2299 Assessing Project Performance through Work Sampling and Earned Value Analysis

Authors: Shobha Ramalingam

Abstract:

The majority of the infrastructure projects are affected by time overrun, resulting in project delays and subsequently cost overruns. Time overrun may vary from a few months to as high as five or more years, placing the project viability at risk. One of the probable reasons noted in the literature for this outcome in projects is due to poor productivity. Researchers contend that productivity in construction has only marginally increased over the years. While studies in the literature have extensively focused on time and cost parameters in projects, there are limited studies that integrate time and cost with productivity to assess project performance. To this end, a study was conducted to understand the project delay factors concerning cost, time and productivity. A case-study approach was adopted to collect rich data from a nuclear power plant project site for two months through observation, interviews and document review. The data were analyzed using three different approaches for a comprehensive understanding. Foremost, a root-cause analysis was performed on the data using Ishikawa’s fish-bone diagram technique to identify the various factors impacting the delay concerning time. Based on it, a questionnaire was designed and circulated to concerned executives, including project engineers and contractors to determine the frequency of occurrence of the delay, which was then compiled and presented to the management for a possible solution to mitigate. Second, a productivity analysis was performed on select activities, including rebar bending and concreting through a time-motion study to analyze product performance. Third, data on cost of construction for three years allowed analyzing the cost performance using earned value management technique. All three techniques allowed to systematically and comprehensively identify the key factors that deter project performance and productivity loss in the construction of the nuclear power plant project. The findings showed that improper planning and coordination between multiple trades, concurrent operations, improper workforce and material management, fatigue due to overtime were some of the key factors that led to delays and poor productivity. The findings are expected to act as a stepping stone for further research and have implications for practitioners.

Keywords: earned value analysis, time performance, project costs, project delays, construction productivity

Procedia PDF Downloads 73
2298 Critical Success Factors of Information Technology Projects

Authors: Athar Imtiaz, Abduljalil S. Al-Mudhary, Taha Mirhashemi, Roslina Ibrahim

Abstract:

Information Technology (IT) is being used by almost all organizations throughout the world. However, its success at supporting and improving business is debatable. There is always the risk of IT project failure and studies have proven that a large number of IT projects indeed do fail. There are many components that further the success of IT projects; these have been studied in previous studies. Studies have found the most necessary components for success in software development projects, executive information systems etc. In this study, previous literature that has looked into these success promoting factors have been critically reviewed and analyzed. Fifteen critical Success Factors (CSF) of IT projects were enlisted and examined. These factors can be applied to all IT projects and is not specific to a particular type of IT/IS project. A hypothesis was also generated after the evaluation of the factors.

Keywords: critical success factors, CSF, IT projects, IS projects, software development projects

Procedia PDF Downloads 362
2297 Risk Assessment in Construction of K-Span Buildings in United Arab Emirates (UAE)

Authors: Imtiaz Ali, Imam Mansoor

Abstract:

Investigations as a part of the academic study were undertaken to identify and evaluate the significant risks associated with the construction of K-span buildings in the region of UAE. Primary field data was collected through questionnaires obtaining specific open and close-ended questions from carefully selected construction firms, civil engineers and, construction manager regarding risks associated to K-span building construction. Historical data available for other regions of the same construction technique was available which was compared for identifying various non-critical and critical risk parameters by comparative evaluation techniques to come up with important risks and potential sources for their control and minimization in K-Span buildings that is increasing in the region. The associated risks have been determined with their Relative Importance Index (RII) values of which Risk involved in Change of Design required by Owners carries the highest value (RII=0.79) whereas, Delayed Payment by Owner to Contractor is one of the least (RII=0.42) value. The overall findings suggest that most relative risks as quantified originate or associated with the contractors. It may be concluded that project proponents undertaking K-span projects in planning and budgeting the cost and delays should take into account of risks on high account if changes in design are also required any delays in the material by the supplier would then be a major risk in K-span project delay. Since projects are, less costly, so owners have limited budgets, then they hire small contractors, which are not highly competent contractors. So study suggests that owner should be aware of these types of risks associated with the construction of K-span buildings in order to make it cost effective.

Keywords: k-span buildings, k-span construction, risk management, relative improvement index (RII)

Procedia PDF Downloads 355
2296 A Review: The Impact of Core Quality the Empirical Review of Critical Factors on the Causes of Delay in Road Constructions Projects in the GCC Countries

Authors: Sulaiman Al-Hinai, Setyawan Widyarto

Abstract:

The aim of this study is to identify the critically dominating factors on the delays of road constructions in the GCC countries and their effects on project delivery in Arab countries. Towards the achieved of the objectives the study used the empirical literature from the all relevant online sources and database as many as possible. The findings of this study have summarized and short listed of the success factors in the two categories such as internal and external factors have caused to be influenced to delay of road constructions in the Arab regions. However, in the category of internal factors, there are 63 factors short listed from seven group of factors which has revealed to effects on the delay of road constructions especially, the consultant related factors, the contractor related factors, designed related factors, client related factors, labor related factors, material related issues, equipment related issues respectively. Moreover, for external related factors are also considered to summarized especially natural disaster (flood, hurricanes and cyclone etc.), conflict, war, global financial crisis, compensation delay to affected property owner, price fluctuated, unexpected ground conditions (soil and high-water level), changing of government regulations and laws, delays in obtaining permission from municipality, loss of time by traffic control and restrictions at job site, problem with inhabitant of community, delays in providing service from utilities (water and electricity’s) and accident during constructions accordingly. The present study also concluded the effects of above factors which has delay road constructions through increasing of cost and overrun it, taken overtime, creating of disputes, going for lawsuits, finally happening of abandon of projects. Thus, the present study has given the following recommendations to overcome of above problems by increasing of detailed site investigations, ensure careful monitoring and regular meetings, effective site management, collaborative working and effective coordination’s, proper and comprehensive planning and scheduling and ensure full and intensive commitment from all parties accordingly.

Keywords: Arab GCC countries, critical success factors, road constructions delay, project management

Procedia PDF Downloads 101
2295 Managing Projects in Practice. A Perspective of Stakeholder Management in Managing Stakeholders within the UK Construction Projects

Authors: Faraz Ali Memon

Abstract:

Stakeholders are a vital part of any organisation. It includes working on the demands of different stakeholders within the projects. However, the reality of construction projects is slightly different when it comes to practice. The UK construction projects have a history of failing to complete projects on time and within the budget. The purpose of this qualitative study is to enhance knowledge of stakeholder engagement. Semi-structured interviews will be carried out using a purposive sampling technique. It includes interviewing and getting knowledge from industry practitioners from top UK construction firms on how to manage stakeholders effectively. The findings from this study will help in understanding stakeholders' impact and how the engagement of stakeholders can affect construction projects. The conclusions of this study add value to the existing body of knowledge on stakeholder management, especially in the UK, where academic studies on construction projects are few. As a contribution, this study will provide a practical guide for the practitioners to engage stakeholders within the scope of the project. In addition, this study is limited to UK construction projects. Therefore, the outcome may not be generalised to other developing and underdeveloped countries.

Keywords: stakeholders, UK construction, project management, cost and time

Procedia PDF Downloads 68
2294 To Handle Data-Driven Software Development Projects Effectively

Authors: Shahnewaz Khan

Abstract:

Machine learning (ML) techniques are often used in projects for creating data-driven applications. These tasks typically demand additional research and analysis. The proper technique and strategy must be chosen to ensure the success of data-driven projects. Otherwise, even exerting a lot of effort, the necessary development might not always be possible. In this post, an effort to examine the workflow of data-driven software development projects and its implementation process in order to describe how to manage a project successfully. Which will assist in minimizing the added workload.

Keywords: data, data-driven projects, data science, NLP, software project

Procedia PDF Downloads 57
2293 Activity-Based Safety Assessment of Real Estate Projects in Western India

Authors: Patel Parul, Harsh Ganvit

Abstract:

The construction industry is the second highest industry after agriculture provides employment in India. In developing countries like India, many construction projects are coming up to meet the demand. On the one hand, construction projects are increasing; on the other hand still, construction companies are struggling with many problems. One of the major problems is to ensure safe working conditions at the construction site. Due to a lack of safety awareness and ignorance of safety aspects, many fatal accidents are very common at the construction site in India. One of the key success factors for construction projects is “Accident-Free Construction Projects”. The construction projects can be divided into various categories like Infrastructure projects, industrial construction and real estate construction. Real estate projects are mainly comprised of commercial and residential projects. In the construction industry, private sectors play a huge role in urban and rural development and also contribute significantly to the growth of the nation. Infrastructure and Industrial projects are mainly executed by well-qualified construction contractors. For such projects, ensuring safety at construction projects is inevitable and probably one of the major clauses of contract documents as well. These projects are monitored from time to time by national agencies and researchers, too. However, Real estate projects are rarely monitored for safety aspects. No systematic contract system is followed for these projects. Safety is the most neglected aspect of these projects. In the current research projects, an attempt is made to carry out safety auditing for about 75 real estate projects. The objective of this work is to collect the activity-based safety survey of real estate projects in western India. The analysis of activity-based safety implementation for real estate projects is discussed in the present work. The activities are divided into three categories based on the data collected. The findings of this work will help local monitoring authorities to implement a safety management plan for real estate projects.

Keywords: construction safety, safety assessment, activity-based safety, real estate projects

Procedia PDF Downloads 29
2292 A Review of the Factors Causing Cost Overrun in Construction Projects in Malaysia

Authors: Kaleem Ullah, Abd Halid Bin Abdullah

Abstract:

This study examines previous literature on cost overrun in construction projects with the specific aim of determining the frequently observed causes of cost overruns in Malaysian construction projects. Cost overrun is one of the major problems in construction projects. Cost overrun is frequently observed in almost every construction projects. This cost overrun in construction projects occurs due to various reasons and many researchers have carried out various studies to identify the cause factors of this issue. The causes of construction cost overrun could vary from country to country because of the difference in political, economic, social and environmental conditions. Likewise, other countries construction projects in Malaysia have also the issue of cost overrun. The concept of cost overrun in construction projects has attracted much attention in recent years and researches are trying to understand the causes of these overruns and their effects to the construction industry as whole. This paper review various research studies carried out in Malaysia which surveyed the cost performance and cause factors of cost overruns in construction projects in Malaysia.

Keywords: cause of cost overrun, cost overrun, construction industry in Malaysia, effects of cost overrun

Procedia PDF Downloads 256
2291 Comparison between Approaches Used in Two Walk About Projects

Authors: Derek O Reilly, Piotr Milczarski, Shane Dowdall, Artur Hłobaż, Krzysztof Podlaski, Hiram Bollaert

Abstract:

Learning through creation of contextual games is a very promising way/tool for interdisciplinary and international group projects. During 2013 and 2014 we took part and organized two intensive students projects in different conditions. The projects enrolled 68 students and 12 mentors from 5 countries. In the paper we want to share our experience how to strengthen the chances to succeed in short (12-15 days long) student projects. In our case almost all teams prepared working prototype and the results were highly appreciated by external experts.

Keywords: contextual games, mobile games, GGULIVRR, walkabout, Erasmus intensive programme

Procedia PDF Downloads 476
2290 Stability of Hybrid Systems

Authors: Kreangkri Ratchagit

Abstract:

This paper is concerned with exponential stability of switched linear systems with interval time-varying delays. The time delay is any continuous function belonging to a given interval, in which the lower bound of delay is not restricted to zero. By constructing a suitable augmented Lyapunov-Krasovskii functional combined with Leibniz-Newton’s formula, a switching rule for the exponential stability of switched linear systems with interval time-varying delays and new delay-dependent sufficient conditions for the exponential stability of the systems are first established in terms of LMIs. Finally, some examples are exploited to illustrate the effectiveness of the proposed schemes.

Keywords: exponential stability, hybrid systems, timevarying delays, Lyapunov-Krasovskii functional, Leibniz-Newton’s formula

Procedia PDF Downloads 428
2289 Economic Factors Affecting Greenfield Petroleum Refinery and Petrochemical Projects in Africa

Authors: Daniel Muwooya

Abstract:

This paper analyses economic factors that have affected the competitiveness of petroleum refinery and petrochemical projects in sub-Saharan Africa in the past and continue to plague greenfield projects today. Traditional factors like plant sizing and complexity, low-capacity utilization, changing regulatory environment, and tighter product specifications have been important in the past. Additional factors include the development of excess refinery capacity in Asia and the growth of renewable sources of energy – especially for transportation. These factors create both challenges and opportunities for the development of greenfield refineries and petrochemical projects in areas of increased demand growth and new low-cost crude oil production – like sub-Saharan Africa. This paper evaluates the strategies available to project developers and host countries to address contemporary issues of energy transition and the apparent reduction of funds available for greenfield oil and gas projects. The paper also evaluates the structuring of greenfield refinery and petrochemical projects for limited recourse project finance bankability. The methodology of this paper includes analysis of current industry data, conference proceedings, academic papers, and academic books on the subjects of petroleum refinery economics, refinery financing, refinery operations, and project finance generally and specifically in the oil and gas industry; evaluation of expert opinions from journal articles; working papers from international bodies like the World Bank and the International Energy Agency; and experience from playing an active role in the development and financing of US$ 10 Billion greenfield oil development project in Uganda. The paper also applies the discounted cash flow modelling to illustrate the circumstances of an inland greenfield refinery project in Uganda. Greenfield refinery and petrochemical projects are still necessary in sub-Saharan Africa to, among other aspirations, support the transition from traditional sources of energy like biomass to such modern forms as liquefied petroleum gas. Project developers and host governments will be required to structure projects that support global climate change goals without occasioning undue delays to project execution.

Keywords: financing, refinery and petrochemical economics, Africa, project finance

Procedia PDF Downloads 38
2288 Identification of Factors Affecting Labor Productivity in Construction Projects of Iran

Authors: Elham Dehghan, A. Shirzadi Javid, Mohsen Tadayon

Abstract:

Labor productivity is very important and gained special concerns among professionals in the construction industry, worldwide. Productivity improvements on labors achieve higher cost savings with minimal investment. Due to the fact that profit margins are small on construction projects, cost savings associated with productivity are crucial to become a successful contractor. This research program studies and highlights the factors affecting labor productivity in Iranian construction industry. A questionnaire was used to gather the relevant data from respondents who involve in managing various types of projects in wide areas in Iran. It involved ranking 57 predefined factors divided into 5 categories: Human/Labor; Financial; Management; Equipments/Materials and Environmental. Total 62 feedbacks were analyzed through the Relative Importance Index (RII) technique. The top ten factors affecting construction labor productivity in Iran are: 1) Professional capability of contractor project manager, 2) skills of contractor’s project management team, 3) professional capability of owner project manager, 4) professional capability of Consulting Project manager, 5) discipline working, 6) delay payments by the owner, 7) material shortages, 8) delays in delivery of materials, 9) turnover power of the owner, 10) poor site management. Recommendations have been made in the study to address these factors. The research has direct benefits to key stakeholders in Iranian construction industry.

Keywords: Iranian construction projects, labor, productivity, relative importance index

Procedia PDF Downloads 238
2287 Phthalates Exposure in Children with Central Precocious Puberty (CPP) or Constitutional Delays in Growth

Authors: Yen-An Tsai, Ching-Ling Lin, Jia-Woei Hou, Mei-Lien Chen

Abstract:

Endocrine-disrupting chemicals (EDCs) adversely affect the endocrine system. Phthalates, also called phthalic acid esters (PAEs), are manmade chemicals that are used as stabilizing agents in personal care products such as perfumes, lotions, and cosmetics. The aim was to explore whether PAEs exposure was associated with central precocious puberty (CPP) or constitutional delays in growth (CDGP). This case-control study included 48 female with CPP, 37 male with constitutional delays in growth, and 127 normal children and was conducted from December 2011 to August 2014. All participants completed a structured questionnaire regarding socio-demographic characteristics, lifestyle, and secondary sexual characteristics. The analytical method was based on ultra performance liquid chromatography-tandem mass spectrometry (UPLC-MS/MS) with isotope dilution for the quantitative detection of several phthalate metabolites in human urine. The risk of CPP with mep, mnbp, LMW >50th percentile were higher than those with 50th percentile were higher than those with <50 percentile in model 2. In model 1, we only found higher CDGP risk in mep, mnbp, and ΣPAEs. It shows that high phthalate exposure may associate with CDGP. In this case-control study, we found PAEs exposure was associated with central precocious puberty (CPP) or constitutional delays in growth.

Keywords: phthalates, puberty, delays, growth

Procedia PDF Downloads 160
2286 Cost Overruns in Mega Projects: Project Progress Prediction with Probabilistic Methods

Authors: Yasaman Ashrafi, Stephen Kajewski, Annastiina Silvennoinen, Madhav Nepal

Abstract:

Mega projects either in construction, urban development or energy sectors are one of the key drivers that build the foundation of wealth and modern civilizations in regions and nations. Such projects require economic justification and substantial capital investment, often derived from individual and corporate investors as well as governments. Cost overruns and time delays in these mega projects demands a new approach to more accurately predict project costs and establish realistic financial plans. The significance of this paper is that the cost efficiency of megaprojects will improve and decrease cost overruns. This research will assist Project Managers (PMs) to make timely and appropriate decisions about both cost and outcomes of ongoing projects. This research, therefore, examines the oil and gas industry where most mega projects apply the classic methods of Cost Performance Index (CPI) and Schedule Performance Index (SPI) and rely on project data to forecast cost and time. Because these projects are always overrun in cost and time even at the early phase of the project, the probabilistic methods of Monte Carlo Simulation (MCS) and Bayesian Adaptive Forecasting method were used to predict project cost at completion of projects. The current theoretical and mathematical models which forecast the total expected cost and project completion date, during the execution phase of an ongoing project will be evaluated. Earned Value Management (EVM) method is unable to predict cost at completion of a project accurately due to the lack of enough detailed project information especially in the early phase of the project. During the project execution phase, the Bayesian adaptive forecasting method incorporates predictions into the actual performance data from earned value management and revises pre-project cost estimates, making full use of the available information. The outcome of this research is to improve the accuracy of both cost prediction and final duration. This research will provide a warning method to identify when current project performance deviates from planned performance and crates an unacceptable gap between preliminary planning and actual performance. This warning method will support project managers to take corrective actions on time.

Keywords: cost forecasting, earned value management, project control, project management, risk analysis, simulation

Procedia PDF Downloads 367
2285 New Results on Exponential Stability of Hybrid Systems

Authors: Grienggrai Rajchakit

Abstract:

This paper is concerned with the exponential stability of switched linear systems with interval time-varying delays. The time delay is any continuous function belonging to a given interval, in which the lower bound of delay is not restricted to zero. By constructing a suitable augmented Lyapunov-Krasovskii functional combined with Leibniz-Newton's formula, a switching rule for the exponential stability of switched linear systems with interval time-varying delays and new delay-dependent sufficient conditions for the exponential stability of the systems are first established in terms of LMIs. Finally, some examples are exploited to illustrate the effectiveness of the proposed schemes.

Keywords: exponential stability, hybrid systems, time-varying delays, lyapunov-krasovskii functional, leibniz-newton's formula

Procedia PDF Downloads 524
2284 The Significance of a Well-Defined Systematic Approach in Risk Management for Construction Projects within Oil Industry

Authors: Batool Ismaeel, Umair Farooq, Saad Mushtaq

Abstract:

Construction projects in the oil industry can be very complex, having unknown outcomes and uncertainties that cannot be easily predicted. Each project has its unique risks generated by a number of factors which, if not controlled, will impact the successful completion of the project mainly in terms of schedule, cost, quality, and safety. This paper highlights the historic risks associated with projects in the south and east region of Kuwait Oil Company (KOC) collated from the company’s lessons learned database. Starting from Contract Award through to handover of the project to the Asset owner, the gaps in project execution in terms of managing risk will be brought to discussion and where a well-defined systematic approach in project risk management reflecting many claims, change of scope, exceeding budget, delays in engineering phase as well as in the procurement and fabrication of long lead items should be adopted. This study focuses on a proposed feasible approach in risk management for engineering, procurement and construction (EPC) level projects including the various stakeholders involved in executing the works from International to local contractors and vendors in KOC. The proposed approach covers the areas categorized into organizational, design, procurement, construction, pre-commissioning, commissioning and project management in which the risks are identified and require management and mitigation. With the effective deployment and implementation of the proposed risk management system and the consideration of it as a vital key in achieving the project’s target, the outcomes will be more predictable in the future, and the risk triggers will be managed and controlled. The correct resources can be allocated on a timely basis for the company for avoiding any unpredictable outcomes during the execution of the project. It is recommended in this paper to apply this risk management approach as an integral part of project management and investigate further in the future, the effectiveness of this proposed system for newly awarded projects and compare the same with those projects of similar budget/complexity that have not applied this approach to risk management.

Keywords: construction, project completion, risk management, uncertainties

Procedia PDF Downloads 129
2283 Two Stage Fuzzy Methodology to Evaluate the Credit Risks of Investment Projects

Authors: O. Badagadze, G. Sirbiladze, I. Khutsishvili

Abstract:

The work proposes a decision support methodology for the credit risk minimization in selection of investment projects. The methodology provides two stages of projects’ evaluation. Preliminary selection of projects with minor credit risks is made using the Expertons Method. The second stage makes ranking of chosen projects using the Possibilistic Discrimination Analysis Method. The latter is a new modification of a well-known Method of Fuzzy Discrimination Analysis.

Keywords: expert valuations, expertons, investment project risks, positive and negative discriminations, possibility distribution

Procedia PDF Downloads 643
2282 Genetic Algorithm Optimization of Multiple Resources for Multi-Projects

Authors: A. Samer Ezeldin, Sarah A. Fotouh

Abstract:

Optimization of resources is very important in all fields, as in construction management. Project managers have to face problems regarding management of cost, time and available resources of single projects and more problems arise when managing multiple projects. Most of the studies focused on optimization of resources for a single project, but, this paper will discuss the design and modeling of multiple resources optimization for multiple projects using Genetic Algorithm. Most of the companies in construction industry optimize the resources for single projects only, but with the presence of several mega projects in several developing countries running at the same time, there is a need for a model to enhance the efficiency of available resources and decreases the fluctuation as much as possible. The proposed model calculates the cost of each resource, tries to minimize the cost of extra resources as much as possible and generates the schedule of each project within a selected program.

Keywords: construction management, genetic algorithm, multiple projects, multiple resources, optimization

Procedia PDF Downloads 429
2281 Crowdfunding for Saudi Arabia Green Projects

Authors: Saleh Komies, Mona Alharbi, Razan Alhayyani, Mozah Almulhim, Roseanne Khawaja, Ahmed Alradhi

Abstract:

One of the proposed solutions that faces some challenges is encouraging sustainable energy consumption across Saudi Arabia through crowdfunding platforms. To address these challenges, we need to determine the level of awareness of crowdfunding and green projects, as well as the preferences and willingness of Saudis to utilize crowdfunding as an alternative funding source for green projects in Saudi Arabia. In this study, we aim to determine the influence of environmental awareness and concern on the propensity to crowdfund green projects. The survey is being conducted as part of environmental initiatives to assess public perceptions and opinions on crowdfunding green projects in Saudi Arabia. A total of 450 responses to an online questionnaire distributed via convenience and snowball sampling were utilized for data analysis. The survey reveals that Saudis have a low understanding of crowdfunding concepts and a relatively high understanding of implementing green projects. The public is interested in crowdfunding green projects if there is a return on investment.

Keywords: crowdfunding, green projects, awareness, Saudi Arabia, energy, solar, wind

Procedia PDF Downloads 66
2280 Legal Issues of Implementing Public Projects through Civic Crowdfunding

Authors: Mahdieh Dehghan Nayeri, Hani Arbabi, Seid Pooyan Ghafoori

Abstract:

Civic crowdfunding- crowdfunding public projects- which goes beyond people management- as a significant part of public projects stakeholders- and requires the active engagement of the public in both the financing and decision-making processes of public projects, is expanding. However, in most countries of the world, no specific legal framework has been approved for governing and managing the implementation of projects through this method. Through a systematic literature review, following the Preferred Reporting Items for Systematic Reviews (PRISMA), this article has studied and discussed the legal issues of civic crowdfunded projects in the countries leading the use of this method, in four themes; one related to the legal environment and three related to three leading players in civic crowdfunded projects include the investor, the platform, and the investee. The review showed that despite the increasing attention to people's engagement in public projects -financial and non-financial- not much scientific research has been done to formulate fully structured legal structures. Finally, neglected areas in research have been discussed as a guide for future research.

Keywords: civic crowdfunding, equity crowdfunding, public projects, legal issues, crowdsourcing

Procedia PDF Downloads 200
2279 A Case Study on the Guidelines for Application of Project Management Methods in Infrastructure Projects

Authors: Fernanda Varella Borges, Silvio Burrattino Melhado

Abstract:

Motivated by the importance of public infrastructure projects in the civil construction chain, this research shows the study of project management methods and the infrastructure projects’ characteristics. The research aims at the objective of improving management efficiency by proposing guidelines for the application of project management methods in infrastructure projects. Through literature review and case studies, the research analyses two major infrastructure projects underway in Brazil, identifying the critical points for achieving its success. As a result, the proposed guidelines indicate that special attention should be given to the management of stakeholders, focusing on their knowledge and experience, their different interests, the efficient management of their communication, and their behavior in the day-by-day project management process.

Keywords: construction, infrastructure, project management, public projects

Procedia PDF Downloads 460
2278 Limits and Barriers of Value Creation and Projects Development: The Case of Tunisian SMEs

Authors: Samira Boussema, Ben Hamed Salah

Abstract:

Entrepreneurship was always considered to be the most appropriate remedy for various economies’ symptoms. It is presented as a complex process that faces several barriers thereby inhibiting a project’s implementation phase. In fact, after a careful review of the literature, we noticed that empirical researches on reasons behind non-developing entrepreneurial projects are very rare, suggesting a lack in modeling the process in general and the pre-start phase in particular. Therefore, in this study we try to identify the main environmental barriers to developing business projects in Tunisia through the study of a representative sample of undeveloped projects. To this end, we used a quantitative approach which allowed us to examine the various barriers encountered by young entrepreneurs during their projects’ implementation. Indeed, by modeling the phenomenon we found that these managers face barriers of legal, financial, educational and government support dimensions.

Keywords: entrepreneurship, environmental barriers, non-implementation of projects, structural modeling

Procedia PDF Downloads 353
2277 Monetary Evaluation of Dispatching Decisions in Consideration of Choice of Transport

Authors: Marcel Schneider, Nils Nießen

Abstract:

Microscopic simulation programs enable the description of the two processes of railway operation and the previous timetabling. Occupation conflicts are often solved based on defined train priorities on both process levels. These conflict resolutions produce knock-on delays for the involved trains. The sum of knock-on delays is commonly used to evaluate the quality of railway operations. It is either compared to an acceptable level-of-service or the delays are evaluated economically by linearly monetary functions. It is impossible to properly evaluate dispatching decisions without a well-founded objective function. This paper presents a new approach for evaluation of dispatching decisions. It uses models of choice of transport and considers the behaviour of the end-costumers. These models evaluate the knock-on delays in more detail than linearly monetary functions and consider other competing modes of transport. The new approach pursues the coupling of a microscopic model of railway operation with the macroscopic model of choice of transport. First it will be implemented for the railway operations process, but it can also be used for timetabling. The evaluation considers the possibility to change over to other transport modes by the end-costumers. The new approach first looks at the rail-mounted and road transport, but it can also be extended to air transport. The split of the end-costumers is described by the modal-split. The reactions by the end-costumers have an effect on the revenues of the railway undertakings. Various travel purposes has different pavement reserves and tolerances towards delays. Longer journey times affect besides revenue changes also additional costs. The costs depend either on time or track and arise from circulation of workers and vehicles. Only the variable values are summarised in the contribution margin, which is the base for the monetary evaluation of the delays. The contribution margin is calculated for different resolution decisions of the same conflict. The conflict resolution is improved until the monetary loss becomes minimised. The iterative process therefore determines an optimum conflict resolution by observing the change of the contribution margin. Furthermore, a monetary value of each dispatching decision can also be determined.

Keywords: choice of transport, knock-on delays, monetary evaluation, railway operations

Procedia PDF Downloads 302
2276 Evaluation and Selection of Contractors in Construction Projects with a View Supply Chain Management and Utilization of Promthee

Authors: Sara Najiazarpour, Mahsa Najiazarpour

Abstract:

There are many problems in contracting projects and their performance. At each project stage and due to different reasons, these problems affect cost, time and overall project quality. Hence, in order to increase the efficiency and performance in all levels of the chain and with supply chain management approach, there will be a coordination from the beginning of a project (contractor selection) to the end of project (handover of project). Contractor selection is the foremost part of construction projects which in this multi-criteria decision-making, the best contractor is determined by expert judgment, different variables and their priorities. In this paper for selecting the best contractor, numerous criteria were collected by asking from adept experts and then among them, 16 criteria with highest frequency were considered for questionnaire. This questionnaire was distributed between experts. Cronbach's alpha coefficient was obtained as 72%. Then based on Borda's function 12 important criteria was selected which was categorized in four main criteria and related sub-criteria as follow: Environmental factors and physical equipment: procurement and materials (supplier), company's machines, contractor’s proposed cost estimate - financial capacity: bank turnover and company's assets, the income of tax declaration in last year, Ability to compensate for losses or delays - past performance- records and technical expertise: experts and key personnel, the past technical backgrounds and experiences, employer satisfaction of previous contracts, the number of similar projects was done - standards: rank and field of expertise which company is qualified for and its validity, availability and number of permitted projects done. Then with PROMTHEE method, the criteria were normalized and monitored, finally the best alternative was selected. In this research, qualitative criteria of each company is became a quantitative criteria. Finally, information of some companies was evaluated and the best contractor was selected based on all criteria and their priorities.

Keywords: contractor evaluation and selection, project development, supply chain management, PROMTHEE method

Procedia PDF Downloads 43
2275 Productivity of Construction Companies Using the Management of Threats and Opportunities ‎in Construction Projects of Iran

Authors: Nima Amani, Ali Salehi Dastjerdi, Fatemeh Ahmadi, Ardalan Sabamehr

Abstract:

The cost overrun of the construction projects has always been one of the main problems of the construction companies caused by the risky nature of the construction projects. Therefore, today, the application of risk management is inevitable. Although in theory, the issue of risk management is divided into the opportunities and threats management, in practice, most of the projects have been focused on the threats management. However, considering the opportunities management and applying the opportunities-response strategies can lead to the improved profitability of the construction projects of the companies. In this paper, a new technique is developed to identify the opportunities in the construction projects using an improved protocol and propose the appropriate opportunities-response strategies to the construction companies to provide them with higher profitability. To evaluate the effectiveness of the protocol for selecting the most appropriate strategies in ‎response to the opportunities and threats, two projects from a construction company in Iran were ‎studied. Both projects selected were in mid-range in terms of size and similar in terms of time, ‎run time and costs. Finally, the output indicates that using the proposed opportunities-response strategies show that the company's profitability in the future can be increased approximately for similar projects.

Keywords: opportunities management, risk-response strategy, opportunity-response strategy, productivity, risk management

Procedia PDF Downloads 203
2274 Effects of the Macro-Scale Investments/Projects to Planning System in Izmir

Authors: Neslihan Karatas, Sibel Ecemis Kilic

Abstract:

This paper aims to examine macro-scale plans and projects/investments which have been prepared for İzmir since The Republican Period. Macro projects that were proposed by central government, local government, industry and urban actors such as the chamber of commerce will be discussed and these projects and its reflections to the city's macro scale planning decisions will be evaluated based on existing development. Effects of macro plans, the related private and public investments, the developments of unplanned/specific projects to the current city form will be discussed. The factors and plans which determine urban form and the problems caused by unanticipated/uncontrolled developments will be evaluated. The proposals will be developed about more efficient planning process.

Keywords: Izmir, macro projects, macro investments, planning

Procedia PDF Downloads 568
2273 Occupational Safety in Construction Projects

Authors: Heba Elbibas, Esra Gnijeewa, Zedan Hatush

Abstract:

This paper presents research on occupational safety in construction projects, where the importance of safety management in projects was studied, including the preparation of a safety plan and program for each project and the identification of the responsibilities of each party to the contract. The research consists of two parts: 1-Field visits: which were field visits to three construction projects, including building projects, road projects, and tower installation. The safety level of these projects was evaluated through a checklist that includes the most important safety elements in terms of the application of these items in the projects. 2-Preparation of a questionnaire: which included supervisors and engineers and aimed to determine the level of awareness and commitment of different project categories to safety standards. The results showed the following: i) There is a moderate occupational safety policy. ii) The preparation and storage of maintenance reports are not fully complied with. iii) There is a moderate level of training on occupational safety for project workers. iv) The company does not impose penalties on safety violators permanently. v) There is a moderate policy for equipment and machinery safety. vi) Self-injuries occur due to (fatigue, lack of attention, deliberate error, and emotional factors), with a rate of 82.4%.

Keywords: management, safety, occupational safety, classification

Procedia PDF Downloads 75
2272 Study of Slum Redevelopment Initiatives for Dharavi Slum, Mumbai and Its Effectiveness in Implementation in Other Cities

Authors: Anurag Jha

Abstract:

Dharavi is the largest slum in Asia, for which many redevelopment projects have been put forth, to improve the housing conditions of the locals. And yet, these projects are met with much-unexpected resistance from the locals. The research analyses the why and the how of the resistances these projects face and analyses these programs and points out the flaws and benefits of such projects, by predicting its impact on the regulars of Dharavi. The research aims to analyze various aspects of Dharavi, which affect its socio-cultural backdrops, such as its history, and eventual growth into a mega slum. Through various surveys, the research aims to analyze the life of a slum dweller, the street life, and the effect of such settlement on the urban fabric. Various development projects such as Dharavi Museum Movement, are analyzed, and a feasibility and efficiency analysis of the proposals for redevelopment of Dharavi Slums has been theorized. Flaws and benefits of such projects, by predicting its impact on the regulars of Dharavi has been the major approach to the research. Also, prediction the implementation of these projects in another prominent slum area, Anand Nagar, Bhopal, with the use of generated hypothetical model has been done. The research provides a basic framework for a comparative analysis of various redevelopment projects and the effect of implementation of such projects on the general populace. Secondly, it proposes a hypothetical model for feasibility of such projects in certain slum areas.

Keywords: Anand Nagar, Bhopal slums, Dharavi, slum redevelopment programmes

Procedia PDF Downloads 308
2271 National Project 'Environment' of Russian Federation as a Management Tool in Achieving SDGs

Authors: Ekaterina Posokhova, Boris Gavrilov

Abstract:

Priority national projects have become an essential phenomenon in the Russian Federation. Both regional and local government institutions and a significant part of the society have been involved in their implementation. The scale and multispectricity of the national projects give a reason to believe that their concept is beyond the scope of the individual state programs. The national project “environment” contains federal projects on waste management, water, and air quality, ecotourism development, and biodiversity conservation highlights the importance of the preservation and restoration of Volga River and Lake Baikal ecosystems. This study assesses the national projects according to their relativeness with the current SDGs (i.e., SGD 14 and 15), evaluates the methodology of the projects. The paper considers the peculiarities of the national projects as strategic management tools as well as the possibility of amending the project objective indicators. Conclusion on the effectiveness of NP in terms of achieving SDGs is provided.

Keywords: management, SDP, russia, conservation, law

Procedia PDF Downloads 119
2270 Application of Knowledge Discovery in Database Techniques in Cost Overruns of Construction Projects

Authors: Mai Ghazal, Ahmed Hammad

Abstract:

Cost overruns in construction projects are considered as worldwide challenges since the cost performance is one of the main measures of success along with schedule performance. To overcome this problem, studies were conducted to investigate the cost overruns' factors, also projects' historical data were analyzed to extract new and useful knowledge from it. This research is studying and analyzing the effect of some factors causing cost overruns using the historical data from completed construction projects. Then, using these factors to estimate the probability of cost overrun occurrence and predict its percentage for future projects. First, an intensive literature review was done to study all the factors that cause cost overrun in construction projects, then another review was done for previous researcher papers about mining process in dealing with cost overruns. Second, a proposed data warehouse was structured which can be used by organizations to store their future data in a well-organized way so it can be easily analyzed later. Third twelve quantitative factors which their data are frequently available at construction projects were selected to be the analyzed factors and suggested predictors for the proposed model.

Keywords: construction management, construction projects, cost overrun, cost performance, data mining, data warehousing, knowledge discovery, knowledge management

Procedia PDF Downloads 338