Sustainable Upgrade of Existing Heritage Infrastructure: Strengthening and Rehabilitation of the LH Ford Bridge
Authors: Vince Scolaro, Lakshman Prasad, Ted Polley, Sanjivan Deshpande
Abstract:
The LH Ford Bridge, built in the 1960’s, comprises 28 spans, is 800 m long and crosses the Macquarie River at Dubbo, NSW. The main bridge spans comprise three spans with a 63 m centre span (25 m drop-in section) supported by halving joints from the main cantilevers and back spans of 28 m. The main bridge spans were built using complex construction staging (first of this type in NSW). They comprise twin precast boxes, in-situ reinforced concrete infills, and cantilevered outriggers stressed both longitudinally and transversely. Since construction, this bridge has undergone significantly increased design vehicle loads and showed signs of excessive shrinkage and creep leading to significant sagging of the centre span with evidence of previous failure and remediation of the halving joints. A comprehensive load rating assessment was undertaken taking account of the original complex construction staging. Deficiencies identified included, inadequate capacity of the halving joints, failure of the bearings at the halving joints, inadequate shear capacity of the girder webs and inadequate girder flexural capacity to carry B-Double design vehicles. A strengthening system comprising two new piers (under each of the halving joints), new bearings and installation of external prestressing to the soffit of both drop-in-span and back spans was adopted. A portion of dead load had to be transferred from the superstructure to the new piers via innovative soft/stiff bearing combinations to reduce new locked in stresses resulting from the new pier supports. Significant temporary works comprised a precast concrete shell beam forming the pile cap/pier structure, addition of temporary suspended scaffold (without overstressing the existing superstructure) and installation of jacking stays for new bearing top and bottom plates. This paper presents how this existing historic and socially important bridge was strengthened and updated to increase its design life without the need for replacement.
Keywords: Strengthening, creep, construction, box girder.
Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 96References:
[1] NAASRA Highway 1965 Bridge Design Specification.
[2] AS 5100:2004 Bridge Design Standard (Parts 1-5 and 7)
[3] AS 5100.5:2015 Concrete Interim RMS Edition – Rev 2
[4] Bridge Deck Behaviour by EC Hambly – 2nd Edition 1991
[5] Menn, C et al. (1990) Prestressed Concrete Bridges, Birkhäuser Verlag, Basel, Germany.
[6] LH Ford Bridge design drawings dated 5.10.1967
[7] LH Ford Bridge design drawings dated 31.5.1973
[8] LH Ford Bridge design drawings dated 18.2.2015