5449 Empirical Study of Correlation between the Cost Performance Index Stability and the Project Cost Forecast Accuracy in Construction Projects
Authors: Amin AminiKhafri, James M. Dawson-Edwards, Ryan M. Simpson, Simaan M. AbouRizk
Abstract:
Earned value management (EVM) has been introduced as an integrated method to combine schedule, budget, and work breakdown structure (WBS). EVM provides various indices to demonstrate project performance including the cost performance index (CPI). CPI is also used to forecast final project cost at completion based on the cost performance during the project execution. Knowing the final project cost during execution can initiate corrective actions, which can enhance project outputs. CPI, however, is not constant during the project, and calculating the final project cost using a variable index is an inaccurate and challenging task for practitioners. Since CPI is based on the cumulative progress values and because of the learning curve effect, CPI variation dampens and stabilizes as project progress. Although various definitions for the CPI stability have been proposed in literature, many scholars have agreed upon the definition that considers a project as stable if the CPI at 20% completion varies less than 0.1 from the final CPI. While 20% completion point is recognized as the stability point for military development projects, construction projects stability have not been studied. In the current study, an empirical study was first conducted using construction project data to determine the stability point for construction projects. Early findings have demonstrated that a majority of construction projects stabilize towards completion (i.e., after 70% completion point). To investigate the effect of CPI stability on cost forecast accuracy, the correlation between CPI stability and project cost at completion forecast accuracy was also investigated. It was determined that as projects progress closer towards completion, variation of the CPI decreases and final project cost forecast accuracy increases. Most projects were found to have 90% accuracy in the final cost forecast at 70% completion point, which is inlined with findings from the CPI stability findings. It can be concluded that early stabilization of the project CPI results in more accurate cost at completion forecasts.Keywords: cost performance index, earned value management, empirical study, final project cost
Procedia PDF Downloads 1565448 Benefits of Construction Management Implications and Processes by Projects Managers on Project Completion
Authors: Mamoon Mousa Atout
Abstract:
Projects managers in construction industry usually face a difficult organizational environment especially if the project is unique. The organization lacks the processes to practice construction management correctly, and the executive’s technical managers who have lack of experience in playing their role and responsibilities correctly. Project managers need to adopt best practices that allow them to do things effectively to make sure that the project can be delivered without any delay even though the executive’s technical managers should follow a certain process to avoid any factor might cause any delay during the project life cycle. The purpose of the paper is to examine the awareness level of projects managers about construction management processes, tools, techniques and implications to complete projects on time. The outcome and the results of the study are prepared based on the designed questionnaires and interviews conducted with many project managers. The method used in this paper is a quantitative study. A survey with a sample of 100 respondents was prepared and distributed in a construction company in Dubai, which includes nine questions to examine the level of their awareness. This research will also identify the necessary benefits of processes of construction management that has to be adopted by projects managers to mitigate the maximum potential problems which might cause any delay to the project life cycle.Keywords: construction management, project objectives, resource planing and scheduling, project completion
Procedia PDF Downloads 4025447 Application of Simulation of Discrete Events in Resource Management of Massive Concreting
Authors: Mohammad Amin Hamedirad, Seyed Javad Vaziri Kang Olyaei
Abstract:
Project planning and control are one of the most critical issues in the management of construction projects. Traditional methods of project planning and control, such as the critical path method or Gantt chart, are not widely used for planning projects with discrete and repetitive activities, and one of the problems of project managers is planning the implementation process and optimal allocation of its resources. Massive concreting projects is also a project with discrete and repetitive activities. This study uses the concept of simulating discrete events to manage resources, which includes finding the optimal number of resources considering various limitations such as limitations of machinery, equipment, human resources and even technical, time and implementation limitations using analysis of resource consumption rate, project completion time and critical points analysis of the implementation process. For this purpose, the concept of discrete-event simulation has been used to model different stages of implementation. After reviewing the various scenarios, the optimal number of allocations for each resource is finally determined to reach the maximum utilization rate and also to reduce the project completion time or reduce its cost according to the existing constraints. The results showed that with the optimal allocation of resources, the project completion time could be reduced by 90%, and the resulting costs can be reduced by up to 49%. Thus, allocating the optimal number of project resources using this method will reduce its time and cost.Keywords: simulation, massive concreting, discrete event simulation, resource management
Procedia PDF Downloads 1495446 A Risk-Based Approach to Construction Management
Authors: Chloe E. Edwards, Yasaman Shahtaheri
Abstract:
Risk management plays a fundamental role in project planning and delivery. The purpose of incorporating risk management into project management practices is to identify and address uncertainties related to key project-related activities. The uncertainties, known as risk events, can relate to project deliverables that are quantifiable and are often measured by impact to project schedule, cost, or environmental impact. Risk management should be incorporated as an iterative practice throughout the planning, execution, and commissioning phases of a project. This paper specifically examines how risk management contributes to effective project planning and delivery through a case study of a transportation project. This case study focused solely on impacts to project schedule regarding three milestones: readiness for delivery, readiness for testing and commissioning, and completion of the facility. The case study followed the ISO 31000: Risk Management – Guidelines. The key factors that are outlined by these guidelines include understanding the scope and context of the project, conducting a risk assessment including identification, analysis, and evaluation, and lastly, risk treatment through mitigation measures. This process requires continuous consultation with subject matter experts and monitoring to iteratively update the risks accordingly. The risk identification process led to a total of fourteen risks related to design, permitting, construction, and commissioning. The analysis involved running 1,000 Monte Carlo simulations through @RISK 8.0 Industrial software to determine potential milestone completion dates based on the project baseline schedule. These dates include the best case, most likely case, and worst case to provide an estimated delay for each milestone. Evaluation of these results provided insight into which risks were the highest contributors to the projected milestone completion dates. Based on the analysis results, the risk management team was able to provide recommendations for mitigation measures to reduce the likelihood of risks occurring. The risk management team also provided recommendations for managing the identified risks and project activities moving forward to meet the most likely or best-case milestone completion dates.Keywords: construction management, monte carlo simulation, project delivery, risk assessment, transportation engineering
Procedia PDF Downloads 1085445 The Influence of Beta Shape Parameters in Project Planning
Authors: Αlexios Kotsakis, Stefanos Katsavounis, Dimitra Alexiou
Abstract:
Networks can be utilized to represent project planning problems, using nodes for activities and arcs to indicate precedence relationship between them. For fixed activity duration, a simple algorithm calculates the amount of time required to complete a project, followed by the activities that comprise the critical path. Program Evaluation and Review Technique (PERT) generalizes the above model by incorporating uncertainty, allowing activity durations to be random variables, producing nevertheless a relatively crude solution in planning problems. In this paper, based on the findings of the relevant literature, which strongly suggests that a Beta distribution can be employed to model earthmoving activities, we utilize Monte Carlo simulation, to estimate the project completion time distribution and measure the influence of skewness, an element inherent in activities of modern technical projects. We also extract the activity criticality index, with an ultimate goal to produce more accurate planning estimations.Keywords: beta distribution, PERT, Monte Carlo simulation, skewness, project completion time distribution
Procedia PDF Downloads 1505444 A Probability Analysis of Construction Project Schedule Using Risk Management Tool
Authors: A. L. Agarwal, D. A. Mahajan
Abstract:
Construction industry tumbled along with other industry/sectors during recent economic crash. Construction business could not regain thereafter and still pass through slowdown phase, resulted many real estate as well as infrastructure projects not completed on schedule and within budget. There are many theories, tools, techniques with software packages available in the market to analyze construction schedule. This study focuses on the construction project schedule and uncertainties associated with construction activities. The infrastructure construction project has been considered for the analysis of uncertainty on project activities affecting project duration and analysis is done using @RISK software. Different simulation results arising from three probability distribution functions are compiled to benefit construction project managers to plan more realistic schedule of various construction activities as well as project completion to document in the contract and avoid compensations or claims arising out of missing the planned schedule.Keywords: construction project, distributions, project schedule, uncertainty
Procedia PDF Downloads 3515443 Analyze and Improve Project Delivery Time Enhancing Business Management System of Review and Approval Process for Project Design Submittals
Authors: Abdulaziz Alnajem, Amit Sharma
Abstract:
Business Case: Project delivery and enhancing activities' completion in the shortest possible time is critical during execution to proceed with the subsequent phases of Procurement, C & C phases of Contracts to have the required Production facilities/Infrastructure in place to achieve the Company strategic objective of 4.0 MBOPD oil production. SOR (Statement of requirement): Design and Engineering phase of Projects execution takes a long time. It is observed that, in most of the cases, company has crossed the Project Design Submittals review time as per the Contract/Company Standards, resulting into delays in projects completion, and cost impact to the company. Study Scope: Scope of the study covers the process from date of first submission of D & E documents by the contractor to final approval by the controlling team to proceed with the procurement of materials. This scope covers projects handled by the company’s project management teams and includes only the internal review process by the company.Keywords: business management system, project management, oil and gas, analysis, improvement, design, delays
Procedia PDF Downloads 2195442 Project Design Deliverables Sequence (PDD)
Authors: Nahed Al-Hajeri
Abstract:
There are several reasons which lead to a delay in project completion, out of all, one main reason is the delay in deliverable processing, i.e. submission and review of documents. Most of the project cycles start with a list of deliverables but without a sequence of submission of the same, means without a direction to move, leading to overlapping of activities and more interdependencies. Hence Project Design Deliverables (PDD) is developed as a solution to Organize Transmittals (Documents/Drawings) received from contractors/consultants during different phases of an EPC (Engineering, Procurement, and Construction) projects, which gives proper direction to the stakeholders from the beginning, to reduce inter-discipline dependency, avoid overlapping of activities, provide a list of deliverables, sequence of activities, etc. PDD attempts to provide a list and sequencing of the engineering documents/drawings required during different phases of a Project which will benefit both client and Contractor in performing planned activities through timely submission and review of deliverables. This helps in ensuring improved quality and completion of Project in time. The successful implementation begins with a detailed understanding the specific challenges and requirements of the project. PDD will help to learn about vendor document submissions including general workflow, sequence and monitor the submission and review of the deliverables from the early stages of Project. This will provide an overview for the Submission of deliverables by the concerned during the projects in proper sequence. The goal of PDD is also to hold responsible and accountability of all stakeholders during complete project cycle. We believe that successful implementation of PDD with a detailed list of documents and their sequence will help organizations to achieve the project target.Keywords: EPC (Engineering, Procurement, and Construction), project design deliverables (PDD), econometrics sciences, management sciences
Procedia PDF Downloads 4005441 Construction Project Planning Using Fuzzy Critical Path Approach
Authors: Omar M. Aldenali
Abstract:
Planning is one of the most important phases of the management science and network planning, which represents the project activities relationship. Critical path is one of the project management techniques used to plan and control the execution of a project activities. The objective of this paper is to implement a fuzzy logic approach to arrange network planning on construction projects. This method is used to finding out critical path in the fuzzy construction project network. The trapezoidal fuzzy numbers are used to represent the activity construction project times. A numerical example that represents a house construction project is introduced. The critical path method is implemented on the fuzzy construction network activities, and the results showed that this method significantly affects the completion time of the construction projects.Keywords: construction project, critical path, fuzzy network project, planning
Procedia PDF Downloads 1445440 Cost Overruns in Mega Projects: Project Progress Prediction with Probabilistic Methods
Authors: Yasaman Ashrafi, Stephen Kajewski, Annastiina Silvennoinen, Madhav Nepal
Abstract:
Mega projects either in construction, urban development or energy sectors are one of the key drivers that build the foundation of wealth and modern civilizations in regions and nations. Such projects require economic justification and substantial capital investment, often derived from individual and corporate investors as well as governments. Cost overruns and time delays in these mega projects demands a new approach to more accurately predict project costs and establish realistic financial plans. The significance of this paper is that the cost efficiency of megaprojects will improve and decrease cost overruns. This research will assist Project Managers (PMs) to make timely and appropriate decisions about both cost and outcomes of ongoing projects. This research, therefore, examines the oil and gas industry where most mega projects apply the classic methods of Cost Performance Index (CPI) and Schedule Performance Index (SPI) and rely on project data to forecast cost and time. Because these projects are always overrun in cost and time even at the early phase of the project, the probabilistic methods of Monte Carlo Simulation (MCS) and Bayesian Adaptive Forecasting method were used to predict project cost at completion of projects. The current theoretical and mathematical models which forecast the total expected cost and project completion date, during the execution phase of an ongoing project will be evaluated. Earned Value Management (EVM) method is unable to predict cost at completion of a project accurately due to the lack of enough detailed project information especially in the early phase of the project. During the project execution phase, the Bayesian adaptive forecasting method incorporates predictions into the actual performance data from earned value management and revises pre-project cost estimates, making full use of the available information. The outcome of this research is to improve the accuracy of both cost prediction and final duration. This research will provide a warning method to identify when current project performance deviates from planned performance and crates an unacceptable gap between preliminary planning and actual performance. This warning method will support project managers to take corrective actions on time.Keywords: cost forecasting, earned value management, project control, project management, risk analysis, simulation
Procedia PDF Downloads 4055439 Increase of Completion Rate of Nursing Care during Therapeutic Hypothermia in Critical Patients
Authors: Yi-Jiun Chou, Ying-Hsuan Li, Yi-Jung Liu, Hsin-Yu Chiang, Hsuan-Ching Wang
Abstract:
Background: Patients received therapeutic hypothermia (TH) after resuscitation from cardiac arrest are more dependent on continue and intensive nursing care. It involves many difficult steps, especially achieving target body temperature. To our best knowledge, there is no consensus or recommended standards on nursing practice of TH. Aim: The aim of this study is to increase the completion rate of nursing care at therapeutic hypothermia. Methods: We took five measures: (1) Amendment of nursing standards of therapeutic hypothermia; (2) Amendment of TH checklist items to nursing records; (3) Establishment of monitor procedure; (4) Design each period of TH care reminder cards; (5) Providing in-service training sections of TH for ICU nursing staff. Outcomes: The completion rate of nursing care at therapeutic hypothermia increased from 78.1% to 89.3%. Conclusion: The project team not only increased the completion rate but also improved patient safety and quality of care.Keywords: therapeutic hypothermia, nursing, critical care, quality of care
Procedia PDF Downloads 4225438 Genetic Algorithms Multi-Objective Model for Project Scheduling
Authors: Elsheikh Asser
Abstract:
Time and cost are the main goals of the construction project management. The first schedule developed may not be a suitable schedule for beginning or completing the project to achieve the target completion time at a minimum total cost. In general, there are trade-offs between time and cost (TCT) to complete the activities of a project. This research presents genetic algorithms (GAs) multi-objective model for project scheduling considering different scenarios such as least cost, least time, and target time.Keywords: genetic algorithms, time-cost trade-off, multi-objective model, project scheduling
Procedia PDF Downloads 4135437 Analysis of Delays during Initial Phase of Construction Projects and Mitigation Measures
Authors: Sunaitan Al Mutairi
Abstract:
A perfect start is a key factor for project completion on time. The study examined the effects of delayed mobilization of resources during the initial phases of the project. This paper mainly highlights the identification and categorization of all delays during the initial construction phase and their root cause analysis with corrective/control measures for the Kuwait Oil Company oil and gas projects. A relatively good percentage of the delays identified during the project execution (Contract award to end of defects liability period) attributed to mobilization/preliminary activity delays. Data analysis demonstrated significant increase in average project delay during the last five years compared to the previous period. Contractors had delays/issues during the initial phase, which resulted in slippages and progressively increased, resulting in time and cost overrun. Delays/issues not mitigated on time during the initial phase had very high impact on project completion. Data analysis of the delays for the past five years was carried out using trend chart, scatter plot, process map, box plot, relative importance index and Pareto chart. Construction of any project inside the Gathering Centers involves complex management skills related to work force, materials, plant, machineries, new technologies etc. Delay affects completion of projects and compromises quality, schedule and budget of project deliverables. Works executed as per plan during the initial phase and start-up duration of the project construction activities resulted in minor slippages/delays in project completion. In addition, there was a good working environment between client and contractor resulting in better project execution and management. Mainly, the contractor was on the front foot in the execution of projects, which had minimum/no delays during the initial and construction period. Hence, having a perfect start during the initial construction phase shall have a positive influence on the project success. Our research paper studies each type of delay with some real example supported by statistic results and suggests mitigation measures. Detailed analysis carried out with all stakeholders based on impact and occurrence of delays to have a practical and effective outcome to mitigate the delays. The key to improvement is to have proper control measures and periodic evaluation/audit to ensure implementation of the mitigation measures. The focus of this research is to reduce the delays encountered during the initial construction phase of the project life cycle.Keywords: construction activities delays, delay analysis for construction projects, mobilization delays, oil & gas projects delays
Procedia PDF Downloads 3185436 Project Progress Prediction in Software Devlopment Integrating Time Prediction Algorithms and Large Language Modeling
Authors: Dong Wu, Michael Grenn
Abstract:
Managing software projects effectively is crucial for meeting deadlines, ensuring quality, and managing resources well. Traditional methods often struggle with predicting project timelines accurately due to uncertain schedules and complex data. This study addresses these challenges by combining time prediction algorithms with Large Language Models (LLMs). It makes use of real-world software project data to construct and validate a model. The model takes detailed project progress data such as task completion dynamic, team Interaction and development metrics as its input and outputs predictions of project timelines. To evaluate the effectiveness of this model, a comprehensive methodology is employed, involving simulations and practical applications in a variety of real-world software project scenarios. This multifaceted evaluation strategy is designed to validate the model's significant role in enhancing forecast accuracy and elevating overall management efficiency, particularly in complex software project environments. The results indicate that the integration of time prediction algorithms with LLMs has the potential to optimize software project progress management. These quantitative results suggest the effectiveness of the method in practical applications. In conclusion, this study demonstrates that integrating time prediction algorithms with LLMs can significantly improve the predictive accuracy and efficiency of software project management. This offers an advanced project management tool for the industry, with the potential to improve operational efficiency, optimize resource allocation, and ensure timely project completion.Keywords: software project management, time prediction algorithms, large language models (LLMS), forecast accuracy, project progress prediction
Procedia PDF Downloads 805435 The Aspect of Urban Inequality after Urban Redevelopment Projects
Authors: Sungik Kang, Ja-Hoon Koo
Abstract:
Globally, urban environments have become unequal, and cities have been segmented by income class. It is predicted that urban inequality has arisen by urban redevelopment and reconstruction projects that improve the urban environment and innovate cities. This study aims to analyze the occurrence and characteristics of urban inequality by using the housing price and sale price and demonstrating the correlation with the urban redevelopment project. This study measures 14 years of urban inequality index for 25 autonomous districts in Seoul and analyzes the correlation between urban inequality with urban redevelopment projects. As a conclusion of this study, first, the urban inequality index of Seoul has been continuously rising since 2015. Trends from 2006 to 2019 have been in U-curved shape in between 2015. In 2019, Seoul's urban inequality index was 0.420, a level similar to that of the 2007 financial crisis. Second, the correlation between urban redevelopment and urban inequality was not statistically significant. Therefore, we judged that urban redevelopment's scale or project structure has nothing with urban inequality. Third, while district designation of urban reconstruction temporarily alleviates urban inequality, the completion of the project increases urban inequality. When designating a district, urban inequality is likely to decrease due to decreased outdated housing transactions. However, the correlation with urban inequality increases as expensive houses has been placed after project completion.Keywords: urban inequality, urban redevelopment projects, urban reconstruction projects, housing price inequality, panel analysis
Procedia PDF Downloads 2075434 The Effect of Critical Activity on Critical Path and Project Duration in Precedence Diagram Method
Abstract:
The additional relationships i.e., start-to-start, finish-to-finish, and start-to-finish, between activity in Precedence Diagram Method (PDM) provides a more flexible schedule than traditional Critical Path Method (CPM). But, changing the duration of critical activities in the PDM network will have an anomalous effect on the critical path and the project completion date. In this study, we classified the critical activities in two groups i.e., 1. activity on single critical path and 2. activity on multi-critical paths, and six classes i.e., normal, reverse, neutral, perverse, decrease-reverse and increase-normal, based on their effects on project duration in PDM. Furthermore, we determined the maximum float of time by which the duration each type of critical activities can be changed without effecting the project duration. This study would help the project manager to clearly understand the behavior of each critical activity on critical path, and he/she would be able to change the project duration by shortening or lengthening activities based on project budget and project deadline.Keywords: construction management, critical path method, project scheduling network, precedence diagram method
Procedia PDF Downloads 2245433 Feasibility Studies in Public Construction Projects in South Africa: Barriers and Implications
Authors: Kenneth O. Otasowie, Matthew Ikuabe, Clinton Aigbavboa, Ayodeji Oke
Abstract:
The practice of feasibility studies plays a huge role in the success of construction projects. Feasibility studies according to several research should be the reason for embarking on any project. However, it has been discovered that in South Africa (SA), feasibility studies are mainly done in the private sector construction but skipped in the construction of most public projects. Hence, this study aims to evaluate the barriers to feasibility studies practice in public projects and the implications. A survey design was adopted. A total number of One hundred and fifty (150) questionnaires were administered to Quantity Surveyors, Construction managers, Construction project managers, Project managers, Architects and Civil and Structural engineers in Guateng Province, SA and ninety (90) were returned and found suitable for analysis. Collected data was analysed using percentage, mean item score, standard deviation, one-sample t-test. The findings show that political interference and corruption are the most significant barriers to feasibility studies practice in the public construction projects in SA, while late project completion, poor quality infrastructure are among the implication of not conducting feasibility studies in SA public projects. Therefore, the study recommends the development of a framework for public projects execution that will reduce the interference of the political class in the country, that way the risk of late project completion and poor quality infrastructure will be mitigated.Keywords: arriers, feasibility studies, public construction, South Africa.
Procedia PDF Downloads 935432 The Significance of a Well-Defined Systematic Approach in Risk Management for Construction Projects within Oil Industry
Authors: Batool Ismaeel, Umair Farooq, Saad Mushtaq
Abstract:
Construction projects in the oil industry can be very complex, having unknown outcomes and uncertainties that cannot be easily predicted. Each project has its unique risks generated by a number of factors which, if not controlled, will impact the successful completion of the project mainly in terms of schedule, cost, quality, and safety. This paper highlights the historic risks associated with projects in the south and east region of Kuwait Oil Company (KOC) collated from the company’s lessons learned database. Starting from Contract Award through to handover of the project to the Asset owner, the gaps in project execution in terms of managing risk will be brought to discussion and where a well-defined systematic approach in project risk management reflecting many claims, change of scope, exceeding budget, delays in engineering phase as well as in the procurement and fabrication of long lead items should be adopted. This study focuses on a proposed feasible approach in risk management for engineering, procurement and construction (EPC) level projects including the various stakeholders involved in executing the works from International to local contractors and vendors in KOC. The proposed approach covers the areas categorized into organizational, design, procurement, construction, pre-commissioning, commissioning and project management in which the risks are identified and require management and mitigation. With the effective deployment and implementation of the proposed risk management system and the consideration of it as a vital key in achieving the project’s target, the outcomes will be more predictable in the future, and the risk triggers will be managed and controlled. The correct resources can be allocated on a timely basis for the company for avoiding any unpredictable outcomes during the execution of the project. It is recommended in this paper to apply this risk management approach as an integral part of project management and investigate further in the future, the effectiveness of this proposed system for newly awarded projects and compare the same with those projects of similar budget/complexity that have not applied this approach to risk management.Keywords: construction, project completion, risk management, uncertainties
Procedia PDF Downloads 1555431 The Impact of Management Competency, Project Team, and Process Design to Corporate Performance through Implementing the Self-Development ERP
Authors: Zeplin Jiwa Husada Tarigan, Sautma Ronni Basana, Widjojo Suprapto
Abstract:
Manufacturing companies in East Java develop their own ERP system or alter the ERP system which is developed by other companies to suit their needs. To make their own system, the companies mostly assign several employees from various departments to create a project team, and the employees are from the departments that are going to utilize the ERP system as the integrated data. The project team decides the making of the ERP system from the preparation stage until the going live implementation process. In designing the business process, the top management is working together with the project team until the project is accomplished. The completion of the ERP projects depends on the project to be undertaken itself, the strategy chosen to complete the project, the work method selection, the measurement system to monitor the project, the evaluation system of the project, and, in the end, the declaration of 'going live' of the ERP project. There is an increase in the business performance for the companies that have implemented the information technology or ERP as they manage to integrate all management functions within their companies. To investigate, some questionnaires are distributed to 100 manufacturing companies, and 90 questionnaires are returned; however, there are only 46 companies that develop their own ERP system, so the response rate is 46%. The result of data analysis using PLS shows that the management competency brings impacts to the project team and the process design. The process design is adjusted to the real process in order to implement the ERP, but it does not bring direct impacts to the business performance. The implementation of ERP brings positive impacts to the company business performance.Keywords: management competency, project team, process design, ERP implementation, business performance
Procedia PDF Downloads 2195430 Ranking the Factors That Influence the Construction Project Success: The Jordanian Perspective
Authors: Ghanim A. Bekr
Abstract:
Project success is what must be done for the project to be acceptable to the client, stakeholders and end-users who will be affected by the project. The study of project success and the critical success factors (CSFs) are the means adopted to improve the effectiveness of project. This research is conducted to make an attempt to identify which variables influence the success of project implementation. This study has selected, through an extensive literature review and interviews, (83) factors categorized in (7) groups that the questionnaire respondents were asked to score. The responses from 66 professionals with an average of 15 years of experience in different types of construction projects in Jordan were collected and analyzed using SPSS and most important factors for success for various success criteria are presented depending on the relative importance index to rank the categories. The research revealed the significant groups of factors are: Client related factors, Contractor’s related factors, Project Manager (PM) related factors, and Project management related factors. In addition the top ten sub factors are: Assertion of the client towards short time of the project, availability of skilled labor, Assertion of the client towards high level of the quality, capability of the client in taking risk, previous experience of the PM in similar projects, previous experience of the contractor in similar projects, decision making by the client/ the client’s representative at the right time, assertion of client towards low cost of project, experience in project management in previous projects, and flow of the information among parties. The results would be helpful to construction project professionals in taking proactive measures for successful completion of construction projects in Jordan.Keywords: construction projects, critical success factors, Jordan, project success
Procedia PDF Downloads 1635429 Use of Self-Monitoring Strategy on Homework Completion among Pupils with Learning Disabilities in Ondo State, Nigeria
Authors: Olusegun Omoluwa, Kolawole Israel Anthony
Abstract:
Pupils with learning disabilities are found in every classroom, but because learning disabilities cannot be seen, the condition is often too neglected. Unless these pupils are recognised and treated, they are likely to become educational discards. This study consequently attempted to determine effects of self-monitoring strategy on homework completion among pupils with learning disabilities. Ninety (90) participants were engaged in the study. Pre-test, post-test, control group quasi experimental design was adopted. Purposive sampling technique was used to select pupils with evidence of learning disabilities from three primary schools in Ondo State. Findings showed that self-monitoring strategy was significant in enhancing homework completion among pupils with learning disabilities. However, gender and self-esteem did not significantly contribute to homework completion. The study therefore recommended that measures such that would uncover unsettling academic, psychological and emotional deficiencies of these pupils through appropriate diagnosis should be undertaken by the parents and teachers, in order for them to have a sense of belonging in the society.Keywords: self monitoring, home work completion, learning dissabilities, learning
Procedia PDF Downloads 3535428 Project Knowledge Harvesting: The Case of Improving Project Performance through Project Knowledge Sharing Framework
Authors: Eng Rima Al-Awadhi, Abdul Jaleel Tharayil
Abstract:
In a project-centric organization like KOC, managing the knowledge of the project is of critical importance to the success of the project and the organization. However, due to the very nature and complexity involved, each project engagement generates a lot of 'learnings' that need to be factored into while new projects are initiated and thus avoid repeating the same mistake. But, many a time these learnings are localized and remains as ‘tacit knowledge’ leading to scope re-work, schedule overrun, adjustment orders, concession requests and claims. While KOC follows an asset based organization structure, with a multi-cultural and multi-ethnic workforce and larger chunk of the work is carried out through complex, long term project engagement, diffusion of ‘learnings’ across assets while dealing with the natural entropy of the organization is of great significance. Considering the relatively higher number of mega projects, it's important that the issues raised during the project life cycle are centrally harvested, analyzed and the ‘learnings’ from these issues are shared, absorbed and are in-turn utilized to enhance and refine the existing process and practices, leading to improve the project performance. One of the many factors contributing to the successful completion of a project on time is the reduction in the number of variations or concessions triggered during the project life cycle. The project process integrated knowledge sharing framework discusses the knowledge harvesting methodology adopted, the challenges faced, learnings acquired and its impact on project performance. The framework facilitates the proactive identification of issues that may have an impact on the overall quality of the project and improve performance.Keywords: knowledge harvesting, project integrated knowledge sharing, performance improvement, knowledge management, lessons learn
Procedia PDF Downloads 3975427 Overcoming the Impacts of Covid-19 Outbreak Using Value Integrated Project Delivery Model
Authors: G. Ramya
Abstract:
Value engineering is a systematic approach, widely used to optimize the design or process or product in the designing stage. It used to achieve the client's obligation by increasing the functionality and attain the targeted cost in the cost planning. Value engineering effectiveness and benefits decrease along with the progress of the project since the change in the scope of the work and design will account for more cost all along the lifecycle of the project. Integrating the value engineering with other project management activities will promote cost minimization, client satisfaction, and ensure early completion of the project in time. Previous research studies suggested that value engineering can integrate with other project delivery activities, but research studies unable to frame a model that collaborates the project management activities with the job plan of value engineering approach. I analyzed various project management activities and their synergy between each other. The project management activities and processes like a)risk analysis b)lifecycle cost analysis c)lean construction d)facility management e)Building information modelling f)Contract administration, collaborated, and project delivery model planned along with the RIBA plan of work. The key outcome of the research is a value-driven project delivery model, which will succeed in dealing with the economic impact, constraints and conflicts arise due to the COVID-19 outbreak in the Indian construction sector. Benefits associated with the structured framework is construction project delivery that ensures early contractor involvement, mutual risk sharing, and reviving the project with a cost overrun and delay back on track ,are discussed. Keywords: Value-driven project delivery model, Integration, RIBA plan of work Themes: Design EconomicsKeywords: value-driven project delivery model, Integration, RIBA
Procedia PDF Downloads 1215426 Impact of Project Leader's Style on the Success of the Projects
Authors: Saadia Khalid
Abstract:
This paper discusses the various leadership styles of project manager which lead to the success of a project since it is important for a project manager to understand and adopt the skills required to cope up with the modern challenges of any project. A project manager must be able to handle a project effectively and efficiently and be ready to assess the factors effecting success or failure of the project. A project manager must be capable of handling a project by managing, directing and leading the projects with requisite knowledge and skills. In this paper a project manager’s characteristics linkage to project success have been developed and analyzed for three different projects/industries. A web-based survey has also been carried out which revealed that specific leadership styles/traits can lead to better performance and success of organizations. Some basic factors like project complexity, the age, gender and nationality of the project manager and type of project also play a vital role in success of a project.Keywords: leadership style, project success, project management, project manager
Procedia PDF Downloads 4285425 The Choosing the Right Projects With Multi-Criteria Decision Making to Ensure the Sustainability of the Projects
Authors: Saniye Çeşmecioğlu
Abstract:
The importance of project sustainability and success has become increasingly significant due to the proliferation of external environmental factors that have decreased project resistance in contemporary times. The primary approach to forestall the failure of projects is to ensure their long-term viability through the strategic selection of projects as creating judicious project selection framework within the organization. Decision-makers require precise decision contexts (models) that conform to the company's business objectives and sustainability expectations during the project selection process. The establishment of a rational model for project selection enables organizations to create a distinctive and objective framework for the selection process. Additionally, for the optimal implementation of this decision-making model, it is crucial to establish a Project Management Office (PMO) team and Project Steering Committee within the organizational structure to oversee the framework. These teams enable updating project selection criteria and weights in response to changing conditions, ensuring alignment with the company's business goals, and facilitating the selection of potentially viable projects. This paper presents a multi-criteria decision model for selecting project sustainability and project success criteria that ensures timely project completion and retention. The model was developed using MACBETH (Measuring Attractiveness by a Categorical Based Evaluation Technique) and was based on broadcaster companies’ expectations. The ultimate results of this study provide a model that endorses the process of selecting the appropriate project objectively by utilizing project selection and sustainability criteria along with their respective weights for organizations. Additionally, the study offers suggestions that may ascertain helpful in future endeavors.Keywords: project portfolio management, project selection, multi-criteria decision making, project sustainability and success criteria, MACBETH
Procedia PDF Downloads 635424 Conflict Causes within Construction Projects; Conflict Interaction across Project Phases
Authors: Abdullah Mohammed Alshehri
Abstract:
The projects in the construction industry have significantly increased, given its contribution to the overall Gross Domestic Product (GDP) of the countries. Reflecting upon the complex nature and involvement of various agents, the study aims to analyze the conflicts cause within construction projects. Therefore, the study strived to come out with understanding the levels of conflict interaction across project phases. However, this conducted by investigating the association between antecedents and apparent conflicts inherent in. The study used a qualitative approach for collecting the data through a quantitative, semi-structured method. Formation of a questionnaire survey has been conducted for over 30 respondents. However, the survey came out with the identification of 25 conflict cause categories, which can take place in different construction project phases, including pre-design phase, pre-construction phase, construction phase, commissioning, and completion phase. For example, conflicts associated with inconsistencies or discrepancies within or between project documents, which took place at tendering time in the pre-construction phase were relatable with the selection of material specifications that should be supplied or used in the construction projects at the construction phase. Its analysis can provide comprehensive understanding, trace the root of the problem, which offers a roadmap to deepen the understanding of the conflict conditions and ‘course of action’ necessary for project management strategy actions toward avoiding or minimizing conflict causes at project life.Keywords: construction, conflict causes, levels, interaction, phases
Procedia PDF Downloads 1805423 Installation of an Inflatable Bladder and Sill Walls for Riverbank Erosion Protection and Improved Water Intake Zone Smokey Hill River – Salina, Kansas
Authors: Jeffrey A. Humenik
Abstract:
Environmental, Limited Liability Corporation (EMR) provided civil construction services to the U.S. Army Corps of Engineers, Kansas City District, for the placement of a protective riprap blanket on the west bank of the Smoky Hill River, construction of 2 shore abutments and the construction of a 140 foot long sill wall spanning the Smoky Hill River in Salina, Kansas. The purpose of the project was to protect the riverbank from erosion and hold back water to a specified elevation, creating a pool to ensure adequate water intake for the municipal water supply. Geotextile matting and riprap were installed for streambank erosion protection. An inflatable bladder (AquaDam®) was designed to the specific river dimension and installed to divert the river and allow for dewatering during the construction of the sill walls and cofferdam. AquaDam® consists of water filled polyethylene tubes to create aqua barriers and divert water flow or prevent flooding. A challenge of the project was the fact that 100% of the sill wall was constructed within an active river channel. The threat of flooding of the work area, damage to the aqua dam by debris, and potential difficulty of water removal presented a unique set of challenges to the construction team. Upon completion of the West Sill Wall, floating debris punctured the AquaDam®. The manufacturing and delivery of a new AquaDam® would delay project completion by at least 6 weeks. To keep the project ahead of schedule, the decision was made to construct an earthen cofferdam reinforced with rip rap for the construction of the East Abutment and East Sill Wall section. During construction of the west sill wall section, a deep scour hole was encountered in the wall alignment that prevented EMR from using the natural rock formation as a concrete form for the lower section of the sill wall. A formwork system was constructed, that allowed the west sill wall section to be placed in two horizontal lifts of concrete poured on separate occasions. The first sectional lift was poured to fill in the scour hole and act as a footing for the second sectional lift. Concrete wall forms were set on the first lift and anchored to the surrounding riverbed in a manner that the second lift was poured in a similar fashion as a basement wall. EMR’s timely decision to keep the project moving toward completion in the face of changing conditions enabled project completion two (2) months ahead of schedule. The use of inflatable bladders is an effective and cost-efficient technology to divert river flow during construction. However, a secondary plan should be part of project design in the event debris transported by river punctures or damages the bladders.Keywords: abutment, AquaDam®, riverbed, scour
Procedia PDF Downloads 1565422 Walking the Tightrope: Balancing Project Governance, Complexity, and Servant Leadership for Megaproject Success
Authors: Muhammad Shoaib Iqbal, Shih Ping Ho
Abstract:
Megaprojects are large-scale, complex ventures with significant financial investments, numerous stakeholders, and extended timelines, requiring meticulous management for successful completion. This study explores the interplay between project governance, project complexity, and servant leadership and their combined effects on project success, specifically within the context of Pakistani megaprojects. The primary objectives are to examine the direct impact of project governance on project success, understand the negative influence of project complexity, assess the positive role of servant leadership, explore the moderating effect of servant leadership on the relationship between governance and success, and investigate how servant leadership mitigates the adverse effects of complexity. Using a quantitative approach, survey data were collected from project managers and team members involved in Pakistani megaprojects. Using a Comprehensive empirical model, 257 Valid responses were analyzed. Multiple regression analysis tested the hypothesized relationships and interaction effects using PLS-SEM. Findings reveal that project governance significantly enhances project success, emphasizing the need for robust governance structures. Conversely, project complexity negatively impacts success, highlighting the challenges of managing complex projects. Servant leadership significantly boosts project success by prioritizing team support and empowerment. Although the interaction between governance and servant leadership is not significant, suggesting no significant change in project success, servant leadership significantly mitigates the negative effects of project complexity, enhancing team resilience and adaptability. These results underscore the necessity for a balanced approach integrating strong governance with flexible, supportive leadership. The study offers valuable insights for practitioners, recommending adaptive governance frameworks and promoting servant leadership to improve the management and success rates of megaprojects. This research contributes to the broader understanding of effective project management practices in complex environments.Keywords: project governance, project complexity, servant leadership, project success, megaprojects, Pakistan
Procedia PDF Downloads 385421 "Project" Approach in Urban: A Response to Uncertainty
Authors: Mouhoubi Nedjima, Sassi Boudemagh Souad
Abstract:
In this paper, we will try to demonstrate the importance of the project approach in the urban to deal with uncertainty, the importance of the involvement of all stakeholders in the urban project process and that the absence of an actor can lead to project failure but also the importance of the urban project management. These points are handled through the following questions: Does the urban adhere to the theory of complexity? Does the project approach bring hope and solution to make urban planning "sustainable"? How converging visions of actors for the same project? Is the management of urban project the solution to support the urban project approach?Keywords: strategic planning, project, urban project stakeholders, management
Procedia PDF Downloads 5145420 BIM Application Research Based on the Main Entrance and Garden Area Project of Shanghai Disneyland
Authors: Ying Yuken, Pengfei Wang, Zhang Qilin, Xiao Ben
Abstract:
Based on the main entrance and garden area (ME&G) project of Shanghai Disneyland, this paper introduces the application of BIM technology in this kind of low-rise comprehensive building with complex facade system, electromechanical system and decoration system. BIM technology is applied to the whole process of design, construction and completion of the whole project. With the construction of BIM application framework of the whole project, the key points of BIM modeling methods of different systems and the integration and coordination of BIM models are elaborated in detail. The specific application methods of BIM technology in similar complex low-rise building projects are sorted out. Finally, the paper summarizes the benefits of BIM technology application, and puts forward some suggestions for BIM management mode and practical application of similar projects in the future.Keywords: BIM, complex low-rise building, BIM modeling, model integration and coordination, 3D scanning
Procedia PDF Downloads 173