6699 Performance Evaluation of Construction Projects by Earned Value Management Method, Using Primavera P6 – A Case Study in Istanbul, Turkey

Authors: Mohammad Lemar Zalmai, Osman Hurol Turkakin, Cemil Akcay, Ekrem Manisali

Abstract:

Most of the construction projects are exposed to time and cost overruns due to various factors and this is a major problem. As a solution to this, the Earned Value Management (EVM) method is considered. EVM is a powerful and well-known method used in monitoring and controlling the project. EVM is a technique that project managers use to track the performance of their project against project baselines. EVM gives an early indication that either project is delayed or not, and the project is either over budget or under budget at any particular day by tracking it. Thus, it helps to improve the management control system of a construction project, to detect and control the problems in potential risk areas and to suggest the importance and purpose of monitoring the construction work. This paper explains the main parameters of the EVM system involved in the calculation of time and cost for construction projects. In this study, the project management software Primavera P6 is used to deals with the project monitoring process of a seven-storeyed (G+6) faculty building whose construction is in progress at Istanbul, Turkey. A comparison between the planned progress of construction activities and actual progress is performed, and the analysis results are interpreted. This case study justifies the benefits of using EVM for project cash flow analysis and forecasting.

Keywords: earned value management (EVM), construction cost management, construction planning, primavera P6, project management, project scheduling

Procedia PDF Downloads 205
6698 The Effect of Engineering Construction in Online Consultancy

Authors: Mariam Wagih Nagib Eskandar

Abstract:

The engineering design process is the activities formulation, to help an engineer raising a plan with a specified goal and performance. The engineering design process is a multi-stage course of action including the conceptualization, research, feasibility studies, establishment of design parameters, preliminary and finally the detailed design. It is a progression from the abstract to the concrete; starting with probably abstract ideas about need, and thereafter elaborating detailed specifications of the object that would satisfy the needs, identified. Engineering design issues, problems, and solutions are discussed in this paper using qualitative approach from an information structure perspective. The objective is to identify the problems, to analyze them and propose solutions by integrating; innovation, practical experience, time and resource management, communications skills, isolating the problem in coordination with all stakeholders. Consequently, this would be beneficial for the engineering community to improve the Engineering design practices.

Keywords: education, engineering, math, performanceengineering design, architectural engineering, team-based learning, construction safetyrequirement engineering, models, practices, organizations

Procedia PDF Downloads 55
6697 Identifying the Level of Awareness on Value Management Practice amongst Construction Practitioners in Nigeria

Authors: Alhassan Dahiru

Abstract:

Value management is widely accepted technique of eliminating unnecessary cost at different stages of project development that maximizes the functional value of a project by managing its evolution and development from concept to completion. Many construction industry practitioners are not aware of Value Management practice, and its use is less widespread in Nigeria. The aim of this research is to identify the level of awareness on value management practice amongst construction practitioners with a view to contribute to the improvement of the implementation of value management practice in the Nigerian construction industry. In this study, construction practitioners have been chosen as respondents from the 6 geopolitical zones of the federation including FCT Abuja. Through the survey, a total number of 360 semi-structured questionnaires were administered and 284 were returned and remained good for the analysis. The results indicate that most of the respondents were aware of the value management concept and issues surrounding construction industry in Nigeria, while about 32% of the respondents were not aware of its potential benefits. Therefore, organisations should review their techniques and processes from time to time for improvement on effective service delivery. Additionally, a change management strategy should also be part of every organization to ease the introduction of new techniques such as value management. There is also the need for more value management training workshops and seminars in order to enlighten the participants of the construction industry on the principles, concept, and techniques involved in the value management process.

Keywords: sustainability, value management, construction practitioners, Nigeria

Procedia PDF Downloads 214
6696 Effects of Different Climate Zones, Building Types, and Primary Fuel Sources for Energy Production on Environmental Damage from Four External Wall Technologies for Residential Buildings in Israel

Authors: Svetlana Pushkar, Oleg Verbitsky

Abstract:

The goal of the present study is to evaluate environmental damage from four wall technologies under the following conditions: four climate zones in Israel, two building (conventional vs. low-energy) types, and two types of fuel source [natural gas vs. photovoltaic (PV)]. The hierarchical ReCiPe method with a two-stage nested (hierarchical) ANOVA test is applied. It was revealed that in a hot climate in Israel in a conventional building fueled by natural gas, OE is dominant (90 %) over the P&C stage (10 %); in a mild climate in Israel in a low-energy building with PV, the P&C stage is dominant (85 %) over the OE stage (15 %). It is concluded that if PV is used in the building sector in Israel, (i) the P&C stage becomes a significant factor that influences the environment, (ii) autoclaved aerated block is the best external wall technology, and (iii) a two-stage nested mixed ANOVA can be used to evaluate environmental damage via ReCiPe when wall technologies are compared.

Keywords: life cycle assessment (LCA), photovoltaic, ReCiPe method, residential buildings

Procedia PDF Downloads 276
6695 A Two-Stage Bayesian Variable Selection Method with the Extension of Lasso for Geo-Referenced Data

Authors: Georgiana Onicescu, Yuqian Shen

Abstract:

Due to the complex nature of geo-referenced data, multicollinearity of the risk factors in public health spatial studies is a commonly encountered issue, which leads to low parameter estimation accuracy because it inflates the variance in the regression analysis. To address this issue, we proposed a two-stage variable selection method by extending the least absolute shrinkage and selection operator (Lasso) to the Bayesian spatial setting, investigating the impact of risk factors to health outcomes. Specifically, in stage I, we performed the variable selection using Bayesian Lasso and several other variable selection approaches. Then, in stage II, we performed the model selection with only the selected variables from stage I and compared again the methods. To evaluate the performance of the two-stage variable selection methods, we conducted a simulation study with different distributions for the risk factors, using geo-referenced count data as the outcome and Michigan as the research region. We considered the cases when all candidate risk factors are independently normally distributed, or follow a multivariate normal distribution with different correlation levels. Two other Bayesian variable selection methods, Binary indicator, and the combination of Binary indicator and Lasso were considered and compared as alternative methods. The simulation results indicated that the proposed two-stage Bayesian Lasso variable selection method has the best performance for both independent and dependent cases considered. When compared with the one-stage approach, and the other two alternative methods, the two-stage Bayesian Lasso approach provides the highest estimation accuracy in all scenarios considered.

Keywords: Lasso, Bayesian analysis, spatial analysis, variable selection

Procedia PDF Downloads 122
6694 Research on Contract's Explicit Incentive and Reputation's Implicit Incentive Mechanism towards Construction Contractors

Authors: Li Ma, Meishuang Ma, Mengying Huang

Abstract:

The quality of construction projects reflects the credit and responsibilities of construction contractors for the owners and the whole society. Because the construction contractors master more relevant information about the entrusted engineering project under construction while the owners are in unfavorable position of gaining information, asymmetric information may lead the contractors act against the owners in order to pursue their own interests. Building a powerful motivation mechanism is the key to guarantee investor economic interests and the life and property of users in construction projects. Based on principal-agent theory and game theory, the authors develop relevant mathematical models to analyze and compare the contractor’s utility functions under different combinations of contracts’ explicit incentive mechanism and reputation’s implicit incentive mechanism aiming at finding out the conditions for incentive validity. The research concludes that the most rational motivation way is to combine the explicit and implicit incentive effects of both contracts and reputation mechanism, and puts forth some measures for problems on account of China’s current situation.

Keywords: construction contractors, contract, reputation, incentive mechanism

Procedia PDF Downloads 490
6693 Innovative Housing Construction Technologies in Slum Upgrading

Authors: Edmund M. Muthigani

Abstract:

Innovation in the construction industry has been characterized by new products and processes especially in slum upgrading. The need for low cost housing has motivated stakeholders to think outside the box in coming up with solutions. This paper explored innovative construction technologies that have been used in slum upgrading. The main objectives of the paper was to examine innovations in the construction housing sector and to show how incremental derived demand for decent housing has led to adoption of innovative technologies and materials. Systematic literature review was used to review studies on innovative construction technologies in slum upgrading. The review revealed slow process of innovations in the construction industry due to risk aversion by firms and the hesitance to adopt by firms and individuals. Low profit margins in low cost housing and lack of sufficient political support remain the major hurdles to innovative techniques adoption that can actualize right to decent housing. Conventional construction materials have remained unaffordable to many people and this has negated them decent housing. This has necessitated exploration of innovative materials to realize low cost housing. Stabilized soil blocks and sisal-cement roofing blocks are some of the innovative construction materials that have been utilized in slum upgrading. These innovative materials have not only lowered the cost of production of building elements but also eased costs of transport as the raw materials to produce them are readily available in or within the slum sites. Despite their shortcomings in durability and compressive strength, they have proved worthwhile in slum upgrading. Production of innovative construction materials and use of innovative techniques in slum upgrading also provided employment to the locals.

Keywords: construction, housing, innovation, slum, technology

Procedia PDF Downloads 187
6692 The Requirements of Developing a Framework for Successful Adoption of Quality Management Systems in the Construction Industry

Authors: Mohammed Ali Ahmed, Vaughan Coffey, Bo Xia

Abstract:

Quality management systems (QMSs) in the construction industry are often implemented to ensure that sufficient effort is made by companies to achieve the required levels of quality for clients. Attainment of these quality levels can result in greater customer satisfaction, which is fundamental to ensure long-term competitiveness for construction companies. However, the construction sector is still lagging behind other industries in terms of its successful adoption of QMSs, due to the relative lack of acceptance of the benefits of these systems among industry stakeholders, as well as from other barriers related to implementing them. Thus, there is a critical need to undertake a detailed and comprehensive exploration of adoption of QMSs in the construction sector. This paper comprehensively investigates in the construction sector setting, the impacts of all the salient factors surrounding successful implementation of QMSs in building organizations, especially those of external factors. This study is part of an ongoing PhD project, which aims to develop a new framework that integrates both internal and external factors affecting QMS implementation. To achieve the paper aim and objectives, interviews will be conducted to define the external factors influencing the adoption of QMSs, and to obtain holistic critical success factors (CSFs) for implementing these systems. In the next stage of data collection, a questionnaire survey will be developed to investigate the prime barriers facing the adoption of QMSs, the CSFs for their implementation, and the external factors affecting the adoption of these systems. Following the survey, case studies will be undertaken to validate and explain in greater detail the real effects of these factors on QMSs adoption. Specifically, this paper evaluates the effects of the external factors in terms of their impact on implementation success within the selected case studies. Using findings drawn from analyzing the data obtained from these various approaches, specific recommendations for the successful implementation of QMSs will be presented, and an operational framework will be developed. Finally, through a focus group, the findings of the study and the new developed framework will be validated. Ultimately, this framework will be made available to the construction industry to facilitate the greater adoption and implementation of QMSs. In addition, deployment of the applicable recommendations suggested by the study will be shared with the construction industry to more effectively help construction companies to implement QMSs, and overcome the barriers experienced by businesses, thus promoting the achievement of higher levels of quality and customer satisfaction.

Keywords: barriers, critical success factors, external factors, internal factors, quality management systems

Procedia PDF Downloads 164
6691 Promoting the Contructor's Reputation in the Nigerian Construction Industry

Authors: Abdulkadir Adamu Shehu

Abstract:

Company’s reputation is an elusive asset. The reputation gained by companies must be preserved for sustainability of the company. However, the construction project is still suffering from declination of character due to the factors that affect their reputation. The problem led to the loss of projects, abandoning of the projects and many more. This contributed to negative impact on the contractors in the construction industry. As for today, previous studies have not investigated in this regards yet. For that reason, this paper examines the factors which could promote contractor’s reputation in the construction industry in Nigeria. To achieve this aim, 140 questionnaires were distributed to the Nigerian contractors. Based on the 67% response rate, descriptive analysis and analysis of variance (ANOVA) were the tools applied for the data obtained to be analysed. The result shows that, good communication system and improve quality of output of products are the most significant variables that can promote contractor’s reputation. The homogenous analyses indicate that there are significant different perceptions of respondents in term of the significant effects. The research concluded that contractor’s reputation in construction industry must be maintained and further research was suggested to focus on the qualitative method to have in-depth knowledge on contractor’s reputation in the construction industry.

Keywords: construction industry, contractor’s reputation, effects of delay, Nigeria

Procedia PDF Downloads 411
6690 Towards Optimising Building Information Modelling and Building Management System in Higher Education Institutions Facility Management: A Review

Authors: Zhuoqun Sun, Francisco Sierra, A. Booth

Abstract:

With BIM rapidly implemented in the design and construction stage of a project, researchers begin to focus on improving the operation and maintenance stage with the aid of BIM. Since the increasing amount of electronic equipment installed in the building, building management system becomes mainstream for controlling a building, especially in higher education institutions that can play an important role in terms of reducing carbon emission and improving energy efficiency. Currently, an approach to integrate BIM and BMS to improve HEIs facility management has not been established yet. Thus, this paper aims to analyse the benefits, issues, and trends of BIM and BMS integration and their application in HEIs. A systematic literature review was carried out on SCOPUS by applying the PRISMA methodology. 73 articles have been chosen based on keywords, abstracts, and the full content of the articles. The benefit and existed issues from the articles are analysed. The review shows the need to develop a tool to improve facility management through BIM BMS integration.

Keywords: BIM, BMS, HEIs, review

Procedia PDF Downloads 144
6689 Development of Active Learning Calculus Course for Biomedical Program

Authors: Mikhail Bouniaev

Abstract:

The paper reviews design and implementation of a Calculus Course required for the Biomedical Competency Based Program developed as a joint project between The University of Texas Rio Grande Valley, and the University of Texas’ Institute for Transformational Learning, from the theoretical perspective as presented in scholarly work on active learning, formative assessment, and on-line teaching. Following a four stage curriculum development process (objective, content, delivery, and assessment), and theoretical recommendations that guarantee effectiveness and efficiency of assessment in active learning, we discuss the practical recommendations on how to incorporate a strong formative assessment component to address disciplines’ needs, and students’ major needs. In design and implementation of this project, we used Constructivism and Stage-by-Stage Development of Mental Actions Theory recommendations.

Keywords: active learning, assessment, calculus, cognitive demand, mathematics, stage-by-stage development of mental action theory

Procedia PDF Downloads 340
6688 Assessment the Correlation of Rice Yield Traits by Simulation and Modelling Methods

Authors: Davood Barari Tari

Abstract:

In order to investigate the correlation of rice traits in different nitrogen management methods by modeling programming, an experiment was laid out in rice paddy field in an experimental field at Caspian Coastal Sea region from 2013 to 2014. Variety used was Shiroudi as a high yielding variety. Nitrogen management was in two methods. Amount of nitrogen at four levels (30, 60, 90, and 120 Kg N ha-1 and control) and nitrogen-splitting at four levels (T1: 50% in base + 50% in maximum tillering stage, T2= 33.33% basal +33.33% in maximum tillering stage +33.33% in panicle initiation stage, T3=25% basal+37.5% in maximum tillering stage +37.5% in panicle initiation stage, T4: 25% in basal + 25% in maximum tillering stage + 50% in panicle initiation stage). Results showed that nitrogen traits, total grain number, filled spikelets, panicle number per m2 had a significant correlation with grain yield. Results related to calibrated and validation of rice model methods indicated that correlation between rice yield and yield components was accurate. The correlation between panicle length and grain yield was minimum. Physiological indices was simulated with low accuracy. According to results, investigation of the correlation between rice traits in physiological, morphological and phenological characters and yield by modeling and simulation methods are very useful.

Keywords: rice, physiology, modelling, simulation, yield traits

Procedia PDF Downloads 330
6687 Characterization of Copper Slag and Jarofix Waste Materials for Road Construction

Authors: V. K. Arora, V. G. Havanagi, A. K. Sinha

Abstract:

Copper slag and Jarofix are waste materials, generated during the manufacture of copper and zinc respectively, which have potential for utility in embankment and road construction. Accordingly, a research project was carried out to study the characteristics of copper slag and Jarofix to utilize in the construction of road. In this study, copper slag and Jarofix were collected from Tuticorin, State of Tamil Nadu and Hindustan Zinc Ltd., Chittorgarh, Rajasthan state, India respectively. These materials were investigated for their physical, chemical, and geotechnical characteristics. The materials were collected from the disposal area and laboratory investigations were carried out to study its feasibility for use in the construction of embankment and sub grade layers of road pavement. This paper presents the results of physical, chemical and geotechnical characteristics of copper slag and Jarofix. It was concluded that copper slag and Jarofix may be utilized in the construction of road.

Keywords: copper slag, Jarofix waste, material, road construction

Procedia PDF Downloads 426
6686 Measuring the Embodied Energy of Construction Materials and Their Associated Cost Through Building Information Modelling

Authors: Ahmad Odeh, Ahmad Jrade

Abstract:

Energy assessment is an evidently significant factor when evaluating the sustainability of structures especially at the early design stage. Today design practices revolve around the selection of material that reduces the operational energy and yet meets their displinary need. Operational energy represents a substantial part of the building lifecycle energy usage but the fact remains that embodied energy is an important aspect unaccounted for in the carbon footprint. At the moment, little or no consideration is given to embodied energy mainly due to the complexity of calculation and the various factors involved. The equipment used, the fuel needed, and electricity required for each material vary with location and thus the embodied energy will differ for each project. Moreover, the method and the technique used in manufacturing, transporting and putting in place will have a significant influence on the materials’ embodied energy. This anomaly has made it difficult to calculate or even bench mark the usage of such energies. This paper presents a model aimed at helping designers select the construction materials based on their embodied energy. Moreover, this paper presents a systematic approach that uses an efficient method of calculation and ultimately provides new insight into construction material selection. The model is developed in a BIM environment targeting the quantification of embodied energy for construction materials through the three main stages of their life: manufacturing, transportation and placement. The model contains three major databases each of which contains a set of the most commonly used construction materials. The first dataset holds information about the energy required to manufacture any type of materials, the second includes information about the energy required for transporting the materials while the third stores information about the energy required by tools and cranes needed to place an item in its intended location. The model provides designers with sets of all available construction materials and their associated embodied energies to use for the selection during the design process. Through geospatial data and dimensional material analysis, the model will also be able to automatically calculate the distance between the factories and the construction site. To remain within the sustainability criteria set by LEED, a final database is created and used to calculate the overall construction cost based on R.M.S. means cost data and then automatically recalculate the costs for any modifications. Design criteria including both operational and embodied energies will cause designers to revaluate the current material selection for cost, energy, and most importantly sustainability.

Keywords: building information modelling, energy, life cycle analysis, sustainablity

Procedia PDF Downloads 255
6685 Lean Implementation: Manufacturing vs. Construction a Roadmap for Success

Authors: Patrick Ahern, David Collery

Abstract:

The implementation of lean thinking in the manufacturing industry revolutionized the traditional approach to large-scale production through the process of identifying the waste in each task and putting in place mitigation measures to eliminate the waste in all its forms. The Irish construction industry, however, has been much slower to adopt the principles of lean, opting instead to stick with the traditional approach to construction project delivery which is inherently wasteful. Lean thinking holds the potential to revolutionize the construction industry in a similar manner to the adoption of lean manufacturing. Lean principles present opportunities for reduced project duration, reduced project cost, improved quality, and elimination of re-works and non-value-added activities. The following research has been designed to accumulate research data through available literature, electronic surveys, and interviews. The results show an industry reluctant to accept change and an undefined path to successful lean construction implementation.

Keywords: barriers, lean construction, lean implementation, lean manufacturing, lean philosophy

Procedia PDF Downloads 56
6684 General Principles of Accident Prevention in Built Environment Rehabilitation

Authors: Alfredo Soeiro

Abstract:

Rehabilitation in construction or built environment is a particular type of operations when concerning prevention of accidents. In fact, it is also a different type of task in construction itself. Therefore, due to the complex characteristics of construction rehabilitation tasks and due to the intrinsic difficulty of preventing accidents in construction, a major challenge faces the responsibility for implementing adequate safety levels in this type of safety management. This paper addresses a set of proposed generic measures to face the unknown characteristics of built environment in terms of stability, materials and actual performance of buildings or other constructions. It is also addressed the necessary adaptation of preventive guidelines to this type of delicate refurbishing and renovating of existing facilities. Training, observation and reflective approaches are necessary to perform this safety management in the rehabilitation of built environment.

Keywords: built environment, rehabilitation, construction safety, accident prevention, safety plan

Procedia PDF Downloads 191
6683 Concrete Recycling in Egypt for Construction Applications: A Technical and Financial Feasibility Model

Authors: Omar Farahat Hassanein, A. Samer Ezeldin

Abstract:

The construction industry is a very dynamic field. Every day new technologies and methods are developing to fasten the process and increase its efficiency. Hence, if a project uses fewer resources, it will be more efficient. This paper examines the recycling of concrete construction and demolition (C&D) waste to reuse it as aggregates in on-site applications for construction projects in Egypt and possibly in the Middle East. The study focuses on a stationary plant setting. The machinery set-up used in the plant is analyzed technically and financially. The findings are gathered and grouped to obtain a comprehensive cost-benefit financial model to demonstrate the feasibility of establishing and operating a concrete recycling plant. Furthermore, a detailed business plan including the time and hierarchy is proposed.

Keywords: construction wastes, recycling, sustainability, financial model, concrete recycling, concrete life cycle

Procedia PDF Downloads 394
6682 A Conceptual Framework of Impact of Lean on the Performance of Construction Industry

Authors: Jaber Shurrab, Matloub Hussain

Abstract:

The rapid pace of changes in the construction industry, technological advancements, and rising costs present tremendous challenges for project managers. Project managers are under severe pressure to minimize the waste, improve the efficiency of the entire operations and the philosophy of ‘lean thinking’ so that ‘more could be achieved with less’ is becoming very popular. Though, lean management has strong roots in manufacturing industry and over the last decade lean philosophy has started gaining attention in the service industry as well. However, little has been known in the context of waste minimization and lean implementation in the construction industry and this paper deals with this important issue. The primary objective of this paper is to propose a conceptual framework for the exploration of appropriate lean techniques applicable to medium and large construction companies and measure their impact on the competitiveness and economic performance of construction companies of United Arab Emirates (UAE). To this end, a comprehensive literature review and interviews with eight project managers of medium and large construction companies of UAE have been conducted. It has been found that competitive, reduce waste and costs are critical to the construction industry. This is an ongoing research in lean management, giving project managers a practical framework for improving the efficiency of their project through various lean techniques. Originality/value: Research significance emphasizes increasing the effectiveness of the construction industry, influences the development of lean construction framework which improves lean construction practices using the lean techniques. This contributes to the effort of applying lean techniques in the construction industry. Limited publications were done in the construction industry mainly in United Arab Emirates (UAE) compared to the lean manufacturing. This research will recommend a systematic approach for the implementing of the anticipated framework within a cyclical look-ahead period and emphasizes the practical implications of the proposed approach.

Keywords: construction, lean, lean manufacturing, waste

Procedia PDF Downloads 268
6681 Assessment of Human Factors Analysis and Classification System in Construction Accident Prevention

Authors: Zakari Mustapha, Clinton Aigbavboa, Wellington Didi Thwala

Abstract:

Majority of the incidents and accidents in complex high-risk systems that exist in the construction industry and other sectors have been attributed to unsafe acts of workers. The purpose of this paper was to asses Human Factors Analysis and Classification System (HFACS) in construction accident prevention. The study was conducted through the use of secondary data from journals, books and internet to achieve the objective of the study. The review of literature looked into details of different views from different scholars about HFACS framework in accidents investigations. It further highlighted on various sections or disciplines of accident occurrences in human performance within the construction. The findings from literature review showed that unsafe acts of a worker and unsafe working conditions are the two major causes of accident in the construction industry.Most significant factor in the cause of site accident in the construction industry is unsafe acts of a worker. The findings also show how the application of HFACS framework in the investigation of accident will lead to the identification of common trends. Further findings show that provision for the prevention of accident will be made based on past accident records to identify and prioritize where intervention is needed within the construction industry.

Keywords: accident, construction, HFACS, unsafe acts

Procedia PDF Downloads 306
6680 A Social Network Analysis for Formulating Construction Defect Generation Mechanisms

Authors: Hamad Aljassmi, Sangwon Han

Abstract:

Various solutions for preventing construction defects have been suggested. However, a construction company may have difficulties adopting all these suggestions due to financial and practical constraints. Based on this recognition, this paper aims to identify the most significant defect causes and formulate their defect generation mechanism in order to help a construction company to set priorities of its defect prevention strategies. For this goal, we conducted a questionnaire survey of 106 industry professionals and identified five most significant causes including: (1) organizational culture, (2) time pressure and constraints, (3) workplace quality system, (4) financial constraints upon operational expenses and (5) inadequate employee training or learning opportunities.

Keywords: defect, quality, failure, risk

Procedia PDF Downloads 605
6679 Modern Construction Methods and Technologies and Their Impacts on Construction Projects

Authors: Michael Anthony Doherty

Abstract:

Modern Methods of Construction (MMC) is a significant topic in the construction industry; while reviewing (MMC) over different fields that are significant in the modern construction world, the following areas were assessed where (MMC) is developing, supply chain management, automation, digital technology, and new construction technologies. Different methods were considered as an approach to research and exploring areas highlighted within the construction industry that are making advancements using Modern Methods of Construction Methods and Technologies (MCMTs). The research was conducted using the following methodologies, literature review of academic sources, primary and secondary data sources, questionaries, and interviews. The paper is composed of two parts, firstly a literature review and secondly a questionnaire used as the basis for interviews were utilised to achieve the following key objectives: to identify (MCMTs) being implemented in the construction industry, research and compile information with regards to these methods, determine their purpose and their application in the industry, establishing what (MCMTs) are being used in the industry while also determining the success of the methods. The research considers the evolution and development of these methods in projects and within the industry itself. Major findings were as follows; automation technologies such as robotics, offsite fabrication utilising automated production lines are increasingly part of project execution, digital technologies such as AR and VR are increasingly utilised in project co-ordination, (MMCTs) are proving to be a solution to the construction industry problems such as a lack of skilled workforce, hazardous work tasks, and situations, new construction technologies are available and finding their place in mainstream construction, (SCM) and (GSCM) are evolving to new levels using new systems and technologies such as block chain technology as well as Company Size and Project size influence the use of (MMCTs) and the adoption of (MMCTS). In summary the paper endeavours to identify and detail how areas of (MMCTs) are developing and are gaining traction within mainstream construction.

Keywords: automation, digital technology, new construction technologies, supply chain management

Procedia PDF Downloads 48
6678 Effect of Baking Temperature on the Mechanical Properties of Reinforced Clayey Soil

Authors: Gul Muhammad, Amanullah Marri, Asif Abbas

Abstract:

Thermal treatment changes the physical and mechanical properties of clayey soils. Thermally treated soils have been used since ancient times for making trails for access and bricks for residence. In this study, it has been focused to observe and analyze the effect of baking (burning) temperature on the mechanical properties of clayey soils usually used for the construction of adobe houses in the rural areas of many of the developing countries. In the first stage of experimental work, a series of tests on clayey soil moulds (100 mm height and 50 mm diameter in size) added different percentages of lime and wheat straw (typically 2%, 4%, 6%, 8%, and 10%) were conducted. In the second stage; samples were made of clayey soils and were subjected to six level of temperatures i.e., 25, 100, 200, 300, 400, and 500⁰C. In the third stage, the moulds of clayey soil were submerged in water prior to testing in order to investigate the flood resilience of the moulds prepared with and without the addition of lime and wheat straw. The experimental results suggest that samples with 6% of lime content and on 2% of wheat straw contents have shown the maximum value of compressive strength. The effect of baking temperature on the clayey soils has shown that maximum UCS is obtained at 200⁰C. The results also suggest reinforcement with 2% wheat straw, give 70.8% increase in the compressive strength compared to soil only, whereas the flooding resilience can be better resist by adding 6% lime and 2% wheat straw.

Keywords: baked temperature, submersion, lime, uniaxial, wheat straw

Procedia PDF Downloads 259
6677 Effects of Hypoxic Duration at Different Growth Stages on Yield Potential of Waxy Corn (Zea mays L.)

Authors: S. Boonlertnirun, R. Suvannasara, K. Boonlertnirun

Abstract:

Hypoxia has negative effects on growth and crop yield, its severity is so varied depending on crop growth stages, duration of hypoxia and crop species. The objective was to evaluate the sensitive growth stage and the duration of hypoxia negatively affecting growth and yield of waxy corn. Pot experiment was conducted using a split plot in randomized complete block with 3 growth stages: V3 (3-4 true leaves), V7 (7-8 true leaves), and R1 (silking stage), and three hypoxic durations: 6, 9, and 12 days, in an open–ended outdoor greenhouse during January to March 2013. The results revealed that different growth stages had significantly (p < 0.5) different responses to hypoxia, seeing that the sensitive growth stage affecting plant height, yield and yield components was mostly detected in V7 growth stage whereas leaf greenness and days to silking were sensitive to hypoxia at R1 growth stage. Different hypoxic durations significantly affected the yield and yield components, hypoxic duration of twelve days showed the most negative effect greater than the others. In this present study, it can be concluded that waxy corn plants were waterlogged at V7 growth stage for twelve days had the most negative effect on yield and yield components.

Keywords: hypoxia duration, waxy corn, growth stage, Zea mays L.

Procedia PDF Downloads 371
6676 The Role of Piaget's Theory in Conjecture via Analogical Reasoning

Authors: Supratman Ahman Maedi

Abstract:

The construction of knowledge is the goal of learning. The purpose of this research is to know how the role of Piaget theory in allegation via analogy reasoning. This study uses Think out loads when troubleshooting. To explore conjecturing via analogical reasoning is given the question of open analogy. The result: conjecture via analogical reasoning has been done by students in the construction of knowledge, in conjecture there are differences in thinking flow depending on the basic knowledge of the students, in the construction of knowledge occurs assimilation and accommodation problems, strategies and relationships.

Keywords: analogical reasoning, conjecturing, knowledge construction, Piaget's theory

Procedia PDF Downloads 306
6675 Exploration of Building Information Modelling Software to Develop Modular Coordination Design Tool for Architects

Authors: Muhammad Khairi bin Sulaiman

Abstract:

The utilization of Building Information Modelling (BIM) in the construction industry has provided an opportunity for designers in the Architecture, Engineering and Construction (AEC) industry to proceed from the conventional method of using manual drafting to a way that creates alternative designs quickly, produces more accurate, reliable and consistent outputs. By using BIM Software, designers can create digital content that manipulates the use of data using the parametric model of BIM. With BIM software, more alternative designs can be created quickly and design problems can be explored further to produce a better design faster than conventional design methods. Generally, BIM is used as a documentation mechanism and has not been fully explored and utilised its capabilities as a design tool. Relative to the current issue, Modular Coordination (MC) design as a sustainable design practice is encouraged since MC design will reduce material wastage through standard dimensioning, pre-fabrication, repetitive, modular construction and components. However, MC design involves a complex process of rules and dimensions. Therefore, a tool is needed to make this process easier. Since the parameters in BIM can easily be manipulated to follow MC rules and dimensioning, thus, the integration of BIM software with MC design is proposed for architects during the design stage. With this tool, there will be an improvement in acceptance and practice in the application of MC design effectively. Consequently, this study will analyse and explore the function and customization of BIM objects and the capability of BIM software to expedite the application of MC design during the design stage for architects. With this application, architects will be able to create building models and locate objects within reference modular grids that adhere to MC rules and dimensions. The parametric modeling capabilities of BIM will also act as a visual tool that will further enhance the automation of the 3-Dimensional space planning modeling process. (Method) The study will first analyze and explore the parametric modeling capabilities of rule-based BIM objects, which eventually customize a reference grid within the rules and dimensioning of MC. Eventually, the approach will further enhance the architect's overall design process and enable architects to automate complex modeling, which was nearly impossible before. A prototype using a residential quarter will be modeled. A set of reference grids guided by specific MC rules and dimensions will be used to develop a variety of space planning and configuration. With the use of the design, the tool will expedite the design process and encourage the use of MC Design in the construction industry.

Keywords: building information modeling, modular coordination, space planning, customization, BIM application, MC space planning

Procedia PDF Downloads 67
6674 A Proposal of Advanced Key Performance Indicators for Assessing Six Performances of Construction Projects

Authors: Wi Sung Yoo, Seung Woo Lee, Youn Kyoung Hur, Sung Hwan Kim

Abstract:

Large-scale construction projects are continuously increasing, and the need for tools to monitor and evaluate the project success is emphasized. At the construction industry level, there are limitations in deriving performance evaluation factors that reflect the diversity of construction sites and systems that can objectively evaluate and manage performance. Additionally, there are difficulties in integrating structured and unstructured data generated at construction sites and deriving improvements. In this study, we propose the Key Performance Indicators (KPIs) to enable performance evaluation that reflects the increased diversity of construction sites and the unstructured data generated, and present a model for measuring performance by the derived indicators. The comprehensive performance of a unit construction site is assessed based on 6 areas (Time, Cost, Quality, Safety, Environment, Productivity) and 26 indicators. We collect performance indicator information from 30 construction sites that meet legal standards and have been successfully performed. And We apply data augmentation and optimization techniques into establishing measurement standards for each indicator. In other words, the KPI for construction site performance evaluation presented in this study provides standards for evaluating performance in six areas using institutional requirement data and document data. This can be expanded to establish a performance evaluation system considering the scale and type of construction project. Also, they are expected to be used as a comprehensive indicator of the construction industry and used as basic data for tracking competitiveness at the national level and establishing policies.

Keywords: key performance indicator, performance measurement, structured and unstructured data, data augmentation

Procedia PDF Downloads 12
6673 Impact of Construction Risk Factors into Actual Construction Price in PPP Projects

Authors: Saleh Alzahrani, Halim Boussabaine

Abstract:

The majority of Public Private Partnership (PPP) are developed based on the rationale that the design, construction, operation, and financing of a public project is to be awarded to a private party within a single contractual framework. PPP project risks normally include the development and construction of a new asset as well as its operation for decades. Undoubtedly the most serious consequences of risks during the construction period are price and time overruns. These events are amongst the most broadly used scenarios in value for money analysis risks. The sources of risk change over the life cycle of a PPP project. In traditional procurement, the public sector normally has to cover all price distress from these risks. At least there is plenty evidence to suggest that price distress is a norm in some of the projects that are delivered under traditional procurement. This paper will find the impact of construction risk factors into actual construction price into PPP projects. The paper will present a brief literature review on PPP risk pricing strategies, and then using system dynamics (SD) to analyses of the risks associated with the estimated project price. Based on the finding from these analyses a risk pricing association model is presented and discussed. The paper concludes with thoughts for future research.

Keywords: Public Private Partnership (PPP), Risk, Risk Pricing, System Dynamics (SD), construction price

Procedia PDF Downloads 544
6672 Traditional Drawing, BIM and Erudite Design Process

Authors: Maryam Kalkatechi

Abstract:

Nowadays, parametric design, scientific analysis, and digital fabrication are dominant. Many architectural practices are increasingly seeking to incorporate advanced digital software and fabrication in their projects. Proposing an erudite design process that combines digital and practical aspects in a strong frame within the method was resulted from the dissertation research. The digital aspects are the progressive advancements in algorithm design and simulation software. These aspects have assisted the firms to develop more holistic concepts at the early stage and maintain collaboration among disciplines during the design process. The erudite design process enhances the current design processes by encouraging the designer to implement the construction and architecture knowledge within the algorithm to make successful design processes. The erudite design process also involves the ongoing improvements of applying the new method of 3D printing in construction. This is achieved through the ‘data-sketches’. The term ‘data-sketch’ was developed by the author in the dissertation that was recently completed. It accommodates the decisions of the architect on the algorithm. This paper introduces the erudite design process and its components. It will summarize the application of this process in development of the ‘3D printed construction unit’. This paper contributes to overlaying the academic and practice with advanced technology by presenting a design process that transfers the dominance of tool to the learned architect and encourages innovation in design processes.

Keywords: erudite, data-sketch, algorithm design in architecture, design process

Procedia PDF Downloads 258
6671 3-D Visualization and Optimization for SISO Linear Systems Using Parametrization of Two-Stage Compensator Design

Authors: Kazuyoshi Mori, Keisuke Hashimoto

Abstract:

In this paper, we consider the two-stage compensator designs of SISO plants. As an investigation of the characteristics of the two-stage compensator designs, which is not well investigated yet, of SISO plants, we implement three dimensional visualization systems of output signals and optimization system for SISO plants by the parametrization of stabilizing controllers based on the two-stage compensator design. The system runs on Mathematica by using “Three Dimensional Surface Plots,” so that the visualization can be interactively manipulated by users. In this paper, we use the discrete-time LTI system model. Even so, our approach is the factorization approach, so that the result can be applied to many linear models.

Keywords: linear systems, visualization, optimization, Mathematica

Procedia PDF Downloads 281
6670 3rd Generation Modular Execution: A Global Breakthrough in Modular Facility Construction System

Authors: Sean Bryner S. Rey, Eric Tanjutco

Abstract:

Modular execution strategies are performed to address the various challenges of any projects and are implemented on each project phase that covers Engineering, Procurement, Fabrication and Construction. It was until the recent years that the intent to surpass mechanical modularization approach were conceptualized to give solution to much greater demands of project components such as site location and adverse weather condition, material sourcing, construction schedule, safety risks and overall plot layout and allocation. The intent of this paper is to introduce the 3rd Generation Modular Execution with an overview of its advantages on project execution and will give emphasis on Engineering, Construction, Operation and Maintenance. Most importantly, the paper will present the key differentiator of 3rd Gen modular execution against other conventional project execution and the merits it bears for the industry.

Keywords: 3rd generation modular, process block, construction, operation & maintenance