5902 Identification of Factors Affecting Labor Productivity in Construction Projects of Iran

Authors: Elham Dehghan, A. Shirzadi Javid, Mohsen Tadayon

Abstract:

Labor productivity is very important and gained special concerns among professionals in the construction industry, worldwide. Productivity improvements on labors achieve higher cost savings with minimal investment. Due to the fact that profit margins are small on construction projects, cost savings associated with productivity are crucial to become a successful contractor. This research program studies and highlights the factors affecting labor productivity in Iranian construction industry. A questionnaire was used to gather the relevant data from respondents who involve in managing various types of projects in wide areas in Iran. It involved ranking 57 predefined factors divided into 5 categories: Human/Labor; Financial; Management; Equipments/Materials and Environmental. Total 62 feedbacks were analyzed through the Relative Importance Index (RII) technique. The top ten factors affecting construction labor productivity in Iran are: 1) Professional capability of contractor project manager, 2) skills of contractor’s project management team, 3) professional capability of owner project manager, 4) professional capability of Consulting Project manager, 5) discipline working, 6) delay payments by the owner, 7) material shortages, 8) delays in delivery of materials, 9) turnover power of the owner, 10) poor site management. Recommendations have been made in the study to address these factors. The research has direct benefits to key stakeholders in Iranian construction industry.

Keywords: Iranian construction projects, labor, productivity, relative importance index

Procedia PDF Downloads 264
5901 A Review of the Factors Causing Cost Overrun in Construction Projects in Malaysia

Authors: Kaleem Ullah, Abd Halid Bin Abdullah

Abstract:

This study examines previous literature on cost overrun in construction projects with the specific aim of determining the frequently observed causes of cost overruns in Malaysian construction projects. Cost overrun is one of the major problems in construction projects. Cost overrun is frequently observed in almost every construction projects. This cost overrun in construction projects occurs due to various reasons and many researchers have carried out various studies to identify the cause factors of this issue. The causes of construction cost overrun could vary from country to country because of the difference in political, economic, social and environmental conditions. Likewise, other countries construction projects in Malaysia have also the issue of cost overrun. The concept of cost overrun in construction projects has attracted much attention in recent years and researches are trying to understand the causes of these overruns and their effects to the construction industry as whole. This paper review various research studies carried out in Malaysia which surveyed the cost performance and cause factors of cost overruns in construction projects in Malaysia.

Keywords: cause of cost overrun, cost overrun, construction industry in Malaysia, effects of cost overrun

Procedia PDF Downloads 281
5900 Effect of Pre-Construction on Construction Schedule and Client Loyalty

Authors: Jong Hoon Kim, Hyun-Soo Lee, Moonseo Park, Min Jeong, Inbeom Lee

Abstract:

Pre-construction is essential in achieving the success of a construction project. Due to the early involvement of project participants in the construction phase, project managers are able to plan ahead and solve issues well in advance leading to the success of the project and the satisfaction of the client. This research utilizes quantitative data derived from construction management projects in order to identify the relationship between pre-construction, construction schedule, and client satisfaction. A total of 65 construction projects and 93 clients were investigated for this research in an attempt to identify (a) the relationship between pre-construction and schedule reduction, and (b) pre-construction and client loyalty. Based on the quantitative analysis, this research was able to establish a negative correlation based on 65 construction projects between pre-construction and project schedule existed. This finding represents that the more pre-construction is performed for a certain project, the overall construction schedule decreased. Then, to determine the relationship between pre-construction and client satisfaction, Net Promoter Score (NPS) of 93 clients from the 65 projects was utilized. Pre-construction and NPS was further analyzed and a positive correlation was found between the two. This infers that clients tend to be more satisfied with projects with higher ratio of pre-construction than those projects with less pre-construction.

Keywords: client loyalty, NPS, pre-construction, schedule reduction

Procedia PDF Downloads 358
5899 Managing Projects in Practice. A Perspective of Stakeholder Management in Managing Stakeholders within the UK Construction Projects

Authors: Faraz Ali Memon

Abstract:

Stakeholders are a vital part of any organisation. It includes working on the demands of different stakeholders within the projects. However, the reality of construction projects is slightly different when it comes to practice. The UK construction projects have a history of failing to complete projects on time and within the budget. The purpose of this qualitative study is to enhance knowledge of stakeholder engagement. Semi-structured interviews will be carried out using a purposive sampling technique. It includes interviewing and getting knowledge from industry practitioners from top UK construction firms on how to manage stakeholders effectively. The findings from this study will help in understanding stakeholders' impact and how the engagement of stakeholders can affect construction projects. The conclusions of this study add value to the existing body of knowledge on stakeholder management, especially in the UK, where academic studies on construction projects are few. As a contribution, this study will provide a practical guide for the practitioners to engage stakeholders within the scope of the project. In addition, this study is limited to UK construction projects. Therefore, the outcome may not be generalised to other developing and underdeveloped countries.

Keywords: stakeholders, UK construction, project management, cost and time

Procedia PDF Downloads 102
5898 Causes of Construction Delays in Qatar Construction Projects

Authors: Murat Gunduz, Mohanad H. A. AbuHassan

Abstract:

Construction industry mainly focuses on the superstructure, infrastructure, and oil and gas industry. The development of infrastructure projects in developing countries attracted a lot of foreign construction contractors, consultants, suppliers and diversified workforce to interfere and to be evolved in such huge investment. Reducing worksite delays in such projects require knowledge and attention. Therefore, it is important to identify the influencing delay attributes affecting construction projects. The significant project factors affecting construction delays were investigated. Data collection was carried out through an online web survey system to capture significant factors. Significant factors were determined with importance index and relevant recommendations are made. The output of the data analysis would lead the industry experts better assess the impact of construction delays on construction projects.

Keywords: construction industry, delays, importance index, frequency index

Procedia PDF Downloads 362
5897 Activity-Based Safety Assessment of Real Estate Projects in Western India

Authors: Patel Parul, Harsh Ganvit

Abstract:

The construction industry is the second highest industry after agriculture provides employment in India. In developing countries like India, many construction projects are coming up to meet the demand. On the one hand, construction projects are increasing; on the other hand still, construction companies are struggling with many problems. One of the major problems is to ensure safe working conditions at the construction site. Due to a lack of safety awareness and ignorance of safety aspects, many fatal accidents are very common at the construction site in India. One of the key success factors for construction projects is “Accident-Free Construction Projects”. The construction projects can be divided into various categories like Infrastructure projects, industrial construction and real estate construction. Real estate projects are mainly comprised of commercial and residential projects. In the construction industry, private sectors play a huge role in urban and rural development and also contribute significantly to the growth of the nation. Infrastructure and Industrial projects are mainly executed by well-qualified construction contractors. For such projects, ensuring safety at construction projects is inevitable and probably one of the major clauses of contract documents as well. These projects are monitored from time to time by national agencies and researchers, too. However, Real estate projects are rarely monitored for safety aspects. No systematic contract system is followed for these projects. Safety is the most neglected aspect of these projects. In the current research projects, an attempt is made to carry out safety auditing for about 75 real estate projects. The objective of this work is to collect the activity-based safety survey of real estate projects in western India. The analysis of activity-based safety implementation for real estate projects is discussed in the present work. The activities are divided into three categories based on the data collected. The findings of this work will help local monitoring authorities to implement a safety management plan for real estate projects.

Keywords: construction safety, safety assessment, activity-based safety, real estate projects

Procedia PDF Downloads 53
5896 Text2Time: Transformer-Based Article Time Period Prediction

Authors: Karthick Prasad Gunasekaran, B. Chase Babrich, Saurabh Shirodkar, Hee Hwang

Abstract:

Construction preparation is crucial for the success of a construction project. By involving project participants early in the construction phase, project managers can plan ahead and resolve issues early, resulting in project success and satisfaction. This study uses quantitative data from construction management projects to determine the relationship between the pre-construction phase, construction schedule, and customer satisfaction. This study examined a total of 65 construction projects and 93 clients per job to (a) identify the relationship between the pre-construction phase and program reduction and (b) the pre-construction phase and customer retention. Based on a quantitative analysis, this study found a negative correlation between pre-construction status and project schedule in 65 construction projects. This finding means that the more preparatory work done on a particular project, the shorter the total construction time. The Net Promoter Score of 93 clients from 65 projects was then used to determine the relationship between construction preparation and client satisfaction. The pre-construction status and the projects were further analyzed, and a positive correlation between them was found. This shows that customers are happier with projects with a higher ready-to-build ratio than projects with less ready-to-build.

Keywords: NLP, BERT, LLM, deep learning, classification

Procedia PDF Downloads 102
5895 Productivity of Construction Companies Using the Management of Threats and Opportunities ‎in Construction Projects of Iran

Authors: Nima Amani, Ali Salehi Dastjerdi, Fatemeh Ahmadi, Ardalan Sabamehr

Abstract:

The cost overrun of the construction projects has always been one of the main problems of the construction companies caused by the risky nature of the construction projects. Therefore, today, the application of risk management is inevitable. Although in theory, the issue of risk management is divided into the opportunities and threats management, in practice, most of the projects have been focused on the threats management. However, considering the opportunities management and applying the opportunities-response strategies can lead to the improved profitability of the construction projects of the companies. In this paper, a new technique is developed to identify the opportunities in the construction projects using an improved protocol and propose the appropriate opportunities-response strategies to the construction companies to provide them with higher profitability. To evaluate the effectiveness of the protocol for selecting the most appropriate strategies in ‎response to the opportunities and threats, two projects from a construction company in Iran were ‎studied. Both projects selected were in mid-range in terms of size and similar in terms of time, ‎run time and costs. Finally, the output indicates that using the proposed opportunities-response strategies show that the company's profitability in the future can be increased approximately for similar projects.

Keywords: opportunities management, risk-response strategy, opportunity-response strategy, productivity, risk management

Procedia PDF Downloads 227
5894 Waste Generation in Iranian Building Industry: Addressing a Theory

Authors: Golnaz Moghimi, Alireza Afsharghotli, Alireza Rezaei

Abstract:

Construction waste has been gradually increased as a result of upsizing construction projects which are occurred within the lifecycle of buildings. Since waste management is a major priority and has profound impacts on the volume of waste generated in construction stage, the majority of efforts have been attempted to reuse, recycle and reduce waste. However, there is still room to study on lack of sufficient knowledge about waste management in construction industry. This paper intends to provide an insight into the effect of project management knowledge areas on waste management solely on construction stage. To this end, a survey among Iranian building construction industry contractors was conducted to identify the effectiveness of project management knowledge areas on three jobsite key factors including ‘Site activity’, ‘Training’, and ‘Awareness’. As a result, four management disciplines were identified as most influential ones on amount of construction waste. These disciplines were Project Cost Management, Quality Management, Human Resource Management, and Integration Management. Based on the research findings, a new model was presented to develop effective construction waste strategies.

Keywords: awareness, PMBOK, site activity, training, waste management

Procedia PDF Downloads 354
5893 Factors Affecting Time Performance in Building Construction Projects

Authors: Ibraheem A. K. Mahameed

Abstract:

The aim of this study is to identify the risks affecting time performance of building construction projects in the West Bank in Palestine from contractors’ viewpoint. 38 risks that might affect time performance of building construction projects were defined through a detailed literature review. These risks have been classified into 6 groups: project, managerial, consultant, financial, external, and construction items. A questionnaire survey was performed to rank the considered risks in terms of severity and frequency. The analysis of the survey indicated that the top five risks affecting time performance of building construction projects in Palestine are: award project to the lowest price, political situation, poor communication and coordination between construction parties, change orders, and financial status of contractor.

Keywords: delay, time performance, construction, building

Procedia PDF Downloads 469
5892 Major Causes of Delay in Construction Projects

Authors: Y. Gholipour, E. Rezazadeh

Abstract:

Delay is one of the most serious and common problems of construction project that can affect project delivery unfavorably. This research presents the most important causes of delay in large dam projects based on a survey on some executed dam construction in Iran. In this survey a randomly selected samples of owners, consultants and contractors have been involved. The outcome of this survey revealed that scheduled payments, site management, shop drawing review process, unforeseen ground conditions and contractor experience as the most important factors affecting on delay in dam construction projects.

Keywords: delay, dam construction, project management, Iran

Procedia PDF Downloads 442
5891 Application of Knowledge Discovery in Database Techniques in Cost Overruns of Construction Projects

Authors: Mai Ghazal, Ahmed Hammad

Abstract:

Cost overruns in construction projects are considered as worldwide challenges since the cost performance is one of the main measures of success along with schedule performance. To overcome this problem, studies were conducted to investigate the cost overruns' factors, also projects' historical data were analyzed to extract new and useful knowledge from it. This research is studying and analyzing the effect of some factors causing cost overruns using the historical data from completed construction projects. Then, using these factors to estimate the probability of cost overrun occurrence and predict its percentage for future projects. First, an intensive literature review was done to study all the factors that cause cost overrun in construction projects, then another review was done for previous researcher papers about mining process in dealing with cost overruns. Second, a proposed data warehouse was structured which can be used by organizations to store their future data in a well-organized way so it can be easily analyzed later. Third twelve quantitative factors which their data are frequently available at construction projects were selected to be the analyzed factors and suggested predictors for the proposed model.

Keywords: construction management, construction projects, cost overrun, cost performance, data mining, data warehousing, knowledge discovery, knowledge management

Procedia PDF Downloads 368
5890 Time Overrun in Pre-Construction Planning Phase of Construction Projects

Authors: Hafiz Usama Imad, Muhammad Akram Akhund, Tauha Hussain Ali, Ali Raza Khoso, Fida Hussain Siddiqui

Abstract:

Construction industry plays a significant role in fulfilling the major requirements of the human being. It is one of the major constituents of every developed country. Although the construction industry of both the developing and developed countries encompasses a major part of the economy, and millions of rupees are utilized every year on various kinds of construction projects. But, this industry is facing numerous hurdles in terms of its budget and timely completion. Construction projects generally consist of several phases like planning, designing, execution, and finishing. This research study aims to determine the significant factors of time overrun in pre-construction planning (PCP) phase of construction projects in Pakistan. Questionnaires were distributed by various means and responses of respondents were compiled and collected data were then analyzed through a statistical technique using SPSS version 24. Major causes of time overrun in pre-construction planning phase; which is an extremely important phase of construction projects, were revealed. The research conclusion will provide a pathway for stakeholders to pay attention to the mentioned causes to overcome the major issue of time overrun.

Keywords: construction industry, Pakistan, pre-construction planning phase, time overrun

Procedia PDF Downloads 254
5889 Development of Risk Assessment and Occupational Safety Management Model for Building Construction Projects

Authors: Preeda Sansakorn, Min An

Abstract:

In order to be capable of dealing with uncertainties, subjectivities, including vagueness arising in building construction projects, the application of fuzzy reasoning technique based on fuzzy set theory is proposed. This study contributes significantly to the development of a fuzzy reasoning safety risk assessment model for building construction projects that could be employed to assess the risk magnitude of each hazardous event identified during construction, and a third parameter of probability of consequence is incorporated in the model. By using the proposed safety risk analysis methodology, more reliable and less ambiguities, which provide the safety risk management project team for decision-making purposes.

Keywords: safety risk assessment, building construction safety, fuzzy reasoning, construction risk assessment model, building construction projects

Procedia PDF Downloads 490
5888 Comparing Productivity of the Foreign versus Local Construction Workers Based on Their Level of Technical Training and Cultural Characteristics: Case Study of Kish Island, Iran

Authors: Mansour Rezvani, Mohammad Mahdi Mortaheb

Abstract:

This study considers the employment of foreign workforce in Kish Free Trade and Industrial Zone and aims to investigate the productivity of foreign construction labours as compared to their local counterpart. Moreover, this study compares work skills and experience of foreign and local Iranian construction workers to optimize construction working conditions. The results and findings have been effectively applied to develop a training program to optimize and promote Iranian workforce productivity and effectiveness in construction industry in comparison with foreign workforce. It is hoped that the accumulated findings contribute to decrease demand for foreign workers and skills shortages in construction sectors. Therefore, job vacancies for local residents in Kish and other looking for job people in main lands will be increased. The method of collecting data has been conducted by distributing a questionnaire and interviewing most foreign construction workers, local Iranian construction works and the project managers of five mega projects in Kish Island including Mica mall, Basak, Persian, Damoon and Sarina mall. All data have been analyzed by SPSS and Excel software. A topic-related survey was conducted through a structured questionnaire including 54 employers, 20 contractors and 13 consultants. About 56 factors were identified. After implementing the context validity test, 52 factors were stated in 52 questions based on five major groups consist of: (1) economical, (2) social and cultural, (3) individual, (4) technical, (5) organizational, environmental and legal. Based on the quantified Relative Importance Index, the ten most important factors, ten less important factors, and three most important categories were identified. To date, there is not any comprehensive study that explores the important critical factors in mega construction projects on Kish Island to identify the major problems to decrease demand for foreign workers.

Keywords: cultural characteristics, foreign worker, local construction workers, productivity, technical training

Procedia PDF Downloads 145
5887 Analysis of Delay Causes in Construction Projects in Saudi Arabia

Authors: Ibrahim Mahamid, A. Al-Ghonamy, M. Aichouni

Abstract:

This study aims at identifying the risk matrix for delay causes in construction projects in Saudi Arabia from consultants’ viewpoint. A questionnaire survey was undertaken of 51 consultants working on construction projects in the Northern Province of Saudi Arabia. 35 delay causes were identified through a literature review. The study concluded that the top delay causes in construction projects in Saudi Arabia from consultants’ perspective are: bid award for lowest price, changes in material types and specifications during construction, contract management, duration of contract period, fluctuation of prices of materials, frequent changes in design, improper planning, inflationary pressure, lack of adequate manpower, long period of design and time of implementation, payments delay, poor labor productivity, and rework.

Keywords: delays, construction, consultants, contributors, risk map

Procedia PDF Downloads 539
5886 Assessing Indicators, Challenges and Benefits of Sustainable Procurement in Construction Projects

Authors: Taha Anjamrooz, Sareh Rajabi, Salwa Bheiry

Abstract:

Procurement is a key process in construction project management. The present construction procurement practices have been extensively analyzed for disregarding sustainability in the project life cycle. Currently, there is a gap of information on status-quo of sustainable procurement in construction field. Thus, the aim of this study is to review sustainable procurement practices in the construction field. Disregard of three sustainability pillars is one of the major drawbacks of present construction procurement practices. Sustainable procurement is a developing idea that can enhance procurement practices and improve the sustainability performance of the construction projects. At present, sustainable procurement is still not entirely used in the construction projects. A comprehensive literature review indicated that the construction industry is still not entirely informed about the benefits and challenges of using sustainable procurement, and about important indicators that play major impacts on those benefits and challenges. This study assesses the major indicator, benefits and challenges encountered in applying sustainable procurement in the construction industry. In addition, this study investigates understanding of construction professionals on the benefits and challenges of utilizing sustainable procurement for construction projects through selected indicators that are categorized according to society and community needs.

Keywords: sustainability, sustainable development, sustainable procurement, procurement, construction industry

Procedia PDF Downloads 193
5885 Lean Implementation Analysis on the Safety Performance of Construction Projects in the Philippines

Authors: Kim Lindsay F. Restua, Jeehan Kyra A. Rivero, Joneka Myles D. Taguba

Abstract:

Lean construction is defined as an approach in construction with the purpose of reducing waste in the process without compromising the value of the project. There are numerous lean construction tools that are applied in the construction process, which maximizes the efficiency of work and satisfaction of customers while minimizing waste. However, the complexity and differences of construction projects cause a rise in challenges on achieving the lean benefits construction can give, such as improvement in safety performance. The objective of this study is to determine the relationship between lean construction tools and their effects on safety performance. The relationship between construction tools applied in construction and safety performance is identified through Logistic Regression Analysis, and Correlation Analysis was conducted thereafter. Based on the findings, it was concluded that almost 60% of the factors listed in the study, which are different tools and effects of lean construction, were determined to have a significant relationship with the level of safety in construction projects.

Keywords: correlation analysis, lean construction tools, lean construction, logistic regression analysis, risk management, safety

Procedia PDF Downloads 183
5884 Statistical Analysis of the Main Causes of Delay Factors of Infrastructure Projects

Authors: Seyed Ali Mohammadiborna, Mehdi Ravanshadnia

Abstract:

Project delays usually detrimentally affect perceptions of project success and can in some instances, result in increased costs and other time-related damages to project stakeholders. One of the realities in the national infrastructure projects is that since the primary stakeholders are state-affiliated, the delay factors of the projects have not been seriously taken into account despite the importance of on-time completion of projects. Project postponement has different economic and social consequences and leads to the technical and economic infeasibility of the infrastructure projects in the form of reduced productivity and exploitation capacity. The present study aimed at investigating delay factors of Iranian national infrastructure projects according to regulatory reports of the Plan and Budget Organization (BPO) of Iran. The present study scrutinized the influence of each of the factors that caused delays in national Iranian infrastructure projects according to the supervision reports of the planning and budget organization in 8 years. For this purpose, the study analyzed the information regarding the impact of 12 key delay factors causing delays in average 4867 projects per year in all provinces. The said factors were classified into the three groups of executive, credit, and financial and environmental-procurement factors.

Keywords: delays, infrastructure, projects, regulatory

Procedia PDF Downloads 135
5883 Study of Management of Waste Construction Materials in Civil Engineering Projects

Authors: Jalindar R. Patil, Harish P. Gayakwad

Abstract:

The increased economic growth across the globe as well as urbanization in developing countries have led into extensive construction activities that generate large amounts of wastes. Material wastage in construction projects resulted into huge financial setbacks to builders and contractors. In addition to this, it may also cause significant effects over aesthetics, health, and the general environment. However in many cities across the globe where construction wastes material management is still a problem. In this paper, the discussion is all about the method for the management of waste construction materials. The objectives of this seminar are to identify the significant source of construction waste globally, to improve the performance of by extracting the major barriers construction waste management and to determine the cost impact on the construction project. These wastes needs to be managed as well as their impacts needs to be ascertained to pave way for their proper management. The seminar includes the details of construction waste management with the reference to construction project. The application of construction waste management in the civil engineering projects is to describe the reduction in the construction wastes.

Keywords: civil engineering, construction materials, waste management, construction activities

Procedia PDF Downloads 529
5882 Causes and Effects of Delays in Construction Projects in Akure, Ondo State, South-West Nigeria

Authors: K.T Alade, A.F Lawal, A.A Omonori

Abstract:

Construction is an everlasting activity across the globe. Likewise, the problem of delay in the construction industry is a global phenomenon. Although there are several reasons that may be responsible for delay during construction, this may vary from place to place and can be reduced to the minimum when identified. This study considered the major causes and effects of delay in the execution of construction projects in Akure, Ondo State, Nigeria. Using literatures, a total number of 30 causes of construction delays were identified. The convenient sampling technique was used to select sixty respondents for a survey. The respondents comprise twenty-two (22) clients, eighteen consultants (18) and twenty (20) contractors. The analyses of the primary data revealed that the three most important causes of delay in construction projects in Akure, Ondo State Nigeria are poor site management and supervision, inadequate contractors experience and client’s financial difficulties. Based on the findings of this study, recommendations were given on how the causes and effects of delay in construction can be mitigated.

Keywords: Akure, causes, construction projects, delay, effects

Procedia PDF Downloads 508
5881 Interface Problems in Construction Projects

Authors: Puti F. Marzuki, Adrianto Oktavianus, Almerinda Regina

Abstract:

Interface problems among interacting parties in Indonesian construction projects have most often led to low productivity and completion delay. In the midst of this country’s needs to accelerate construction of public infrastructure providing connectivity among regions and supporting economic growth as well as better living quality, project delays have to be seriously addressed. This paper identifies potential causes factors of interface problems experienced by construction projects in Indonesia. Data are collected through a survey involving the main actors of six important public infrastructure construction projects including railway, LRT, sports stadiums, apartment, and education building construction projects. Five of these projects adopt the design-build project delivery method and one applies the design-bid-build scheme. Interface problems’ potential causes are categorized into contract, management, technical experience, coordination, financial, and environmental factors. Research results reveal that, especially in railway and LRT projects, potential causes of interface problems are mainly technical and managerial in nature. These relate to complex construction execution in highly congested areas. Meanwhile, coordination cause factors are mainly found in the education building construction project with loan from a foreign donor. All of the six projects have to resolve interface problems caused by incomplete or low-quality contract documents. This research also shows that the design-bid-build delivery method involving more parties in construction projects tends to induce more interface problem cause factors than the design-build scheme.

Keywords: cause factors, construction delays, project delivery method, contract documents

Procedia PDF Downloads 255
5880 Daily Site Risks Associated with Construction Projects and On-spot Corrective Measurements: Case Study of Revamping Projects in Kuwait Oil Company Fields Area

Authors: Yousef S. Al-Othman

Abstract:

The growth and expansion of the industrial facilities comes proportional to the market increasing demand of products and services. Furthermore, raw material producers such as oil companies usually undergo massive revamping projects to maintain a synchronized supply. These revamping projects are usually delivered through challenging construction projects held and associated with daily site risks related to the construction process. Henceforth, a case study related to these risks and corresponding on-spot corrective measurements has been made on a certain number of construction project contractors at Kuwait Oil Company (KOC) to derive the benefits and overall effectiveness of the on-spot corrective measurements during the construction phase of a project, and how would the same help in avoiding major incidents, ensuring a smooth, cost effective and on time delivery of the project. Findings of this case study shall have an added value to the overall risk management process by minimizing the daily site risks that may affect the project lead time, resulting in an undisturbed on-site construction process.

Keywords: oil and gas, risk management, construction projects, project lead time

Procedia PDF Downloads 105
5879 Genetic Algorithm Optimization of Multiple Resources for Multi-Projects

Authors: A. Samer Ezeldin, Sarah A. Fotouh

Abstract:

Optimization of resources is very important in all fields, as in construction management. Project managers have to face problems regarding management of cost, time and available resources of single projects and more problems arise when managing multiple projects. Most of the studies focused on optimization of resources for a single project, but, this paper will discuss the design and modeling of multiple resources optimization for multiple projects using Genetic Algorithm. Most of the companies in construction industry optimize the resources for single projects only, but with the presence of several mega projects in several developing countries running at the same time, there is a need for a model to enhance the efficiency of available resources and decreases the fluctuation as much as possible. The proposed model calculates the cost of each resource, tries to minimize the cost of extra resources as much as possible and generates the schedule of each project within a selected program.

Keywords: construction management, genetic algorithm, multiple projects, multiple resources, optimization

Procedia PDF Downloads 458
5878 Environmental Issues in Construction Projects in India

Authors: Gurbir Singh Khaira, Anmoldeep Singh Kang

Abstract:

Exposures to environmental pollution remain a major source of health risk throughout the world, though risks are generally higher in developing countries, where poverty, lack of investment in modern technology and weak environmental legislation combine to cause high pollution levels. This paper will tell us about the environment is threatened severely by so many problems, some of which are caused by the activities of Construction Projects. The research reveals major environmental impacts of building construction projects to include environmental pollution, resource depletion and habitat destruction causing Destruction of ecosystem, Desertification, Soil Erosion and increasing Material Wastage. Construction is considered as one of the main sources of environmental pollution in the world, the level of knowledge and awareness of project participants, especially project managers, with regards to environmental impacts of construction processes needs to be enhanced. It was found that ‘Transportation Resource’, ‘Noise Pollution’, and ‘Dust Generation with Construction Machinery’ are the greatest environmental impacts in INDIA respectively. The results of this study are useful for construction managers and other participants in construction sites to become aware of construction processes impacts on the environment.

Keywords: construction projects, environmental impacts, material waste age, awareness

Procedia PDF Downloads 379
5877 Conflict Causes within Construction Projects; Conflict Interaction across Project Phases

Authors: Abdullah Mohammed Alshehri

Abstract:

The projects in the construction industry have significantly increased, given its contribution to the overall Gross Domestic Product (GDP) of the countries. Reflecting upon the complex nature and involvement of various agents, the study aims to analyze the conflicts cause within construction projects. Therefore, the study strived to come out with understanding the levels of conflict interaction across project phases. However, this conducted by investigating the association between antecedents and apparent conflicts inherent in. The study used a qualitative approach for collecting the data through a quantitative, semi-structured method. Formation of a questionnaire survey has been conducted for over 30 respondents. However, the survey came out with the identification of 25 conflict cause categories, which can take place in different construction project phases, including pre-design phase, pre-construction phase, construction phase, commissioning, and completion phase. For example, conflicts associated with inconsistencies or discrepancies within or between project documents, which took place at tendering time in the pre-construction phase were relatable with the selection of material specifications that should be supplied or used in the construction projects at the construction phase. Its analysis can provide comprehensive understanding, trace the root of the problem, which offers a roadmap to deepen the understanding of the conflict conditions and ‘course of action’ necessary for project management strategy actions toward avoiding or minimizing conflict causes at project life.

Keywords: construction, conflict causes, levels, interaction, phases

Procedia PDF Downloads 177
5876 An Introduction to Critical Chain Project Management Methodology

Authors: Ranjini Ramanath, Nanjunda P. Swamy

Abstract:

Construction has existed in our lives since time immemorial. However, unlike any other industry, construction projects have their own unique challenges – project type, purpose and end use of the project, geographical conditions, logistic arrangements, largely unorganized manpower and requirement of diverse skill sets, etc. These unique characteristics bring in their own level of risk and uncertainties to the project, which cause the project to deviate from its planned objectives of time, cost, quality, etc. over the many years, there have been significant developments in the way construction projects are conceptualized, planned, and managed. With the rapid increase in the population, increased rate of urbanization, there is a growing demand for infrastructure development, and it is required that the projects are delivered timely, and efficiently. In an age where ‘Time is Money,' implementation of new techniques of project management is required in leading to successful projects. This paper proposes a different approach to project management, which if applied in construction projects, can help in the accomplishment of the project objectives in a faster manner.

Keywords: critical chain project management methodology, critical chain, project management, construction management

Procedia PDF Downloads 422
5875 Risk Management in Construction Projects

Authors: Mustafa Dogru, Ruveyda Komurlu

Abstract:

Companies and professionals in the construction sector face various risks in every project depending on the characteristics, size, complexity, the location of the projects and the techniques used. Some risks’ effects may increase as the project progresses whereas new risks may emerge. Because of the ever-changing nature of the risks, risk management is a cyclical process that needs to be repeated throughout the project. Since the risks threaten the success of the project, risk management is an important part of the entire project management process. The aims of this study are to emphasize the importance of risk management in construction projects, summarize the risk identification process, and introduce a number of methods for preventing risks such as alternative design, checklists, prototyping and test-analysis-correction technique etc. Following the literature review conducted to list the techniques for preventing risks, case studies has been performed to compare and evaluate the success of the techniques in a number of completed projects with the same typology, performed domestic and international. Findings of the study suggest that controlling and minimizing the level of the risks in construction projects, taking optimal precautions for different risks, and mitigating or eliminating the effects of risks are important in order to prevent additional costs for the project. Additionally, focusing on the risks that have highest impact is the most rational way to minimize the effects of the risks on projects.

Keywords: construction projects, construction management, project management, risk management

Procedia PDF Downloads 316
5874 Feasibility Studies in Public Construction Projects in South Africa: Barriers and Implications

Authors: Kenneth O. Otasowie, Matthew Ikuabe, Clinton Aigbavboa, Ayodeji Oke

Abstract:

The practice of feasibility studies plays a huge role in the success of construction projects. Feasibility studies according to several research should be the reason for embarking on any project. However, it has been discovered that in South Africa (SA), feasibility studies are mainly done in the private sector construction but skipped in the construction of most public projects. Hence, this study aims to evaluate the barriers to feasibility studies practice in public projects and the implications. A survey design was adopted. A total number of One hundred and fifty (150) questionnaires were administered to Quantity Surveyors, Construction managers, Construction project managers, Project managers, Architects and Civil and Structural engineers in Guateng Province, SA and ninety (90) were returned and found suitable for analysis. Collected data was analysed using percentage, mean item score, standard deviation, one-sample t-test. The findings show that political interference and corruption are the most significant barriers to feasibility studies practice in the public construction projects in SA, while late project completion, poor quality infrastructure are among the implication of not conducting feasibility studies in SA public projects. Therefore, the study recommends the development of a framework for public projects execution that will reduce the interference of the political class in the country, that way the risk of late project completion and poor quality infrastructure will be mitigated.

Keywords: arriers, feasibility studies, public construction, South Africa.

Procedia PDF Downloads 88
5873 BIM Model and Virtual Prototyping in Construction Management

Authors: Samar Alkindy

Abstract:

Purpose: The BIM model has been used to support the planning of different construction projects in the industry by showing the different stages of the construction process. The model has been instrumental in identifying some of the common errors in the construction process through the spatial arrangement. The continuous use of the BIM model in the construction industry has resulted in various radical changes such as virtual prototyping. Construction virtual prototyping is a highly advanced technology that incorporates a BIM model with realistic graphical simulations, and facilitates the simulation of the project before a product is built in the factory. The paper presents virtual prototyping in the construction industry by examining its application, challenges and benefits to a construction project. Methodology approach: A case study was conducted for this study in four major construction projects, which incorporate virtual construction prototyping in several stages of the construction project. Furthermore, there was the administration of interviews with the project manager and engineer and the planning manager. Findings: Data collected from the methodological approach shows a positive response for virtual construction prototyping in construction, especially concerning communication and visualization. Furthermore, the use of virtual prototyping has increased collaboration and efficiency between construction experts handling a project. During the planning stage, virtual prototyping has increased accuracy, reduced planning time, and reduced the amount of rework during the implementation stage. Irrespective of virtual prototyping being a new concept in the construction industry, the findings outline that the approach will benefit the management of construction projects.

Keywords: construction operations, construction planning, process simulation, virtual prototyping

Procedia PDF Downloads 230