many internal and external factors that impact project activities and the project overall. This research shows the importance of considering the influence of complexity on the project master plan undertaken at the post-contract award pre-construction phase of a project.

Keywords: project planning, project complexity measurement, planning uncertainty management, project risk management, strategic project scheduling

Procedia PDF Downloads 71
5246 The Influence of Construction Workers Wages and Working Conditions on Productivity in Ghana

Authors: Emmanuel Donkor

Abstract:

Aim/Purpose – This paper examines the influence of construction workers wages and working conditions on productivity in Ghana. Design/methodology/Approach - The study adopted a quantitative research approach with purposive sampling techniques where data was collected using surveys. The data were analyzed using SPSS software version 20.0, which enables the findings of the study to be examined under thematic areas.Findings: - The study revealed that good wages and working condition of workers have a positive correlation on productivity in the construction industry. Increase and improved wages and working conditions can results in higher productivity in the construction industry.Originality/value - This paper is exceptional in the sense that, it does examine the influence of construction workers wages and working conditions on productivity in Ghana. Social value/implications - The paper concludes that workers’ wages and their conditions have a high influence on productivity. It is then recommended that government should train, educate, give good wages to workers and improve on their working condition, give incentives and reduce tax importation on building or construction materials to aid in good productivity of construction firms.

Keywords: construction firms, construction industry, productivity, workers’ wages, working conditions

Procedia PDF Downloads 109
5245 Hybrid Risk Assessment Model for Construction Based on Multicriteria Decision Making Methods

Authors: J. Tamosaitiene

Abstract:

The article focuses on the identification and classification of key risk management criteria that represent the most important sustainability aspects of the construction industry. The construction sector is one of the most important sectors in Lithuania. Nowadays, the assessment of the risk level of a construction project is especially important for the quality of construction projects, the growth of enterprises and the sector. To establish the most important criteria for successful growth of the sector, a questionnaire for experts was developed. The analytic hierarchy process (AHP), the expert judgement method and other multicriteria decision making (MCDM) methods were used to develop the hybrid model. The results were used to develop an integrated knowledge system for the measurement of a risk level particular to construction projects. The article presents a practical case that details the developed system, sustainable aspects, and risk assessment.

Keywords: risk, system, model, construction

Procedia PDF Downloads 135
5244 Delay Studies in Construction: Synthesis, Critical Evaluation, and the Way Forward

Authors: Abdullah Alsehaimi

Abstract:

Over decades, there have been many studies of delay in construction, and this type of study continues to be popular in construction management research. A synthesis and critical evaluation of delay studies in developing countries reveals that poor project management is cited as one of the main causes of delay. However, despite such consensus, most of the previous studies fall short in providing clear recommendations demonstrating how project management practice could be improved. Moreover, the majority of recommendations are general and not devoted to solving the difficulties associated with particular delay causes. This paper aims to demonstrate that the root cause of this state of affairs is that typical research into delay tends to be descriptive and explanatory, making it inadequate for solving persistent managerial problems in construction. It is contended that many problems in construction could be mitigated via alternative research approaches, i.e. action and constructive research. Such prescriptive research methods can assist in the development and implementation of innovative tools tackling managerial problems of construction, including that of delay. In so doing, those methods will better connect research and practice, and thus strengthen the relevance of academic construction management.

Keywords: construction delay, action research, constructive research, industrial engineering

Procedia PDF Downloads 400
5243 Comparative Study of the Distribution of Seismic Loads of Buildings with Asymmetries Plan

Authors: Ahmed Hamza Yache

Abstract:

The main purpose of this study is to estimate the distribution of shear forces in building structures with asymmetries in the plan submitted to seismic forces can cause, in this case, simultaneous deformations of translation and torsion. To this end, the distribution of shear forces is obtained by seismic forces calculated from the equivalent static method of the Algerian earthquake code RPA 99 (2003 version) and spectral modal analysis for an irregular building plan without kinks. Comparison of the results obtained by these two methods used to highlight the difference in terms of distributions of shear forces in such structures.

Keywords: structure, irregular, code, seismic, method, force, period

Procedia PDF Downloads 551
5242 Humanitarian Aid and National Sovereignty: The Case of Kosovo

Authors: Nick Papanikolaou

Abstract:

In modern world politics, International relations are very complex not only in their construction but also in their interpretation the ex-Yugoslavian(western Balkans) countries, due to the establishment of independent states, have also risen pending geopolitical and territorial issues such as the Kosovo dispute widely known as an active frozen conflict. Science of anthropology and its subfield of anthropology of conflict can suggest a sustainable plan of communities coexistence and abolishment of fondamentalism. The 1244 Security Council Resolution provides a framework of implementation of a transitional international joint international armed presence for ensuring control and stability in the territory. The changing international relations landscape and the rise of the integration of the Western Balkans in the European Union have brought the question of Kosovo and all the till now internationally controlled system of governance to a dead end. A new solution that will ensure a sustainable future needs to be applied in order to solve this case in a way that rights of both albanians and Serbians will be equally respected and both populations will coexist peacefully. What this presentation aims for is to present a plan for the peaceful coexistence and sovreignty of habitants of Kosovo in a whole new way of governance.

Keywords: sovereignty, Kosovo, Western Balkans, anthropology of conflict

Procedia PDF Downloads 41
5241 Examining Renewable Energy Policy Implementation for Sustainable Development in Kenya

Authors: Eliud Kiprop, Kenichi Matsui, Joseph Karanja, Hesborn Ondiba

Abstract:

To double the share of renewable energy in the global energy mix by 2030 as part of actions for the Paris Agreement, policymakers in each ratifying country must accelerate their efforts within the next few years by implementing their own renewable energy strategies. Kenya has increased its funding for research and development in renewable energy sources largely because it intends to reduce greenhouse gas GHG emissions by 30% from business as usual (BAU) levels (143 MtCO₂eq) by 2030. In 2013, the Kenyan government launched an ambitious plan to increase the installed power generation capacity from 1,768MW to more than 5,000MW by the end of 2017. This paper examines the formulation and implementation process of this plan and shows how this plan will affect Kenya’s renewable energy industry and national policy implementation in general. Results demonstrate that, despite having a well- documented policy in place, the Kenyan government cannot meet its target of 5000MW by the end of 2017. Among other factors, we find that the main reason is attributable to the failure in adhering to the main principles of the policy plan. We also find that the government has failed to consider the future energy demand. Had the policy been implemented on time, we argue that there would have been excess power.

Keywords: policy implementation, policy plan, renewable energy, sustainable development

Procedia PDF Downloads 189
5240 Necessity of Using Cellular Lightweights Concrete in Construction Sector

Authors: Soner Guler, Fuat Korkut

Abstract:

Recently, the using of lightweights concretes in construction sector is rapidly increasing all over the world. Faster construction, low density and thermal transmitting coefficient and high fire resistance are the remarkable characteristics of the lightweight concretes. Lightweight concrete can be described as a type of concrete which enhance the volume of the mixture while giving additional advantages such as to reduce the dead weight of the structures. It is lighter than the conventional concrete. The use of lightweight concrete has been widely spread across countries such as USA, United Kingdom, and Sweden. In this study, the necessity of the using of lightweights concretes in the construction sector is emphasized and evaluated briefly for the architectures and civil engineers.

Keywords: lightweights concretes, low density, low thermal coefficient, construction sector

Procedia PDF Downloads 486
5239 Progress of Research on Community Canteens and Reflections on Planning in China

Authors: Xi Zuo

Abstract:

Against the background of the aging population and changing family structure in China, community canteens have become an important vehicle for community-based home care services and a new space for social interaction. In this paper, we review past studies and the actual construction situation in China, firstly sort out the social interaction of the elderly and the types of places, and on this basis, we find that there is an obvious disconnection between the current construction and the academic research, and the contradiction between social benefit and cost-effectiveness, and therefore we put forward the relevant construction planning and thinking, in order to provide a disciplinary basis and academic support for the construction of community canteens and the construction of elderly-friendly cities. In order to provide disciplinary basis and academic support for the construction of community canteens and the construction of senior-friendly cities.

Keywords: urban and rural planning, community canteens, elderly people, senior-friendly

Procedia PDF Downloads 19
5238 Productivity of Construction Companies Using the Management of Threats and Opportunities ‎in Construction Projects of Iran

Authors: Nima Amani, Ali Salehi Dastjerdi, Fatemeh Ahmadi, Ardalan Sabamehr

Abstract:

The cost overrun of the construction projects has always been one of the main problems of the construction companies caused by the risky nature of the construction projects. Therefore, today, the application of risk management is inevitable. Although in theory, the issue of risk management is divided into the opportunities and threats management, in practice, most of the projects have been focused on the threats management. However, considering the opportunities management and applying the opportunities-response strategies can lead to the improved profitability of the construction projects of the companies. In this paper, a new technique is developed to identify the opportunities in the construction projects using an improved protocol and propose the appropriate opportunities-response strategies to the construction companies to provide them with higher profitability. To evaluate the effectiveness of the protocol for selecting the most appropriate strategies in ‎response to the opportunities and threats, two projects from a construction company in Iran were ‎studied. Both projects selected were in mid-range in terms of size and similar in terms of time, ‎run time and costs. Finally, the output indicates that using the proposed opportunities-response strategies show that the company's profitability in the future can be increased approximately for similar projects.

Keywords: opportunities management, risk-response strategy, opportunity-response strategy, productivity, risk management

Procedia PDF Downloads 200
5237 Research on the Calculation Method of Smartization Rate of Concrete Structure Building Construction

Authors: Hongyu Ye, Hong Zhang, Minjie Sun, Hongfang Xu

Abstract:

In the context of China's promotion of smart construction and building industrialization, there is a need for evaluation standards for the development of building industrialization based on assembly-type construction. However, the evaluation of smart construction remains a challenge in the industry's development process. This paper addresses this issue by proposing a calculation and evaluation method for the smartization rate of concrete structure building construction. The study focuses on examining the factors of smart equipment application and their impact on costs throughout the process of smart construction design, production, transfer, and construction. Based on this analysis, the paper presents an evaluation method for the smartization rate based on components. Furthermore, it introduces calculation methods for assessing the smartization rate of buildings. The paper also suggests a rapid calculation method for determining the smartization rate using Building Information Modeling (BIM) and information expression technology. The proposed research provides a foundation for the swift calculation of the smartization rate based on BIM and information technology. Ultimately, it aims to promote the development of smart construction and the construction of high-quality buildings in China.

Keywords: building industrialization, high quality building, smart construction, smartization rate, component

Procedia PDF Downloads 33
5236 Mobile Application for Construction Sites Management

Authors: A. Khelifi, M. Al Kaabi, B. Al Rawashdeh

Abstract:

The infrastructure is one of the most important pillars of the UAE, where it spends millions of dollars for investments in the construction sectors. The research done by Kuwait Finance House (KFH) Research showed clearly that the UAE investments in the construction sectors have exceeded 30 billion dollars in 2013. There are many construction companies in the UAE and each one of them is taking the responsibilities to build different infrastructures. The large scale construction projects consist of multi human activities which can affect the efficiency and productivity of the running projects. The Construction Administration System is developed to increase the efficiency and productivity at the construction sites. It runs on two platforms: web server and mobile phone and supports two main users: mobile user and institution employee. With Construction Administration Mobile Application the user can manage and control several projects, create several reports and send these reports in Portable Document Format (PDF) formats through emails, view the physical location of each project, capturing and save photos. An institution employee can use the system to view all existing workers and projects, send emails and view the progress of each project.

Keywords: construction sites, management, mobile application, Portable Document Format (PDF)

Procedia PDF Downloads 349
5235 The Sustainability of Health and Safety on Construction Sites in Zamfara State

Authors: Ismaila Oladunni Muhammed, Adegbenga Raphael Ashiru

Abstract:

Construction industry has been attributed to be the engine growth of Nigerian economic and infrastructural development. It promotes infrastructural development and grows an average output of Nigerian Gross Domestic Profit. However, from this great prospect, yearly reports show that consistent accidents on construction sites in Zamfara State has affected a substantial number of workers as they become temporarily or permanently disabled, thereby making many construction sites a death trap. This posed a great threat to the industry’s sustainability, de- motivate workers from working in the industry, and further have negative impact on the economy as well. It is as a result of high construction site accident currently experiencing in Zamfara state that this research was carried out to appraise the sustainability of health and safety of construction workers on sites. The proper practice and compliance to Construction Health and safety laws are very vital to the output and growth of Zamfara State construction sector. However, a quantitative approach was adopted to justify the aforesaid statement which will provide a broader understanding of the study. Descriptive statistical analysis was obtained through Statistical Package for the Social Sciences (SPSS Version 20). Furthermore, the findings from the research highlighted that the performance and output of construction workers on construction sites depends on the proper practice of health and safety. The research findings also recommended ways to enhance employers and employee’s compliance with existing laws guiding health and safety on Zamfara State construction sites. Nevertheless, the purpose of the paper is to appraise the sustainability of Health and Safety on Zamfara State construction sites. This study further provided thorough information for resolving challenges of construction sites accidents to improve construction firm productivity and also ensured construction worker’s safety on site.

Keywords: construction industry, health and safety regulations, causes of accident, construction safety practices

Procedia PDF Downloads 186
5234 Analysis of Delays during Initial Phase of Construction Projects and Mitigation Measures

Authors: Sunaitan Al Mutairi

Abstract:

A perfect start is a key factor for project completion on time. The study examined the effects of delayed mobilization of resources during the initial phases of the project. This paper mainly highlights the identification and categorization of all delays during the initial construction phase and their root cause analysis with corrective/control measures for the Kuwait Oil Company oil and gas projects. A relatively good percentage of the delays identified during the project execution (Contract award to end of defects liability period) attributed to mobilization/preliminary activity delays. Data analysis demonstrated significant increase in average project delay during the last five years compared to the previous period. Contractors had delays/issues during the initial phase, which resulted in slippages and progressively increased, resulting in time and cost overrun. Delays/issues not mitigated on time during the initial phase had very high impact on project completion. Data analysis of the delays for the past five years was carried out using trend chart, scatter plot, process map, box plot, relative importance index and Pareto chart. Construction of any project inside the Gathering Centers involves complex management skills related to work force, materials, plant, machineries, new technologies etc. Delay affects completion of projects and compromises quality, schedule and budget of project deliverables. Works executed as per plan during the initial phase and start-up duration of the project construction activities resulted in minor slippages/delays in project completion. In addition, there was a good working environment between client and contractor resulting in better project execution and management. Mainly, the contractor was on the front foot in the execution of projects, which had minimum/no delays during the initial and construction period. Hence, having a perfect start during the initial construction phase shall have a positive influence on the project success. Our research paper studies each type of delay with some real example supported by statistic results and suggests mitigation measures. Detailed analysis carried out with all stakeholders based on impact and occurrence of delays to have a practical and effective outcome to mitigate the delays. The key to improvement is to have proper control measures and periodic evaluation/audit to ensure implementation of the mitigation measures. The focus of this research is to reduce the delays encountered during the initial construction phase of the project life cycle.

Keywords: construction activities delays, delay analysis for construction projects, mobilization delays, oil & gas projects delays

Procedia PDF Downloads 287
5233 Short-Term Operation Planning for Energy Management of Exhibition Hall

Authors: Yooncheol Lee, Jeongmin Kim, Kwang Ryel Ryu

Abstract:

This paper deals with the establishment of a short-term operational plan for an air conditioner for efficient energy management of exhibition hall. The short-term operational plan is composed of a time series of operational schedules, which we have searched using genetic algorithms. Establishing operational schedule should be considered the future trends of the variables affecting the exhibition hall environment. To reflect continuously changing factors such as external temperature and occupant, short-term operational plans should be updated in real time. But it takes too much time to evaluate a short-term operational plan using EnergyPlus, a building emulation tool. For that reason, it is difficult to update the operational plan in real time. To evaluate the short-term operational plan, we designed prediction models based on machine learning with fast evaluation speed. This model, which was created by learning the past operational data, is accurate and fast. The collection of operational data and the verification of operational plans were made using EnergyPlus. Experimental results show that the proposed method can save energy compared to the reactive control method.

Keywords: exhibition hall, energy management, predictive model, simulation-based optimization

Procedia PDF Downloads 308