10 Enhancing the Implementation Strategy of Simultaneous Operations (SIMOPS) for the Major Turnaround at Pertamina Plaju Refinery

Authors: Fahrur Rozi, Daniswara Krisna Prabatha, Latief Zulfikar Chusaini

Abstract:

Amidst the backdrop of Pertamina Plaju Refinery, which stands as the oldest and historically less technologically advanced among Pertamina's refineries, lies a unique challenge. Originally integrating facilities established by Shell in 1904 and Stanvac (originally Standard Oil) in 1926, the primary challenge at Plaju Refinery does not solely revolve around complexity; instead, it lies in ensuring reliability, considering its operational history of over a century. After centuries of existence, Plaju Refinery has never undergone a comprehensive major turnaround encompassing all its units. The usual practice involves partial turnarounds that are sequentially conducted across its primary, secondary, and tertiary units (utilities and offsite). However, a significant shift is on the horizon. In the Q-IV of 2023, the refinery embarks on its first-ever major turnaround since its establishment. This decision was driven by the alignment of maintenance timelines across various units. Plaju Refinery's major turnaround was scheduled for October-November 2023, spanning 45 calendar days, with the objective of enhancing the operational reliability of all refinery units. The extensive job list for this turnaround encompasses 1583 tasks across 18 units/areas, involving approximately 9000 contracted workers. In this context, the Strategy of Simultaneous Operations (SIMOPS) execution emerges as a pivotal tool to optimize time efficiency and ensure safety. A Hazard Effect Management Process (HEMP) has been employed to assess the risk ratings of each task within the turnaround. Out of the tasks assessed, 22 are deemed high-risk and necessitate mitigation. The SIMOPS approach serves as a preventive measure against potential incidents. It is noteworthy that every turnaround period at Pertamina Plaju Refinery involves SIMOPS-related tasks. In this context, enhancing the implementation strategy of "Simultaneous Operations (SIMOPS)" becomes imperative to minimize the occurrence of incidents. At least four improvements have been introduced in the enhancement process for the major turnaround at Refinery Plaju. The first improvement involves conducting systematic risk assessment and potential hazard mitigation studies for SIMOPS tasks before task execution, as opposed to the previous on-site approach. The second improvement includes the completion of SIMOPS Job Mitigation and Work Matrices Sheets, which was often neglected in the past. The third improvement emphasizes comprehensive awareness to workers/contractors regarding potential hazards and mitigation strategies for SIMOPS tasks before and during the major turnaround. The final improvement is the introduction of a daily program for inspecting and observing work in progress for SIMOPS tasks. Prior to these improvements, there was no established program for monitoring ongoing activities related to SIMOPS tasks during the turnaround. This study elucidates the steps taken to enhance SIMOPS within Pertamina, drawing from the experiences of Plaju Refinery as a guide. A real actual case study will be provided from our experience in the operational unit. In conclusion, these efforts are essential for the success of the first-ever major turnaround at Plaju Refinery, with the SIMOPS strategy serving as a central component. Based on these experiences, enhancements have been made to Pertamina's official Internal Guidelines for Executing SIMOPS Risk Mitigation, benefiting all Pertamina units.

Keywords: process safety management, turn around, oil refinery, risk assessment

Procedia PDF Downloads 34
9 Water Self Sufficient: Creating a Sustainable Water System Based on Urban Harvest Approach in La Serena, Chile

Authors: Zulfikar Dinar Wahidayat Putra

Abstract:

Water scarcity become a major challenge in an arid area. One of the arid areas is La Serena city in the Northern Chile which become a case study of this paper. Based on that, this paper tries to identify a sustainable water system by using urban harvest approach as a method to achieve water self-sufficiency for a neighborhood area in the La Serena city. By using the method, it is possible to create sustainable water system in the neighborhood area by reducing up to 38% of water demand and 94% of wastewater production even though water self-sufficient cannot be fully achieved, because of its dependency to the drinking water supply from water treatment plant of La Serena city.

Keywords: arid area, sustainable water system, urban harvest approach, self-sufficiency

Procedia PDF Downloads 234
8 Reproductive Performance of Dairy Cows at Different Parities: A Case Study in Enrekang Regency, Indonesia

Authors: Muhammad Yusuf, Abdul Latief Toleng, Djoni Prawira Rahardja, Ambo Ako, Sahiruddin Sahiruddin, Abdi Eriansyah

Abstract:

The objective of this study was to know the reproductive performance of dairy cows at different parities. A total of 60 dairy Holstein-Friesian cows with parity one to three from five small farms raised by the farmers were used in the study. All cows were confined in tie stall barn with rubber on the concrete floor. The herds were visited twice for survey with the help of a questionnaire. Reproductive parameters used in the study were days open, calving interval, and service per conception (S/C). The results of this study showed that the mean (±SD) days open of the cows in parity 2 was slightly longer than those in parity 3 (228.2±121.5 vs. 205.5±144.5; P=0.061). None cows conceived within 85 days postpartum in parity 3 in comparison to 13.8% cows conceived in parity 2. However, total cows conceived within 150 days post partum in parity 2 and parity 3 were 30.1% and 36.4%, respectively. Likewise, after reaching 210 days after calving, number of cows conceived in parity 3 had higher than number of cows in parity 2 (72.8% vs. 44.8%; P<0.05). The mean (±SD) calving interval of the cows in parity 2 and parity 3 were 508.2±121.5 and 495.5±144.1, respectively. Number of cows with calving interval of 400 and 450 days in parity 3 was higher than those cows in parity 2 (23.1% vs. 17.2% and 53.9% vs. 31.0%). Cows in parity 1 had significantly (P<0.01) lower number of S/C in comparison to the cows with parity 2 and parity 3 (1.6±1.2 vs. 3.5±3.4 and 3.3±2.1). It can be concluded that reproductive performance of the cows is affected by different parities.

Keywords: dairy cows, parity, days open, calving interval, service per conception

Procedia PDF Downloads 223
7 Effect of the Truss System to the Flexural Behavior of the External Reinforced Concrete Beams

Authors: Rudy Djamaluddin, Yasser Bachtiar, Rita Irmawati, Abd. Madjid Akkas, Rusdi Usman Latief

Abstract:

The aesthetic qualities and the versatility of reinforced concrete have made it a popular choice for many architects and structural engineers. Therefore, the exploration of natural materials such as gravels and sands as well as lime-stone for cement production is increasing to produce a concrete material. The exploration must affect to the environment. Therefore, the using of the concrete materials should be as efficient as possible. According to its natural behavior of the concrete material, it is strong in compression and weak in tension. Therefore the contribution of the tensile stresses of the concrete to the flexural capacity of the beams is neglected. However, removing of concrete on tension zone affects to the decreasing of flexural capacity. Introduce the strut action of truss structures may an alternative to solve the decreasing of flexural capacity. A series of specimens were prepared to clarify the effect of the truss structures in the concrete beams without concrete on the tension zone. Results indicated that the truss system is necessary for the external reinforced concrete beams. The truss system of concrete beam without concrete on tension zone (BR) could develop almost same capacity to the normal beam (BN). It can be observed also that specimens BR has lower number of cracks than specimen BN. This may be caused by the fact that there was no bonding effect on the tensile reinforcement on specimen BR to distribute the cracks.

Keywords: external reinforcement, truss, concrete beams, flexural behavior

Procedia PDF Downloads 408
6 Risk-Based Institutional Evaluation of Trans Sumatera Toll Road Infrastructure Development to Improve Time Performance

Authors: Muhammad Ridho Fakhrin, Leni Sagita Riantini, Yusuf Latief

Abstract:

Based on the 2015-2019 RPJMN data, the realization of toll road infrastructure development in Indonesia experienced a delay of 49% or 904 km of the total plan. One of the major causes of delays in development is caused by institutional factors. The case study taken in this research is the construction of the Trans Sumatra Toll Road (JTTS). The purpose of this research is to identify the institutional forms, functions, roles, duties, and responsibilities of each stakeholder and the risks that occur in the Trans Sumatra Toll Road Infrastructure Development. Risk analysis is implemented on functions, roles, duties, responsibilities of each existing stakeholder and is carried out at the Funding Stage, Technical Planning Stage, and Construction Implementation Stage in JTTS. This research is conducted by collecting data through a questionnaire survey, then processed using statistical methods, such as homogeneity, data adequacy, validity, and reliability test, continued with risk assessment based on a risk matrix. The results of this study are the evaluation and development of institutional functions in risk-based JTTS development can improve time performance and minimize delays in the construction process.

Keywords: institutional, risk management, time performance, toll road

Procedia PDF Downloads 118
5 Application of Enzyme-Mediated Calcite Precipitation for Surface Control of Gold Mining Tailing Waste

Authors: Yogi Priyo Pradana, Heriansyah Putra, Regina Aprilia Zulfikar, Maulana Rafiq Ramadhan, Devyan Meisnnehr, Zalfa Maulida Insani

Abstract:

This paper studied the effects and mechanisms of fine-grained tailing by Enzyme-Mediated Calcite Precipitation (EMCP). Grouting solution used consists of reagents (CaCl₂ and (CO(NH₂)₂) and urease enzymes which react to produce CaCO₃. In sample preparation, the test tube is used to investigate the precipitation rate of calcite. The grouting solution added is 75 mL for one mold sample. The solution was poured into a mold sample up to as high as 5 mm from the top surface of the tailing to ensure the entire surface is submerged. The sample is left open in a cylinder for up to 3 days for curing. The direct mixing method is conducted so that the cementation process occurs by evenly distributed. The relationship between the results of the UCS test and the calcite precipitation rate likely indicates that the amount of calcite deposited in treated tailing could control the strength of the tailing. The sample results are analyzed using atomic absorption spectroscopy (AAS) to evaluate metal and metalloid content. Calcium carbonate deposited in the tailing is expected to strengthen the bond between tailing granules, which are easily slipped on the banks of the tailing dam. The EMCP method is expected to strengthen tailing in erosion-control surfaces.

Keywords: tailing, EMCP, UCS, AAS

Procedia PDF Downloads 106
4 Evaluation of Geotechnical Parameters at Nubian Habitations in Kurkur Area, Aswan, Egypt

Authors: R. E. Fat-Helbary, A. A. Abdel-latief, M. S. Arfa, Alaa Mostafa

Abstract:

The Egyptian Government proposed a general plan, aiming at constructing new settlements for Nubian in south Aswan in different places around Nasser Lake, one of these settlements in Kurkur area. The Nubian habitations in Wadi Kurkur are located around 30 km southwest of Aswan City. This area are affecting by near distance earthquakes from Kalabsha faults system. The shallow seismic refraction technique was conducted at the study area, to evaluate the soil and rock material quality and geotechnical parameters, in addition to the detection of the subsurface ground model under the study area. The P and S-wave velocities were calculated. The surface layer has P-wave, velocity ranges from 900 m/sec to 1625 m/sec and S-wave velocity ranges from 650 m/sec to 1400 m/sec. On the other hand the bedrock has P-wave velocity ranges from 1300 m/sec to 1980 m/sec and S-wave velocity ranges from 1050 m/sec to1725 m/sec. Measuring Vp and Vs velocities together with bulk density are calculated and used to extract the mechanical properties and geotechnical parameters of the foundation material at the study area. Output of this study is very important for solving the problems, which associated with the construction of various civil engineering purposes, for land use planning and for earthquakes resistant structure design.

Keywords: shallow seismic refraction technique, Kurkur area, p and s-wave velocities, geotechnical parameters, bulk density, Kalabsha faults

Procedia PDF Downloads 393
3 Analyzing the Sensation of Jogja Kembali Monument (Monjali): Case Study of Yogyakarta as the Implementation of Attraction Tour

Authors: Hutomo Abdurrohman, Muhammad Latief, Waridatun Nida, Ranta Dwi Irawati

Abstract:

Yogyakarta Kembali Monument (Monjali) is one of the most popular tourist attraction in Yogyakarta. Yogyakarta is known as ‘Student City’, and Monjali is a right place to learn and explore more about Yogyakarta, especially for students in elementary and junior high school to do the study tour. Monjali is located in North Ringroad, Jongkang, Sariharjo village, Ngaglik Subdistrict, Sleman Regency, Yogyakarta. Monjali offers many historical replicas, and also the story behind them. That is about the war between Indonesia's fighter, called TNI (Indonesian national army) and the colonizer of Netherlands in Yogyakarta, on March, 1st 1949. That event could open the eyes of the whole of Indonesia, because at that time the TNI was placed by the invaders. This research is an effort to evaluate the visitor's interest in Monjali as a special tourist attraction. The substance that we use in this research is the Monjali's visitors whom up to 17 years old by taking a respondent in every 15 persons who visit Monjali, and we need 200 respondents to know the condition and facilities of Monjali. This research has been collected since January 2017 until October 2017. We do the interview and spread the questionnaire which has been tested all of its validity and reliability. This data analysis is descriptive statistic analysis by using the qualitative data, which is converted into the quantitative data, use the Linkert Scale. The result of this research shows that the interest of Monjali's visitors is higher 75,6%. Based on the result, we know that Monjali is being an attractiveness for people which always experience its improvements and the development. Monjali is the success to be a place which combines the entertainment with its education as a vision of Yogyakarta as a Student City.

Keywords: descriptive statistical analysis, Jogja Kembali monument, Linkert scale, sensation

Procedia PDF Downloads 157
2 Building Information Modelling for Construction Delay Management

Authors: Essa Alenazi, Zulfikar Adamu

Abstract:

The Kingdom of Saudi Arabia (KSA) is not an exception in relying on the growth of its construction industry to support rapid population growth. However, its need for infrastructure development is constrained by low productivity levels and cost overruns caused by factors such as delays to project completion. Delays in delivering a construction project are a global issue and while theories such as Optimism Bias have been used to explain such delays, in KSA, client-related causes of delays are also significant. The objective of this paper is to develop a framework-based approach to explore how the country’s construction industry can manage and reduce delays in construction projects through building information modelling (BIM) in order to mitigate the cost consequences of such delays.  It comprehensively and systematically reviewed the global literature on the subject and identified gaps, critical delay factors and the specific benefits that BIM can deliver for the delay management.  A case study comprising of nine hospital projects that have experienced delay and cost overruns was also carried out. Five critical delay factors related to the clients were identified as candidates that can be mitigated through BIM’s benefits. These factors are: Ineffective planning and scheduling of the project; changes during construction by the client; delay in progress payment; slowness in decision making by the client; and poor communication between clients and other stakeholders. In addition, data from the case study projects strongly suggest that optimism bias is present in many of the hospital projects. Further validation via key stakeholder interviews and documentations are planned.

Keywords: building information modelling (BIM), clients perspective, delay management, optimism bias, public sector projects

Procedia PDF Downloads 291
1 The Effectiveness of E-Training on the Attitude and Skill Competencies of Vocational High School Teachers during Covid-19 Pandemic in Indonesia

Authors: Sabli, Eddy Rismunandar, Akhirudin, Nana Halim, Zulfikar, Nining Dwirosanti, Wila Ningsih, Pipih Siti Sofiah, Danik Dania Asadayanti, Dewi Eka Arini Algozi, Gita Mahardika Pamuji, Ajun, Mangasa Aritonang, Nanang Rukmana, Arief Rachman Wonodhipo, Victor Imanuel Nahumury, Lili Husada, Wawan Saepul Irwan, Al Mukhlas Fikri

Abstract:

Covid-19 pandemic has widely impacted the lives. An adaptive strategy must be quickly formulated to maintain the quality of education, especially by vocational school which technical skill competencies are highly needed. This study aimed to evaluate the effectiveness of e-training on the attitude and skill competencies of vocational high school teachers in Indonesia. A total of 720 Indonesian vocational high school teachers with various programs, including hospitality, administration, online business and marketing, culinary arts, fashion, cashier, tourism, haircut, and accounting participated e-training for a month. The training used electronic learning management system to provide materials (modules, presentation slides, and tutorial videos), tasks, and evaluations. Tutorial class was carried out by video conference meeting. Attitude and skill competencies were evaluated before and after the training. Meanwhile, the teachers also gave satisfactory feedback on the quality of the organizer and tutors. Data analysis used paired sample t-test and Anova with Tukey’s post hoc test. The results showed that e-training significantly increased the score of attitude and skill competencies of the teachers (p <0,05). Moreover, the remarkable increase was found among hospitality (57,5%), cashier (50,1%), and online business and marketing (48,7%) teachers. However, the effect among fashion, tourism and haircut teachers was less obvious. In addition, the satisfactory score on the quality of the organizer and tutors were 88,9 (very good), and 93,5 (excellence), respectively. The study concludes that a well-organized e-training could increase the attitude and skill competencies of Indonesian vocational high school teachers during Covid-19 pandemic.

Keywords: E-training, skill, teacher, vocational high school

Procedia PDF Downloads 106