15378 Causes of Construction Delays in Qatar Construction Projects

Authors: Murat Gunduz, Mohanad H. A. AbuHassan

Abstract:

Construction industry mainly focuses on the superstructure, infrastructure, and oil and gas industry. The development of infrastructure projects in developing countries attracted a lot of foreign construction contractors, consultants, suppliers and diversified workforce to interfere and to be evolved in such huge investment. Reducing worksite delays in such projects require knowledge and attention. Therefore, it is important to identify the influencing delay attributes affecting construction projects. The significant project factors affecting construction delays were investigated. Data collection was carried out through an online web survey system to capture significant factors. Significant factors were determined with importance index and relevant recommendations are made. The output of the data analysis would lead the industry experts better assess the impact of construction delays on construction projects.

Keywords: construction industry, delays, importance index, frequency index

Procedia PDF Downloads 313
15377 Integrating Music on Construction Sites: Key Benefits and Cautions: A Literature Perspective

Authors: Oluwatayomi Daniel Fadumo, Chinyere Celestina Esimone

Abstract:

The construction industry, as a massive human capital-related sector, requires an always motivated workforce. The inability to maintain this state has been found to hamper productivity which ultimately leads to poor project delivery, infrastructural development decline, and low morale among citizens. The need to develop an approach to keep this set of people inspired before, during, and after work becomes a necessity; this paper aims to evaluate the key benefits and cautions in integrating music on construction sites in Nigeria to improve effective project delivery. In attaining this, the study identified the advantages of music on construction sites, evaluated the key considerations in introducing music on construction sites, and recommended measures for the effective integration of music on construction sites in Nigeria. The study is a descriptive research through the use of secondary data gleaned from relevant literature, journals, and research sites. The study concluded that different forms of music genres can be implemented ranging from Pop music, rock, metal, and classical music. Introducing music has the advantage of industrial branding, improving workers` morale, setting the pace for working, helping in information retention, and improving mental health and happiness. The key consideration, however, is to provide the right volume and music that doesn’t pose health and safety challenges. The study finally recommended that for effective integration of music on construction sites in Nigeria, policies should be drafted regulating its use, specific radio customized for the site be introduced and that research-based music, proven to have previously helped, should be given to a group of workers.

Keywords: music, construction sites, workers, construction industry, construction management practice

Procedia PDF Downloads 16
15376 Flexibility Cost and Its Application for Construction Projects

Authors: Rashmi Shahu

Abstract:

Flexibility is becoming a more widely accepted aspect of project management. Although contingency theory in project management states that the unknowns are controllable, complexity theory believes that the best way to handle the unknowns would be to have a flexible approach rather than rigidity. Designing a flexible system is a method of managing uncertainty. The present research work aims to evaluate flexibility in the initial design phase of projects taking examples of construction projects. Flexibility in the initial design phase is modeled in order to know the advantage in future. The comparison between the extra cost of flexibility in the initial design phase and the discount that can be achieved in future due to this premium will help the developers in making strategic decisions. This research uses a methodology for valuing flexibility by developing a mathematical formula for predicting future saving of cost. Two case studies were considered in this research to validate the mathematical formula. This research explains three case studies of an educational institution 28 years old for explaining the concept and giving benefits of flexible design for modification/renovation work of building.

Keywords: flexibility, future saving, flexibility cost, construction projects

Procedia PDF Downloads 330
15375 Risk Management Practices In The Construction Industry In Malawi

Authors: Taonga Temwani Chibaka

Abstract:

This qualitative research study was conducted to identify the common risk factors that affect the construction industry in Malawi in the building and infrastructure (civil works) projects. The study then evaluates the possible risk responses that are done to mitigate the various risk factors that were identified. I addition the research also established the barriers to risk management implementation with lastly mapping out as where the identified risk factors fall on which stage of the project and then also map out the knowledge areas that need to be worked on the cases on Malawian construction industry in order to mitigate most of the identified risk factors. The study involved the interviewing the professionals from the construction industry in Malawi where insights and ideas were collected, analysed and interpreted. The key study findings show that risks related to clients group are perceived as most critical followed by the contractor related, consultant related and then external group related factors respectively where preventive measures are the most applied risk response technique where the aim to avoid most of the risk factors from happening. Most of the risk factors identified were internal risks and in managerial category which suggested that risk planning was to be emphasized at pre-contract stage to minimize these risks since a bigger percentage of the risk factors were mapped out at implementation stage. Furthermore, barriers to risk management were identified and the key barriers were lack of awareness; lack of knowledge; lack of formal policies in place; regarded as costly and limited time which resulted in proposing that regulating authorities to purposefully introduce intense training on risk management to make known of this new knowledge area. The study then recommends that organisation should formally implement risk management where policies should be introduced to enforce all parties to undertake this. Risk planning was regarded as paramount and this to be done from pre-contract phase so as to mitigate 80% of the risk factors. Finally, training should be done on all project management knowledge areas.

Keywords: risk management, risk factors, risks, malawi

Procedia PDF Downloads 254
15374 Composing Method of Decision-Making Function for Construction Management Using Active 4D/5D/6D Objects

Authors: Hyeon-Seung Kim, Sang-Mi Park, Sun-Ju Han, Leen-Seok Kang

Abstract:

As BIM (Building Information Modeling) application continually expands, the visual simulation techniques used for facility design and construction process information are becoming increasingly advanced and diverse. For building structures, BIM application is design - oriented to utilize 3D objects for conflict management, whereas for civil engineering structures, the usability of nD object - oriented construction stage simulation is important in construction management. Simulations of 5D and 6D objects, for which cost and resources are linked along with process simulation in 4D objects, are commonly used, but they do not provide a decision - making function for process management problems that occur on site because they mostly focus on the visual representation of current status for process information. In this study, an nD CAD system is constructed that facilitates an optimized schedule simulation that minimizes process conflict, a construction duration reduction simulation according to execution progress status, optimized process plan simulation according to project cost change by year, and optimized resource simulation for field resource mobilization capability. Through this system, the usability of conventional simple simulation objects is expanded to the usability of active simulation objects with which decision - making is possible. Furthermore, to close the gap between field process situations and planned 4D process objects, a technique is developed to facilitate a comparative simulation through the coordinated synchronization of an actual video object acquired by an on - site web camera and VR concept 4D object. This synchronization and simulation technique can also be applied to smartphone video objects captured in the field in order to increase the usability of the 4D object. Because yearly project costs change frequently for civil engineering construction, an annual process plan should be recomposed appropriately according to project cost decreases/increases compared with the plan. In the 5D CAD system provided in this study, an active 5D object utilization concept is introduced to perform a simulation in an optimized process planning state by finding a process optimized for the changed project cost without changing the construction duration through a technique such as genetic algorithm. Furthermore, in resource management, an active 6D object utilization function is introduced that can analyze and simulate an optimized process plan within a possible scope of moving resources by considering those resources that can be moved under a given field condition, instead of using a simple resource change simulation by schedule. The introduction of an active BIM function is expected to increase the field utilization of conventional nD objects.

Keywords: 4D, 5D, 6D, active BIM

Procedia PDF Downloads 251
15373 A Predictive Analytics Approach to Project Management: Reducing Project Failures in Web and Software Development Projects

Authors: Tazeen Fatima

Abstract:

Use of project management in web & software development projects is very significant. It has been observed that even with the application of effective project management, projects usually do not complete their lifecycle and fail. To minimize these failures, key performance indicators have been introduced in previous studies to counter project failures. However, there are always gaps and problems in the KPIs identified. Despite of incessant efforts at technical and managerial levels, projects still fail. There is no substantial approach to identify and avoid these failures in the very beginning of the project lifecycle. In this study, we aim to answer these research problems by analyzing the concept of predictive analytics which is a specialized technology and is very easy to use in this era of computation. Project organizations can use data gathering, compute power, and modern tools to render efficient Predictions. The research aims to identify such a predictive analytics approach. The core objective of the study was to reduce failures and introduce effective implementation of project management principles. Existing predictive analytics methodologies, tools and solution providers were also analyzed. Relevant data was gathered from projects and was analyzed via predictive techniques to make predictions well advance in time to render effective project management in web & software development industry.

Keywords: project management, predictive analytics, predictive analytics methodology, project failures

Procedia PDF Downloads 306
15372 Effects of Main Contractors’ Service Quality on Subcontractors’ Behaviours and Project Outcomes

Authors: Zhuoyuan Wang, Benson T. H. Lim, Imriyas Kamardeen

Abstract:

Effective service quality management has long been touted as a means of improving project and organisational performance. Particularly, in construction projects, main contractors are often seen as a broker between clients and subcontractors, and their service quality is thus associated with the overall project affinity and outcomes. While a considerable amount of research has focused on the aspect of clients-main contractors, very little research has been done to explore the effect of contractors’ service quality on subcontractors’ behaviours and so project outcomes. In addressing this gap, this study surveyed 97 subcontractors in the Chinese Construction industry and data was analysed using the Partial Least Square (PLS) Structural Equation Modelling (SEM) technique. The overall findings reveal that subcontractors categorised main contractors’ service quality into three dimensions: assurance; responsiveness; reliability and empathy. Of these, it is found that main contractors’ ‘assurance’ and ‘responsiveness’ positively influence subcontractors’ intention to engage in contractual behaviours. The results further show that the subcontractors’ intention to engage in organizational citizenship behaviours is associated with how flexible and committed the main contractors are in reliability and empathy. Collectively, both subcontractors’ contractual and organizational citizenship behaviours positively influence the overall project outcomes. In conclusion, the findings inform contractors different strategies towards managing and gaining subcontractors’ behaviour commitment in a socially connected, yet complex and uncertain, business environment.

Keywords: construction firms, organisational citizenship behaviour, service quality, social exchange theory

Procedia PDF Downloads 167
15371 Analysis of the Interference from Risk-Determining Factors of Cooperative and Conventional Construction Contracts

Authors: E. Harrer, M. Mauerhofer, T. Werginz

Abstract:

As a result of intensive competition, the building sector is suffering from a high degree of rivalry. Furthermore, there can be observed an unbalanced distribution of project risks. Clients are aimed to shift their own risks into the sphere of the constructors or planners. The consequence of this is that the number of conflicts between the involved parties is inordinately high or even increasing; an alternative approach to counter on that developments are cooperative project forms in the construction sector. This research compares conventional contract models and models with partnering agreements to examine the influence on project risks by an early integration of the involved parties. The goal is to show up deviations in different project stages from the design phase to the project transfer phase. These deviations are evaluated by a survey of experts from the three spheres: clients, contractors and planners. By rating the influence of the participants on specific risk factors it is possible to identify factors which are relevant for a smooth project execution.

Keywords: building projects, contract models, partnering, project risks

Procedia PDF Downloads 245
15370 Practical Experiences as Part of Project Management Course

Authors: H. Hussain, N. H. Mohamad

Abstract:

Practical experiences have been one of the successful criteria for the Project Management course for the art and design students. There are series of events that the students have to undergo as part of their practical exercises in the learning context for Project Management courses. These series have been divided into few mini programs that involved the whole individual in each group. Therefore, the events have been one of the bench marks for these students. Through the practical experience, the task that has been given to individual has been performed according to the needs of professional practice and ethics.

Keywords: practical experience, project management, art and design students, events, programs

Procedia PDF Downloads 533
15369 Simulation IDM for Schedule Generation of Slip-Form Operations

Authors: Hesham A. Khalek, Shafik S. Khoury, Remon F. Aziz, Mohamed A. Hakam

Abstract:

Slipforming operation’s linearity is a source of planning complications, and operation is usually subjected to bottlenecks at any point, so careful planning is required in order to achieve success. On the other hand, Discrete-event simulation concepts can be applied to simulate and analyze construction operations and to efficiently support construction scheduling. Nevertheless, preparation of input data for construction simulation is very challenging, time-consuming and human prone-error source. Therefore, to enhance the benefits of using DES in construction scheduling, this study proposes an integrated module to establish a framework for automating the generation of time schedules and decision support for Slipform construction projects, particularly through the project feasibility study phase by using data exchange between project data stored in an Intermediate database, DES and Scheduling software. Using the stored information, proposed system creates construction tasks attribute [e.g. activities durations, material quantities and resources amount], then DES uses all the given information to create a proposal for the construction schedule automatically. This research is considered a demonstration of a flexible Slipform project modeling, rapid scenario-based planning and schedule generation approach that may be of interest to both practitioners and researchers.

Keywords: discrete-event simulation, modeling, construction planning, data exchange, scheduling generation, EZstrobe

Procedia PDF Downloads 349
15368 Project Management Tools within SAP S/4 Hana Program Environment

Authors: Jagoda Bruni, Jan Müller-Lucanus, Gernot Stöger-Knes

Abstract:

The purpose of this article is to demonstrate modern project management approaches in the SAP S/R Hana surrounding a programming environment composed of multiple focus-diversified projects. We would like to propose innovative and goal-oriented management standards based on the specificity of the SAP transformations and customer-driven expectations. Due to the regular sprint-based controlling and management tools' application, it has been data-proven that extensive analysis of productive hours of the employees as much as a thorough review of the project progress (per GAP, per business process, and per Lot) within the whole program, can have a positive impact on customer satisfaction and improvement for projects' budget. This has been a collaborative study based on real-life experience and measurements in collaboration with our customers.

Keywords: project management, program management, SAP, controlling

Procedia PDF Downloads 52
15367 Risk Assessment in Construction of K-Span Buildings in United Arab Emirates (UAE)

Authors: Imtiaz Ali, Imam Mansoor

Abstract:

Investigations as a part of the academic study were undertaken to identify and evaluate the significant risks associated with the construction of K-span buildings in the region of UAE. Primary field data was collected through questionnaires obtaining specific open and close-ended questions from carefully selected construction firms, civil engineers and, construction manager regarding risks associated to K-span building construction. Historical data available for other regions of the same construction technique was available which was compared for identifying various non-critical and critical risk parameters by comparative evaluation techniques to come up with important risks and potential sources for their control and minimization in K-Span buildings that is increasing in the region. The associated risks have been determined with their Relative Importance Index (RII) values of which Risk involved in Change of Design required by Owners carries the highest value (RII=0.79) whereas, Delayed Payment by Owner to Contractor is one of the least (RII=0.42) value. The overall findings suggest that most relative risks as quantified originate or associated with the contractors. It may be concluded that project proponents undertaking K-span projects in planning and budgeting the cost and delays should take into account of risks on high account if changes in design are also required any delays in the material by the supplier would then be a major risk in K-span project delay. Since projects are, less costly, so owners have limited budgets, then they hire small contractors, which are not highly competent contractors. So study suggests that owner should be aware of these types of risks associated with the construction of K-span buildings in order to make it cost effective.

Keywords: k-span buildings, k-span construction, risk management, relative improvement index (RII)

Procedia PDF Downloads 351
15366 Critical Activity Effect on Project Duration in Precedence Diagram Method

Authors: Salman Ali Nisar, Koshi Suzuki

Abstract:

Precedence Diagram Method (PDM) with its additional relationships i.e., start-to-start, finish-to-finish, and start-to-finish, between activities provides more flexible schedule than traditional Critical Path Method (CPM). But, changing the duration of critical activities in PDM network will have anomalous effect on critical path. Researchers have proposed some classification of critical activity effects. In this paper, we do further study on classifications of critical activity effect and provide more information in detailed. Furthermore, we determine the maximum amount of time for each class of critical activity effect by which the project managers can control the dynamic feature (shortening/lengthening) of critical activities and project duration more efficiently.

Keywords: construction project management, critical path method, project scheduling, precedence diagram method

Procedia PDF Downloads 482
15365 Cost Overrun in Construction Projects

Authors: Hailu Kebede Bekele

Abstract:

Construction delays are suitable where project events occur at a certain time expected due to causes related to the client, consultant, and contractor. Delay is the major cause of the cost overrun that leads to the poor efficiency of the project. The cost difference between completion and the originally estimated is known as cost overrun. The common ways of cost overruns are not simple issues that can be neglected, but more attention should be given to prevent the organization from being devastated to be failed, and financial expenses to be extended. The reasons that may raised in different studies show that the problem may arise in construction projects due to errors in budgeting, lack of favorable weather conditions, inefficient machinery, and the availability of extravagance. The study is focused on the pace of mega projects that can have a significant change in the cost overrun calculation.15 mega projects are identified to study the problem of the cost overrun in the site. The contractor, consultant, and client are the principal stakeholders in the mega projects. 20 people from each sector were selected to participate in the investigation of the current mega construction project. The main objective of the study on the construction cost overrun is to prioritize the major causes of the cost overrun problem. The methodology that was employed in the construction cost overrun is the qualitative methodology that mostly rates the causes of construction project cost overrun. Interviews, open-ended and closed-ended questions group discussions, and rating qualitative methods are the best methodologies to study construction projects overrun. The result shows that design mistakes, lack of labor, payment delay, old equipment and scheduling, weather conditions, lack of skilled labor, payment delays, transportation, inflation, and order variations, market price fluctuation, and people's thoughts and philosophies, the prior cause of the cost overrun that fail the project performance. The institute shall follow the scheduled activities to bring a positive forward in the project life.

Keywords: cost overrun, delay, mega projects, design

Procedia PDF Downloads 29
15364 Multiple-Material Flow Control in Construction Supply Chain with External Storage Site

Authors: Fatmah Almathkour

Abstract:

Managing and controlling the construction supply chain (CSC) are very important components of effective construction project execution. The goals of managing the CSC are to reduce uncertainty and optimize the performance of a construction project by improving efficiency and reducing project costs. The heart of much SC activity is addressing risk, and the CSC is no different. The delivery and consumption of construction materials is highly variable due to the complexity of construction operations, rapidly changing demand for certain components, lead time variability from suppliers, transportation time variability, and disruptions at the job site. Current notions of managing and controlling CSC, involve focusing on one project at a time with a push-based material ordering system based on the initial construction schedule and, then, holding a tremendous amount of inventory. A two-stage methodology was proposed to coordinate the feed-forward control of advanced order placement with a supplier to a feedback local control in the form of adding the ability to transship materials between projects to improve efficiency and reduce costs. It focused on the single supplier integrated production and transshipment problem with multiple products. The methodology is used as a design tool for the CSC because it includes an external storage site not associated with one of the projects. The idea is to add this feature to a highly constrained environment to explore its effectiveness in buffering the impact of variability and maintaining project schedule at low cost. The methodology uses deterministic optimization models with objectives that minimizing the total cost of the CSC. To illustrate how this methodology can be used in practice and the types of information that can be gleaned, it is tested on a number of cases based on the real example of multiple construction projects in Kuwait.

Keywords: construction supply chain, inventory control supply chain, transshipment

Procedia PDF Downloads 100
15363 A New Suburb Renovation Concept

Authors: Anu Soikkelii, Laura Sorri

Abstract:

Finnish national research project, User- and Business-oriented Suburb Renovation Concept (KLIKK), was started in January 2012 and will end in June 2014. The perspective of energy efficiency is emphasised in the project, but also it addresses what improving the energy efficiency of suburban apartment buildings means from the standpoint of architecturally valuable buildings representing different periods. The project will also test the impacts of stricter energy efficiency requirements on renovation projects. The primary goal of the project is to develop a user-oriented, industrial, economic renovation concept for suburban apartment building renovation, extension and construction of additional storeys. The concept will make it possible to change from performance- and cost-based operation to novel service- and user-oriented, site-specifically tailored renovation methods utilizing integrated order and delivery chains.The present project is collaborating with Ministry of the Environment and participating cities in developing a new type of lighter town planning model for suburban renovations and in-fill construction. To support this, the project will simultaneously develop practices for environmental impact assessment tools in renovation and suburban supplementary and in-fill construction.

Keywords: energy efficiency, prefabrication, renovation concept, suburbs, sustainability, user-orientated

Procedia PDF Downloads 311
15362 Reaching New Levels: Using Systems Thinking to Analyse a Major Incident Investigation

Authors: Matthew J. I. Woolley, Gemma J. M. Read, Paul M. Salmon, Natassia Goode

Abstract:

The significance of high consequence, workplace failures within construction continues to resonate with a combined average of 12 fatal incidents occurring daily throughout Australia, the United Kingdom, and the United States. Within the Australian construction domain, more than 35 serious, compensable injury incidents are reported daily. These alarming figures, in conjunction with the continued occurrence of fatal and serious, occupational injury incidents globally suggest existing approaches to incident analysis may not be achieving required injury prevention outcomes. One reason may be that, incident analysis methods used in construction have not kept pace with advances in the field of safety science and are not uncovering the full range system-wide contributory factors that are required to achieve optimal levels of construction safety performance. Another reason underpinning this global issue may also be the absence of information surrounding the construction operating and project delivery system. For example, it is not clear who shares the responsibility for construction safety in different contexts. To respond to this issue, to the author’s best knowledge, a first of its kind, control structure model of the construction industry is presented and then used to analyse a fatal construction incident. The model was developed by applying and extending the Systems Theoretic and Incident Model and Process method to hierarchically represent the actors, constraints, feedback mechanisms, and relationships that are involved in managing construction safety performance. The Causal Analysis based on Systems Theory (CAST) method was then used to identify the control and feedback failures involved in the fatal incident. The conclusions from the Coronial investigation into the event are compared with the findings stemming from the CAST analysis. The CAST analysis highlighted additional issues across the construction system that were not identified in the coroner’s recommendations, suggested there is a potential benefit in applying a systems theory approach to incident analysis in construction. The findings demonstrate the utility applying systems theory-based methods to the analysis of construction incidents. Specifically, this study shows the utility of the construction control structure and the potential benefits for project leaders, construction entities, regulators, and construction clients in controlling construction performance.

Keywords: construction project management, construction performance, incident analysis, systems thinking

Procedia PDF Downloads 100
15361 An Analytical Survey of Construction Changes: Gaps and Opportunities

Authors: Ehsan Eshtehardian, Saeed Khodaverdi

Abstract:

This paper surveys the studies on construction change and reveals some of the potential future works. A full-scale investigation of change literature, including change definitions, types, causes and effects, and change management systems, is accomplished to explore some of the coming change trends. It is tried to pick up the critical works in each section to deduct a true timeline of construction changes. The findings show that leaping from best practice guides in late 1990s and generic process models in the early 2000s to very advanced modeling environments in the mid-2000s and the early 2010s have made gaps along with opportunities for change researchers in order to develop some more easy and applicable models. Another finding is that there is a compelling similarity between the change and risk prediction models. Therefore, integrating these two concepts, specifically from proactive management point of view, may lead to a synergy and help project teams avoid rework. Also, the findings show that exploitation of cause-effect relationship models, in order to facilitate the dispute resolutions, seems to be an interesting field for future works.

Keywords: construction change, change management systems, dispute resolutions, change literature

Procedia PDF Downloads 271
15360 Exploring the Role of Building Information Modeling for Delivering Successful Construction Projects

Authors: Muhammad Abu Bakar Tariq

Abstract:

Construction industry plays a crucial role in the progress of societies and economies. Furthermore, construction projects have social as well as economic implications, thus, their success/failure have wider impacts. However, the industry is lagging behind in terms of efficiency and productivity. Building Information Modeling (BIM) is recognized as a revolutionary development in Architecture, Engineering and Construction (AEC) industry. There are numerous interest groups around the world providing definitions of BIM, proponents describing its advantages and opponents identifying challenges/barriers regarding adoption of BIM. This research is aimed at to determine what actually BIM is, along with its potential role in delivering successful construction projects. The methodology is critical analysis of secondary data sources i.e. information present in public domain, which include peer reviewed journal articles, industry and government reports, conference papers, books, case studies etc. It is discovered that clash detection and visualization are two major advantages of BIM. Clash detection option identifies clashes among structural, architectural and MEP designs before construction actually commences, which subsequently saves time as well as cost and ensures quality during execution phase of a project. Visualization is a powerful tool that facilitates in rapid decision-making in addition to communication and coordination among stakeholders throughout project’s life cycle. By eliminating inconsistencies that consume time besides cost during actual construction, improving collaboration among stakeholders throughout project’s life cycle, BIM can play a positive role to achieve efficiency and productivity that consequently deliver successful construction projects.

Keywords: building information modeling, clash detection, construction project success, visualization

Procedia PDF Downloads 230
15359 Integrated Information System on Human Resource Management in Project-Based Organizations

Authors: Akbar Farahani, Afsaneh Hassani, Peyman M. Farkhondeh

Abstract:

Human Resource Management as one of the core processes of the project-based companies, despite its key role in the success and competitive advantage, is relatively unknown. In the project-based companies, due to the accelerated movement of knowledge in the work activities and the temporary nature of the project, the need to develop mechanisms for achieving optimal management of this issues is very challenging. Approach to human resource management in these companies evolves with goals, strategies, and operational processes. Therefore, the need for appropriate tools to facilitate implementation of the optimized human resource management in the project is more than before,Which currently with the development of information technology and modern communication, appropriate to address the optimal approach for dynamic management of human resources in the project have been provided.This is done by using the referral system implemented in Mahab GCE that provides 1: the ability to use humans in projects without geographic limitation and 2:information on the activities and outcomes of referrals.Furthermore, by using this system, recording the lessons learned after any particular activity on projects,accessing quantitative information, procedures, documentation of learned practices that have been stored in the data base as well as using them in future projects is provided.

Keywords: human resource management, project base company, ERP, referrals system

Procedia PDF Downloads 444
15358 Adoption of Noise and Vibration Management Tools for Major Infrastructure Projects in Sydney, Australia

Authors: Adrian Morris, Rodney Phillips, Mattia Tabacchi

Abstract:

Minimizing construction noise and vibration impacts is a key challenge for major infrastructure projects in urban environments. Before commencing construction works, Construction Noise and Vibration Management Plan (CNVMP) and Construction Noise and Vibration Impact Statements (CNVIS) are required to be prepared and submitted to the relevant government authorities for review and approval. However, the assessment of potential impacts from work activities at pre-approval stage may be inaccurate as works methodology and scheduling are yet to be determined. In response, noise and vibration management tools have been developed to refine and supplement the CNVIS as works progress. These tools have been successfully implemented in major infrastructure projects allowing contractors to plan and assess construction works in a cost effective and timely manner. As a result, noise and vibration management tools have been incorporated into management plans and are increasingly required by regulators.

Keywords: noise management, environmental noise, infrastructure projects, construction, vibration, cost effective

Procedia PDF Downloads 96
15357 Impact of Exogenous Risk Factors into Actual Construction Price in PPP Projects

Authors: Saleh Alzahrani, Halim Boussabaine

Abstract:

Many of Public Private Partnership (PPP) are developed based on a public project is to be awarded to a private party within a one contractual framework. PPP project risks typically include the development and construction of a new asset as well as its operation. Certainly the most severe consequences of risks through the construction period are price and time overruns. These events are among the most generally used situation in value for money analysis risks. The sources of risk change during the time in PPP project. In traditional procurement, the public sector usually has to cover all prices suffering from these risks. At least there is plenty to suggest that price suffering is a norm in some of the projects that are delivered under traditional procurement. This paper will find the impact of exogenous risk factors into actual construction price into PPP projects. The paper will present a brief literature review on PPP risk pricing strategies and then using system dynamics (SD) to analyses of the risks associated with the estimated project price. Based on the finding from these analyses a risk pricing association model is presented and discussed. The paper concludes with thoughts for future research.

Keywords: public private partnership (PPP), risk, risk pricing, system dynamics (SD)

Procedia PDF Downloads 518
15356 Comprehensive Risk Assessment Model in Agile Construction Environment

Authors: Jolanta Tamošaitienė

Abstract:

The article focuses on a developed comprehensive model to be used in an agile environment for the risk assessment and selection based on multi-attribute methods. The model is based on a multi-attribute evaluation of risk in construction, and the determination of their optimality criterion values are calculated using complex Multiple Criteria Decision-Making methods. The model may be further applied to risk assessment in an agile construction environment. The attributes of risk in a construction project are selected by applying the risk assessment condition to the construction sector, and the construction process efficiency in the construction industry accounts for the agile environment. The paper presents the comprehensive risk assessment model in an agile construction environment. It provides a background and a description of the proposed model and the developed analysis of the comprehensive risk assessment model in an agile construction environment with the criteria.

Keywords: assessment, environment, agile, model, risk

Procedia PDF Downloads 224
15355 A Relational Case-Based Reasoning Framework for Project Delivery System Selection

Authors: Yang Cui, Yong Qiang Chen

Abstract:

An appropriate project delivery system (PDS) is crucial to the success of a construction project. Case-based reasoning (CBR) is a useful support for PDS selection. However, the traditional CBR approach represents cases as attribute-value vectors without taking relations among attributes into consideration, and could not calculate the similarity when the structures of cases are not strictly same. Therefore, this paper solves this problem by adopting the relational case-based reasoning (RCBR) approach for PDS selection, considering both the structural similarity and feature similarity. To develop the feature terms of the construction projects, the criteria and factors governing PDS selection process are first identified. Then, feature terms for the construction projects are developed. Finally, the mechanism of similarity calculation and a case study indicate how RCBR works for PDS selection. The adoption of RCBR in PDS selection expands the scope of application of traditional CBR method and improves the accuracy of the PDS selection system.

Keywords: relational cased-based reasoning, case-based reasoning, project delivery system, PDS selection

Procedia PDF Downloads 396
15354 Building Information Modeling and Its Application in the State of Kuwait

Authors: Michael Gerges, Ograbe Ahiakwo, Martin Jaeger, Ahmad Asaad

Abstract:

Recent advances of Building Information Modeling (BIM) especially in the Middle East have increased remarkably. Dubai has been taking a lead on this by making it mandatory for BIM to be adopted for all projects that involve complex architecture designs. This is because BIM is a dynamic process that assists all stakeholders in monitoring the project status throughout different project phases with great transparency. It focuses on utilizing information technology to improve collaboration among project participants during the entire life cycle of the project from the initial design, to the supply chain, resource allocation, construction and all productivity requirements. In view of this trend, the paper examines the extent of applying BIM in the State of Kuwait, by exploring practitioners’ perspectives on BIM, especially their perspectives on main barriers and main advantages. To this end structured interviews were carried out based on questionnaires and with a range of different construction professionals. The results revealed that practitioners perceive improved communication and mitigated project risks by encouraged collaboration between project participants. However, it was also observed that the full implementation of BIM in the State of Kuwait requires concerted efforts to make clients demanding BIM, counteract resistance to change among construction professionals and offer more training for design team members. This paper forms part of an on-going research effort on BIM and its application in the State of Kuwait and it is on this basis that further research on the topic is proposed.

Keywords: building information modeling, BIM, construction industry, Kuwait

Procedia PDF Downloads 348
15353 Applying an Application-Based Knowledge Capturing and Reusing for Construction Consultant Organizations Applying

Authors: Phan Nghiem Vu, Le Tuan Vu, Ta Quang Tai

Abstract:

Knowledge Management effectively is critical to the survival and advance of a company, especially in company-based industries such as construction. Knowledge management practice is crucial to the survival and progress of a company, especially company-based knowledge such as construction consultancy. Effective knowledge management practices are very significant to the competitive and development of a consulting organization. Hence, the success of knowledge management implementation depends on knowledge capturing and reusing effectively. In this paper, a survey was carried out of engineers and managers with experience in seven construction consulting organizations that provide services on the north-central coast of Vietnam. The main objectives of the survey to finding out how these organizations capture and reuse knowledge and significant barriers to the implementation of knowledge management. A conceptual framework based-on Trello application is proposed to formalize the knowledge-capturing and reusing process within construction consulting companies. It is showed that the conceptual framework could be used to manage both implicit and explicit knowledge effectively in construction consultant organizations.

Keywords: knowledge management, construction consultant organization, knowledge capturing, reusing knowledge, application-based technology

Procedia PDF Downloads 98
15352 Safety Management on Construction Sites

Authors: Jonathan Doku

Abstract:

The study's goal was to evaluate construction site safety management in Ghana. The construction sector has long been seen as a high-risk business. It entails a variety of hazardous and challenging labor duties, such as lifting and working at a height, among others. The accident rate is a standard indicator for comparing the safety performance of construction projects. Because of its high-risk and fast-changing work environment, the construction business is regarded as one of the industries with the highest accident rates in the world. Many mishaps and work-related diseases have occurred there, and construction workers are particularly vulnerable to catastrophic calamities such as falls, collapses, and burial. The study's main goals were to discover characteristics that have a substantial impact on construction site safety, to evaluate the safety management methods utilized on construction sites, and to assess the obstacles associated with construction site safety management. The study was conducted using a quantitative research method and a purposive sampling strategy. Google forms were used to distribute self-administered surveys to 85 responders. 72 of the 85 questionnaires were completed and submitted for analysis, accounting for 84.7 percent of the total. The variables were analyzed using descriptive statistics, mean score ranking, and Cronbach's Alpha Coefficient to ensure the scale's reliability. The formal safety organization structure and the Safety checklist were identified as the key practices of safety management on site as part of the study goals. In addition, it was discovered that the most serious problem with safety management is ineffective supervision. To guarantee efficient monitoring and proper implementation of health and safety rules on building sites, management must be on the ball.

Keywords: construction, safety, risk, management

Procedia PDF Downloads 46
15351 Analyzing Competition in Public Construction Projects

Authors: Khaled Hesham Hyari, Amjad Almani

Abstract:

Construction projects in the public sector are commonly awarded through competitive bidding. In the last decade, the Construction projects environment in the Middle East went through many changes. These changes have been caused by different factors including the economic crisis, delays in monthly payments, international competition and reduced number of projects. These factors had a great impact on the bidding behaviors of contractors and their pricing strategies. This paper examines the competition characteristics in public construction projects through an analysis of bidding results of contractors in public construction projects over a period of 6 years (2006-2011) in Jordan. The analyzed projects include all categories of projects such as infrastructure, buildings, transportation and engineering services (design and supervision contracts). Data for the projects were obtained from the General Tender’s Directorate in Jordan and includes 462 projects. The analysis performed in this projects includes, studying the bid spread in all projects as it is an indication of the level of competition in the analyzed bids. The analysis studied the factors that affect bid spread such as number of bidders, Value of the project, Project category and years. It also studying the “Signal to Noise Ratio” in all projects as it is an indication of the accuracy of cost estimating performed by competing bidders and bidder´s evaluation of project risks. The analysis performed includes the relationship between signal to noise ratio and different parameters such as project category, number of bidders and changes over years. Moreover, the analysis includes determining the bidder´s aggressiveness in bidding as it is an indication of competition level in such projects. This was performed by determining the pack price which can be considered as the true value of the project and comparing it with the lowest bid submitted for each project to determine the level of aggressiveness in submitted bids. The analysis performed in this project should prove to be useful to owners in understanding bidding behaviors of contractors and pointing out areas that needs improvement in preparing bidding documents. Also the project should be useful to contractors in understanding the competitive bidding environment and should help them to improve their bidding strategies to maximize the success rate in obtaining contracts.

Keywords: construction projects, competitive bidding, public construction, competition

Procedia PDF Downloads 304
15350 Technology Blending as an Innovative Construction Mechanism in the Global South

Authors: Janet Kaningen, Richard N. Kaningen, Jonas Kaningen

Abstract:

This paper aims to discover the best ways to improve production efficiency, cost efficiency, community cohesion, and long-term sustainability in Ghana's housing delivery. Advanced Construction Technologies (ACTs) are set to become the sustainable mainstay of the construction industry due to the demand for innovative housing solutions. Advances in material science, building component production, and assembly technologies are leading to the development of next-generation materials such as polymeric-fiber-based products, light-metal alloys, and eco-materials. Modular housing construction has become more efficient and cost-effective than traditional building methods and is becoming increasingly popular for commercial, industrial, and residential projects. Effective project management and logistics will be imperative in the future speed and cost of modular construction housing.

Keywords: technology blending, sustainability, housing, Ghana

Procedia PDF Downloads 55
15349 A Risk Management Framework for Selling a Mega Power Plant Project in a New Market

Authors: Negar Ganjouhaghighi, Amirali Dolatshahi

Abstract:

The origin of most risks of a mega project usually takes place in the phases before closing the contract. As a practical point of view, using project risk management techniques for preparing a proposal is not a total solution for managing the risks of a contract. The objective of this paper is to cover all those activities associated with risk management of a mega project sale’s processes; from entrance to a new market to awarding activities and the review of contract performance. In this study, the risk management happens in six consecutive steps that are divided into three distinct but interdependent phases upstream of the award of the contract: pre-tendering, tendering and closing. In the first step, by preparing standard market risk report, risks of the new market are identified. The next step is the bid or no bid decision making based on the previous gathered data. During the next three steps in tendering phase, project risk management techniques are applied for determining how much contingency reserve must be added or reduced to the estimated cost in order to put the residual risk to an acceptable level. Finally, the last step which happens in closing phase would be an overview of the project risks and final clarification of residual risks. The sales experience of more than 20,000 MW turn-key power plant projects alongside this framework, are used to develop a software that assists the sales team to have a better project risk management.

Keywords: project marketing, risk management, tendering, project management, turn-key projects