Search results for: BIM schedule updating mechanism
3734 Enhance Construction Visual As-Built Schedule Management Using BIM Technology
Authors: Shu-Hui Jan, Hui-Ping Tserng, Shih-Ping Ho
Abstract:
Construction project control attempts to obtain real-time as-built schedule information and to eliminate project delays by effectively enhancing dynamic schedule control and management. Suitable platforms for enhancing an as-built schedule visually during the construction phase are necessary and important for general contractors. As the application of building information modeling (BIM) becomes more common, schedule management integrated with the BIM approach becomes essential to enhance visual construction management implementation for the general contractor during the construction phase. To enhance visualization of the updated as-built schedule for the general contractor, this study presents a novel system called the Construction BIM-assisted Schedule Management (ConBIM-SM) system for general contractors in
Keywords: building information modeling (BIM), construction schedule management, as-built schedule management, BIM schedule updating mechanism
Procedia PDF Downloads 3753733 The Constraint of Machine Breakdown after a Match up Scheduling of Paper Manufacturing Industry
Authors: John M. Ikome
Abstract:
In the process of manufacturing, a machine breakdown usually forces a modified flow shop out of the prescribed state, this strategy reschedules part of the initial schedule to match up with the pre-schedule at some point with the objective to create a schedule that is reliable with the other production planning decisions like material flow, production and suppliers by utilizing a critical decision-making concept. We propose a rescheduling strategy and a match-up point that will have a determination procedure through an advanced feedback control mechanism to increase both the schedule quality and stability. These approaches are compared with alternative re-scheduling methods under different experimental settings.Keywords: scheduling, heuristics, branch, integrated
Procedia PDF Downloads 4083732 A Probability Analysis of Construction Project Schedule Using Risk Management Tool
Authors: A. L. Agarwal, D. A. Mahajan
Abstract:
Construction industry tumbled along with other industry/sectors during recent economic crash. Construction business could not regain thereafter and still pass through slowdown phase, resulted many real estate as well as infrastructure projects not completed on schedule and within budget. There are many theories, tools, techniques with software packages available in the market to analyze construction schedule. This study focuses on the construction project schedule and uncertainties associated with construction activities. The infrastructure construction project has been considered for the analysis of uncertainty on project activities affecting project duration and analysis is done using @RISK software. Different simulation results arising from three probability distribution functions are compiled to benefit construction project managers to plan more realistic schedule of various construction activities as well as project completion to document in the contract and avoid compensations or claims arising out of missing the planned schedule.Keywords: construction project, distributions, project schedule, uncertainty
Procedia PDF Downloads 3503731 An Advanced Match-Up Scheduling Under Single Machine Breakdown
Abstract:
When a machine breakdown forces a Modified Flow Shop (MFS) out of the prescribed state, the proposed strategy reschedules part of the initial schedule to match up with the preschedule at some point. The objective is to create a new schedule that is consistent with the other production planning decisions like material flow, tooling and purchasing by utilizing the time critical decision making concept. We propose a new rescheduling strategy and a match-up point determination procedure through a feedback mechanism to increase both the schedule quality and stability. The proposed approach is compared with alternative reactive scheduling methods under different experimental settings.Keywords: advanced critical task methods modified flow shop (MFS), Manufacturing, experiment, determination
Procedia PDF Downloads 4053730 Nurse Schedule Problem in Mubarak Al Kabeer Hospital
Authors: Khaled Al-Mansour, Nawaf Esmael, Abdulaziz Al-Zaid, Mohammed Al Ateeqi, Ali Al-Yousfi, Sayed Al-Zalzalah
Abstract:
In this project we will create the new schedule of nurse according to the preference of them. We did our project in Mubarak Al Kabeer Hospital (in Kuwait). The project aims to optimize the schedule of nurses in Mubarak Al Kabeer Hospital. The schedule of the nurses was studied and understood well to do any modification for their schedule to make the nurses feel as much comfort as they are. First constraints were found to know what things we can change and what things we can’t, the hard constraints are the hospital and ministry policies where we can’t change anything about, and the soft constraints are things that make nurses more comfortable. Data were collected and nurses were interviewed to know what is more better for them. All these constraints and date have been formulated to mathematical equations. This report will first contain an introduction to the topic which includes details of the problem definition. It will also contain information regarding the optimization of a nurse schedule and its contents and importance; furthermore, the report will contain information about the data needed to solve the problem and how it was collected. The problem requires formulation and that is also to be shown. The methodology will be explained which will state what has already been done. We used the lingo software to find the best schedule for the nurse. The schedule has been made according to what the nurses prefer, and also took consideration of the hospital policy when we make the schedule.Keywords: nurse schedule problem, Kuwait, hospital policy, optimization of schedules
Procedia PDF Downloads 2683729 Feature Selection for Production Schedule Optimization in Transition Mines
Authors: Angelina Anani, Ignacio Ortiz Flores, Haitao Li
Abstract:
The use of underground mining methods have increased significantly over the past decades. This increase has also been spared on by several mines transitioning from surface to underground mining. However, determining the transition depth can be a challenging task, especially when coupled with production schedule optimization. Several researchers have simplified the problem by excluding operational features relevant to production schedule optimization. Our research objective is to investigate the extent to which operational features of transition mines accounted for affect the optimal production schedule. We also provide a framework for factors to consider in production schedule optimization for transition mines. An integrated mixed-integer linear programming (MILP) model is developed that maximizes the NPV as a function of production schedule and transition depth. A case study is performed to validate the model, with a comparative sensitivity analysis to obtain operational insights.Keywords: underground mining, transition mines, mixed-integer linear programming, production schedule
Procedia PDF Downloads 1693728 Model Updating Based on Modal Parameters Using Hybrid Pattern Search Technique
Authors: N. Guo, C. Xu, Z. C. Yang
Abstract:
In order to ensure the high reliability of an aircraft, the accurate structural dynamics analysis has become an indispensable part in the design of an aircraft structure. Therefore, the structural finite element model which can be used to accurately calculate the structural dynamics and their transfer relations is the prerequisite in structural dynamic design. A dynamic finite element model updating method is presented to correct the uncertain parameters of the finite element model of a structure using measured modal parameters. The coordinate modal assurance criterion is used to evaluate the correlation level at each coordinate over the experimental and the analytical mode shapes. Then, the weighted summation of the natural frequency residual and the coordinate modal assurance criterion residual is used as the objective function. Moreover, the hybrid pattern search (HPS) optimization technique, which synthesizes the advantages of pattern search (PS) optimization technique and genetic algorithm (GA), is introduced to solve the dynamic FE model updating problem. A numerical simulation and a model updating experiment for GARTEUR aircraft model are performed to validate the feasibility and effectiveness of the present dynamic model updating method, respectively. The updated results show that the proposed method can be successfully used to modify the incorrect parameters with good robustness.Keywords: model updating, modal parameter, coordinate modal assurance criterion, hybrid genetic/pattern search
Procedia PDF Downloads 1613727 Development of Construction Cost Optimization System Using Genetic Algorithm Method
Authors: Hyeon-Seung Kim, Young-Hwan Kim, Sang-Mi Park, Min-Seo Kim, Jong-Myeung Shin, Leen-Seok Kang
Abstract:
The project budget at the planned stage might be changed by the insufficient government budget or the design change. There are many cases more especially in the case of a project performed for a long period of time. If the actual construction budget is insufficient comparing with the planned budget, the construction schedule should also be changed to match the changed budget. In that case, most project managers change the planned construction schedule by a heuristic approach without a reasonable consideration on the work priority. This study suggests an optimized methodology to modify the construction schedule according to the changed budget. The genetic algorithm was used to optimize the modified construction schedule within the changed budget. And a simulation system of construction cost histogram in accordance with the construction schedule was developed in the BIM (Building Information Modeling) environment.Keywords: 5D, BIM, GA, cost optimization
Procedia PDF Downloads 5873726 Effect of Pre-Construction on Construction Schedule and Client Loyalty
Authors: Jong Hoon Kim, Hyun-Soo Lee, Moonseo Park, Min Jeong, Inbeom Lee
Abstract:
Pre-construction is essential in achieving the success of a construction project. Due to the early involvement of project participants in the construction phase, project managers are able to plan ahead and solve issues well in advance leading to the success of the project and the satisfaction of the client. This research utilizes quantitative data derived from construction management projects in order to identify the relationship between pre-construction, construction schedule, and client satisfaction. A total of 65 construction projects and 93 clients were investigated for this research in an attempt to identify (a) the relationship between pre-construction and schedule reduction, and (b) pre-construction and client loyalty. Based on the quantitative analysis, this research was able to establish a negative correlation based on 65 construction projects between pre-construction and project schedule existed. This finding represents that the more pre-construction is performed for a certain project, the overall construction schedule decreased. Then, to determine the relationship between pre-construction and client satisfaction, Net Promoter Score (NPS) of 93 clients from the 65 projects was utilized. Pre-construction and NPS was further analyzed and a positive correlation was found between the two. This infers that clients tend to be more satisfied with projects with higher ratio of pre-construction than those projects with less pre-construction.Keywords: client loyalty, NPS, pre-construction, schedule reduction
Procedia PDF Downloads 3603725 Reliability Analysis of Construction Schedule Plan Based on Building Information Modelling
Authors: Lu Ren, You-Liang Fang, Yan-Gang Zhao
Abstract:
In recent years, the application of BIM (Building Information Modelling) to construction schedule plan has been the focus of more and more researchers. In order to assess the reasonable level of the BIM-based construction schedule plan, that is whether the schedule can be completed on time, some researchers have introduced reliability theory to evaluate. In the process of evaluation, the uncertain factors affecting the construction schedule plan are regarded as random variables, and probability distributions of the random variables are assumed to be normal distribution, which is determined using two parameters evaluated from the mean and standard deviation of statistical data. However, in practical engineering, most of the uncertain influence factors are not normal random variables. So the evaluation results of the construction schedule plan will be unreasonable under the assumption that probability distributions of random variables submitted to the normal distribution. Therefore, in order to get a more reasonable evaluation result, it is necessary to describe the distribution of random variables more comprehensively. For this purpose, cubic normal distribution is introduced in this paper to describe the distribution of arbitrary random variables, which is determined by the first four moments (mean, standard deviation, skewness and kurtosis). In this paper, building the BIM model firstly according to the design messages of the structure and making the construction schedule plan based on BIM, then the cubic normal distribution is used to describe the distribution of the random variables due to the collecting statistical data of the random factors influencing construction schedule plan. Next the reliability analysis of the construction schedule plan based on BIM can be carried out more reasonably. Finally, the more accurate evaluation results can be given providing reference for the implementation of the actual construction schedule plan. In the last part of this paper, the more efficiency and accuracy of the proposed methodology for the reliability analysis of the construction schedule plan based on BIM are conducted through practical engineering case.Keywords: BIM, construction schedule plan, cubic normal distribution, reliability analysis
Procedia PDF Downloads 1463724 Probability-Based Damage Detection of Structures Using Model Updating with Enhanced Ideal Gas Molecular Movement Algorithm
Authors: M. R. Ghasemi, R. Ghiasi, H. Varaee
Abstract:
Model updating method has received increasing attention in damage detection structures based on measured modal parameters. Therefore, a probability-based damage detection (PBDD) procedure based on a model updating procedure is presented in this paper, in which a one-stage model-based damage identification technique based on the dynamic features of a structure is investigated. The presented framework uses a finite element updating method with a Monte Carlo simulation that considers the uncertainty caused by measurement noise. Enhanced ideal gas molecular movement (EIGMM) is used as the main algorithm for model updating. Ideal gas molecular movement (IGMM) is a multiagent algorithm based on the ideal gas molecular movement. Ideal gas molecules disperse rapidly in different directions and cover all the space inside. This is embedded in the high speed of molecules, collisions between them and with the surrounding barriers. In IGMM algorithm to accomplish the optimal solutions, the initial population of gas molecules is randomly generated and the governing equations related to the velocity of gas molecules and collisions between those are utilized. In this paper, an enhanced version of IGMM, which removes unchanged variables after specified iterations, is developed. The proposed method is implemented on two numerical examples in the field of structural damage detection. The results show that the proposed method can perform well and competitive in PBDD of structures.Keywords: enhanced ideal gas molecular movement (EIGMM), ideal gas molecular movement (IGMM), model updating method, probability-based damage detection (PBDD), uncertainty quantification
Procedia PDF Downloads 2773723 Development of Work Breakdown Structure for EVMS in South Korea
Authors: Dong-Ho Kim, Su-Sang Lim, Sang-Won Han, Chang-Taek Hyun
Abstract:
In the construction site, the cost and schedules are the most important management elements. Despite efforts to integrated management the cost and schedule, WBS classification is struggling to differ from each other. The cost and schedule can be integrated and can be managed due to the characteristic of the detail system in the case of Korea around the axis of pressure and official fixture system. In this research, the Work Breakdown Structure (WBS) integrating the cost and schedules around in government office construction, WBS which can be used in common was presented in order to analyze the detail system of the public institution construction and improve. As to this method, the efficient administration of not only the link application of the cost and schedule but also construction project is expected.Keywords: WBS, EVMS, integrated cost and schedule, Korea case
Procedia PDF Downloads 3843722 Compensation Mechanism Applied to Eco-Tourism Development in China
Authors: Min Wei
Abstract:
With the rapid development eco-tourism resources exploitation, the conflict between economy development and ecological environment is increasingly prominent. The environmental protection laws, however, are lack of necessary legal support to use market mechanism and economic means to carry out ecological compensation and promote the environmental protection. In order to protect the sustainable utilization of eco-tourism resources and the benign development of the interests of various stakeholders, protection of ecological compensation balance should be put on schedule. The main role of institutional guarantee in eco-tourism resources' value compensation mechanism is to solve the question 'how to guarantee compensation'. The evaluation of the game model in this paper reveals that interest balance of stakeholders is an important cornerstone to obtain the sustainable development. The findings result in constructing a sustainable development pattern of eco- tourism industry based on tripartite game equilibrium among government, tourism enterprises and tourists. It is important that the social, economic and ecological environment should be harmonious development during the pursuit of eco-tourism growth.Keywords: environmental protection, ecological compensation, eco-tourism, market mechanism
Procedia PDF Downloads 3843721 Development of Intelligent Construction Management System Using Web-Camera Image and 3D Object Image
Authors: Hyeon-Seung Kim, Bit-Na Cho, Tae-Woon Jeong, Soo-Young Yoon, Leen-Seok Kang
Abstract:
Recently, a construction project has been large in the size and complicated in the site work. The web-cameras are used to manage the construction site of such a large construction project. They can be used for monitoring the construction schedule as compared to the actual work image of the planned work schedule. Specially, because the 4D CAD system that the construction appearance is continually simulated in a 3D CAD object by work schedule is widely applied to the construction project, the comparison system between the real image of actual work appearance by web-camera and the simulated image of planned work appearance by 3D CAD object can be an intelligent construction schedule management system (ICON). The delayed activities comparing with the planned schedule can be simulated by red color in the ICON as a virtual reality object. This study developed the ICON and it was verified in a real bridge construction project in Korea. To verify the developed system, a web-camera was installed and operated in a case project for a month. Because the angle and zooming of the web-camera can be operated by Internet, a project manager can easily monitor and assume the corrective action.Keywords: 4D CAD, web-camera, ICON (intelligent construction schedule management system), 3D object image
Procedia PDF Downloads 5073720 The Effect Of Flights Schedules On Airline Choice Model For International Round-Trip Flights
Authors: Claudia Munoz, Henry Laniado
Abstract:
In this research, the impact of outbound and return flight schedule preferences on airline choice for international trips is quantified. Several studies have used airline choice data to identify preferences and trade-offs of different air carrier service attributes, such as travel time, fare and frequencies. However, estimation of the effect return flight schedules have on airline choice for an international round-trip flight has not yet been studied in detail. The multinomial logit model found shows that airfare, travel time, arrival preference schedule in the outward journey, departure preference in the return journey and the schedule combination of round-trip flights are significantly affecting passenger choice behavior in international round-trip flights. it results indicated that return flight schedule preference plays a substantial role in air carrier choice and has a similar effect to outbound flight schedule preference. Thus, this study provides an analytical tool designed to provide a better understanding of international round-trip flight demand determinants and support carrier decisions.Keywords: flight schedule, airline choice, return flight, passenger choice behavior
Procedia PDF Downloads 163719 Renovation Planning Model for a Shopping Mall
Authors: Hsin-Yun Lee
Abstract:
In this study, the pedestrian simulation VISWALK integration and application platform ant algorithms written program made to construct a renovation engineering schedule planning mode. The use of simulation analysis platform construction site when the user running the simulation, after calculating the user walks in the case of construction delays, the ant algorithm to find out the minimum delay time schedule plan, and add volume and unit area deactivated loss of business computing, and finally to the owners and users of two different positions cut considerations pick out the best schedule planning. To assess and validate its effectiveness, this study constructed the model imported floor of a shopping mall floor renovation engineering cases. Verify that the case can be found from the mode of the proposed project schedule planning program can effectively reduce the delay time and the user's walking mall loss of business, the impact of the operation on the renovation engineering facilities in the building to a minimum.Keywords: pedestrian, renovation, schedule, simulation
Procedia PDF Downloads 4133718 Round Addition DFA on Lightweight Block Ciphers with On-The-Fly Key Schedule
Authors: Hideki Yoshikawa, Masahiro Kaminaga, Arimitsu Shikoda, Toshinori Suzuki
Abstract:
Round addition differential fault analysis (DFA) using operation bypassing for lightweight block ciphers with on-the-fly key schedule is presented. For 64-bit KLEIN and 64-bit LED, it is shown that only a pair of correct ciphertext and faulty ciphertext can derive the secret master key. For PRESENT, one correct ciphertext and two faulty ciphertexts are required to reconstruct the secret key.Keywords: differential fault analysis (DFA), round addition, block cipher, on-the-fly key schedule
Procedia PDF Downloads 7023717 Optimizing Skill Development in Golf Putting: An Investigation of Blocked, Random, and Increasing Practice Schedules
Authors: John White
Abstract:
This study investigated the effects of practice schedules on learning and performance in golf putting, specifically focusing on the impact of increasing contextual interference (CI). University students (n=7) were randomly assigned to blocked, random, or increasing practice schedules. During acquisition, participants performed 135 putting trials using different weighted golf balls. The blocked group followed a specific sequence of ball weights, while the random group practiced with the balls in a random order. The increasing group started with a blocked schedule, transitioned to a serial schedule, and concluded with a random schedule. Retention and transfer tests were conducted 24 hours later. The results indicated that high levels of CI (random practice) were more beneficial for learning than low levels of CI (blocked practice). The increasing practice schedule, incorporating blocked, serial, and random practice, demonstrated advantages over traditional blocked and random schedules. Additionally, EEG was used to explore the neurophysiological effects of the increasing practice schedule.Keywords: skill acquisition, motor control, learning, contextual interference
Procedia PDF Downloads 963716 Scheduling of Cross-Docking Center: An Auction-Based Algorithm
Authors: Eldho Paul, Brijesh Paul
Abstract:
This work proposes an auction mechanism based solution methodology for the optimum scheduling of trucks in a cross-docking centre. The cross-docking centre is an important element of lean supply chain. It reduces the amount of storage and transportation costs in the distribution system compared to an ordinary warehouse. Better scheduling of trucks in a cross-docking center is the best way to reduce storage and transportation costs. Auction mechanism is commonly used for allocation of limited resources in different real-life applications. Here, we try to schedule inbound trucks by integrating auction mechanism with the functioning of a cross-docking centre. A mathematical model is developed for the optimal scheduling of inbound trucks based on the auction methodology. The determination of exact solution for problems involving large number of trucks was found to be computationally difficult, and hence a genetic algorithm based heuristic methodology is proposed in this work. A comparative study of exact and heuristic solutions is done using five classes of data sets. It is observed from the study that the auction-based mechanism is capable of providing good solutions to scheduling problem in cross-docking centres.Keywords: auction mechanism, cross-docking centre, genetic algorithm, scheduling of trucks
Procedia PDF Downloads 4123715 Schedule Risk Management for Complex Projects: The Royal Research Ship: Sir David Attenborough Case Study
Authors: Chatelier Charlene, Oyegoke Adekunle, Ajayi Saheed, Jeffries Andrew
Abstract:
This study seeks to understand Schedule Risk Assessments as a priori for better performance whilst exploring the strategies employed to deliver complex projects like the New Polar research ship. This high-profile vessel was offered to Natural Environment Research Council and British Antarctic Survey (BAS) by Cammell Laird Shipbuilders. The Research Ship was designed to support science in extreme environments, with the expectancy to provide a wide range of specialist scientific facilities, instruments, and laboratories to conduct research over multiple disciplines. Aim: The focus is to understand the allocation and management of schedule risk on such a Major Project. Hypothesising that "effective management of schedule risk management" could be the most critical factor in determining whether the intended benefits mentioned are delivered within time and cost constraints. Objective 1: Firstly, the study seeks to understand the allocation and management of schedule risk in Major Projects. Objective 2: Secondly, it explores "effective management of schedule risk management" as the most critical factor determining the delivery of intended benefits. Methodology: This study takes a retrospective review of schedule risk management and how it influences project performance using a case study approach for the RRS (Royal Research Ship) Sir David Attenborough. Research Contribution: The outcomes of this study will contribute to a better understanding of project performance whilst building on its under-researched relationship to schedule risk management for complex projects. The outcomes of this paper will guide further research on project performance and enable the understanding of how risk-based estimates over time impact the overall risk management of the project.Keywords: complexity, major projects, performance management, schedule risk management, uncertainty
Procedia PDF Downloads 963714 Reflections on Mechanism of Foreign Teachers’ Administration in Colleges and Universities in China
Authors: YangHui
Abstract:
Foreign teachers play an important role in the process of internationalization of higher education in China. Based on the method of literature analysis, firstly study the contents about the mechanism of the foreign teachers’ administration in our country, then secondly analyze the main barriers of the foreign teacher’s administration mechanism. Finally, it is suggested that the international exchange department in universities should constantly improve the employment mechanism, training mechanism, appraisal mechanism and incentive mechanism to promote the internationalization of higher education.Keywords: internationalization of higher education, mechanism, administration of foreign teachers, colleges and universities, China
Procedia PDF Downloads 4783713 A Scalable Media Job Framework for an Open Source Search Engine
Authors: Pooja Mishra, Chris Pollett
Abstract:
This paper explores efficient ways to implement various media-updating features like news aggregation, video conversion, and bulk email handling. All of these jobs share the property that they are periodic in nature, and they all benefit from being handled in a distributed fashion. The data for these jobs also often comes from a social or collaborative source. We isolate the class of periodic, one round map reduce jobs as a useful setting to describe and handle media updating tasks. As such tasks are simpler than general map reduce jobs, programming them in a general map reduce platform could easily become tedious. This paper presents a MediaUpdater module of the Yioop Open Source Search Engine Web Portal designed to handle such jobs via an extension of a PHP class. We describe how to implement various media-updating tasks in our system as well as experiments carried out using these implementations on an Amazon Web Services cluster.Keywords: distributed jobs framework, news aggregation, video conversion, email
Procedia PDF Downloads 2983712 Enumerative Search for Crane Schedule in Anodizing Operations
Authors: Kanate Pantusavase, Jaramporn Hassamontr
Abstract:
This research aims to develop an algorithm to generate a schedule of multiple cranes that will maximize load throughputs in anodizing operation. The algorithm proposed utilizes an enumerative strategy to search for constant time between successive loads and crane covering range over baths. The computer program developed is able to generate a near-optimal crane schedule within reasonable times, i.e. within 10 minutes. Its results are compared with existing solutions from an aluminum extrusion industry. The program can be used to generate crane schedules for mixed products, thus allowing mixed-model line balancing to improve overall cycle times.Keywords: crane scheduling, anodizing operations, cycle time minimization
Procedia PDF Downloads 4633711 Dynamic Background Updating for Lightweight Moving Object Detection
Authors: Kelemewerk Destalem, Joongjae Cho, Jaeseong Lee, Ju H. Park, Joonhyuk Yoo
Abstract:
Background subtraction and temporal difference are often used for moving object detection in video. Both approaches are computationally simple and easy to be deployed in real-time image processing. However, while the background subtraction is highly sensitive to dynamic background and illumination changes, the temporal difference approach is poor at extracting relevant pixels of the moving object and at detecting the stopped or slowly moving objects in the scene. In this paper, we propose a moving object detection scheme based on adaptive background subtraction and temporal difference exploiting dynamic background updates. The proposed technique consists of a histogram equalization, a linear combination of background and temporal difference, followed by the novel frame-based and pixel-based background updating techniques. Finally, morphological operations are applied to the output images. Experimental results show that the proposed algorithm can solve the drawbacks of both background subtraction and temporal difference methods and can provide better performance than that of each method.Keywords: background subtraction, background updating, real time, light weight algorithm, temporal difference
Procedia PDF Downloads 3423710 An Application of a Feedback Control System to Minimize Unforeseen Disruption in a Paper Manufacturing Industry in South Africa
Authors: Martha E. Ndeley
Abstract:
Operation management is the key element within the manufacturing process. However, during this process, there are a number of unforeseen disruptions that causes the process to a standstill which are, machine breakdown, employees absenteeism, improper scheduling. When this happens, it forces the shop flow to a rescheduling process and these strategy reschedules only a limited part of the initial schedule to match up with the pre-schedule at some point with the objective to create a new schedule that is reliable which in the long run gets disrupted. In this work, we have developed feedback control system that minimizes any form of disruption before the impact becomes severe, the model was tested in a paper manufacturing industries and the results revealed that, if the disruption is minimized at the initial state, the impact becomes unnoticeable.Keywords: disruption, machine, absenteeism, scheduling
Procedia PDF Downloads 3063709 Resource Constrained Time-Cost Trade-Off Analysis in Construction Project Planning and Control
Authors: Sangwon Han, Chengquan Jin
Abstract:
Time-cost trade-off (TCTO) is one of the most significant part of construction project management. Despite the significance, current TCTO analysis, based on the Critical Path Method, does not consider resource constraint, and accordingly sometimes generates an impractical and/or infeasible schedule planning in terms of resource availability. Therefore, resource constraint needs to be considered when doing TCTO analysis. In this research, genetic algorithms (GA) based optimization model is created in order to find the optimal schedule. This model is utilized to compare four distinct scenarios (i.e., 1) initial CPM, 2) TCTO without considering resource constraint, 3) resource allocation after TCTO, and 4) TCTO with considering resource constraint) in terms of duration, cost, and resource utilization. The comparison results identify that ‘TCTO with considering resource constraint’ generates the optimal schedule with the respect of duration, cost, and resource. This verifies the need for consideration of resource constraint when doing TCTO analysis. It is expected that the proposed model will produce more feasible and optimal schedule.Keywords: time-cost trade-off, genetic algorithms, critical path, resource availability
Procedia PDF Downloads 1863708 Public-Private Partnership Transportation Projects: An Exploratory Study in the US
Authors: Medya Fathi
Abstract:
When public transportation projects were delivered through design-bid-build and later design-build, governments found a serious issue: inadequate funding. With population growth, governments began to develop new arrangements in which the private sectors were involved to cut the financial burden. This arrangement, known as Public-Private Partnership (PPP), has its own risks; however, performance outputs can motivate or discourage its use. On top of such output's list are time and budget, which can be affected by the type of project delivery methods. Project completion within or ahead of schedule as well as within or under budget is among any owner’s objectives. With a higher application of PPP in the highway industry in the US and insufficient PPP research, the current study addresses the schedule and cost performance of PPP highway projects and determines which one outperforms the other. To meet this objective, after collecting performance data of all PPP projects, schedule growth and cost growth are calculated, and finally, statistical analysis is conducted to evaluate the PPP performance. The results and conclusions will be provided. This study can assist practitioners in applying PPP for transportation projects by showing its ability to save time and/or cost.Keywords: cost, delivery method, highway, public-private partnership, schedule, transportation
Procedia PDF Downloads 1763707 Performance Evaluation of Production Schedules Based on Process Mining
Authors: Kwan Hee Han
Abstract:
External environment of enterprise is rapidly changing majorly by global competition, cost reduction pressures, and new technology. In these situations, production scheduling function plays a critical role to meet customer requirements and to attain the goal of operational efficiency. It deals with short-term decision making in the production process of the whole supply chain. The major task of production scheduling is to seek a balance between customer orders and limited resources. In manufacturing companies, this task is so difficult because it should efficiently utilize resource capacity under the careful consideration of many interacting constraints. At present, many computerized software solutions have been utilized in many enterprises to generate a realistic production schedule to overcome the complexity of schedule generation. However, most production scheduling systems do not provide sufficient information about the validity of the generated schedule except limited statistics. Process mining only recently emerged as a sub-discipline of both data mining and business process management. Process mining techniques enable the useful analysis of a wide variety of processes such as process discovery, conformance checking, and bottleneck analysis. In this study, the performance of generated production schedule is evaluated by mining event log data of production scheduling software system by using the process mining techniques since every software system generates event logs for the further use such as security investigation, auditing and error bugging. An application of process mining approach is proposed for the validation of the goodness of production schedule generated by scheduling software systems in this study. By using process mining techniques, major evaluation criteria such as utilization of workstation, existence of bottleneck workstations, critical process route patterns, and work load balance of each machine over time are measured, and finally, the goodness of production schedule is evaluated. By using the proposed process mining approach for evaluating the performance of generated production schedule, the quality of production schedule of manufacturing enterprises can be improved.Keywords: data mining, event log, process mining, production scheduling
Procedia PDF Downloads 2793706 A Construction Scheduling Model by Applying Pedestrian and Vehicle Simulation
Authors: Akhmad F. K. Khitam, Yi Tai, Hsin-Yun Lee
Abstract:
In the modern research of construction management, the goals of scheduling are not only to finish the project within the limited duration, but also to improve the impact of people and environment. Especially for the impact to the pedestrian and vehicles, the considerable social cost should be estimated in the total performance of a construction project. However, the site environment has many differences between projects. These interactions affect the requirement and goal of scheduling. It is difficult for schedule planners to quantify these interactions. Therefore, this study use 3D dynamic simulation technology to plan the schedule of the construction engineering projects that affect the current space users (i.e., the pedestrians and vehicles). The proposed model can help the project manager find out the optimal schedule to minimize the inconvenience brought to the space users. Besides, a roadwork project and a building renovation project were analyzed for the practical situation of engineering and operations. Then this study integrates the proper optimization algorithms and computer technology to establish a decision support model. The proposed model can generate a near-optimal schedule solution for project planners.Keywords: scheduling, simulation, optimization, pedestrian and vehicle behavior
Procedia PDF Downloads 1413705 Automated Method Time Measurement System for Redesigning Dynamic Facility Layout
Authors: Salam Alzubaidi, G. Fantoni, F. Failli, M. Frosolini
Abstract:
The dynamic facility layout problem is a really critical issue in the competitive industrial market; thus, solving this problem requires robust design and effective simulation systems. The sustainable simulation requires inputting reliable and accurate data into the system. So this paper describes an automated system integrated into the real environment to measure the duration of the material handling operations, collect the data in real-time, and determine the variances between the actual and estimated time schedule of the operations in order to update the simulation software and redesign the facility layout periodically. The automated method- time measurement system collects the real data through using Radio Frequency-Identification (RFID) and Internet of Things (IoT) technologies. Hence, attaching RFID- antenna reader and RFID tags enables the system to identify the location of the objects and gathering the time data. The real duration gathered will be manipulated by calculating the moving average duration of the material handling operations, choosing the shortest material handling path, and then updating the simulation software to redesign the facility layout accommodating with the shortest/real operation schedule. The periodic simulation in real-time is more sustainable and reliable than the simulation system relying on an analysis of historical data. The case study of this methodology is in cooperation with a workshop team for producing mechanical parts. Although there are some technical limitations, this methodology is promising, and it can be significantly useful in the redesigning of the manufacturing layout.Keywords: dynamic facility layout problem, internet of things, method time measurement, radio frequency identification, simulation
Procedia PDF Downloads 120