Non-Chronological Approach in Crane Girder and Composite Steel Beam Installation: Case Study
Commenced in January 2007
Frequency: Monthly
Edition: International
Paper Count: 32797
Non-Chronological Approach in Crane Girder and Composite Steel Beam Installation: Case Study

Authors: Govindaraj Ramanathan

Abstract:

The time delay and the structural stability are major issues in big size projects due to several factors. Improper planning and poor coordination lead to delay in construction, which sometimes result in reworking or rebuilding. This definitely increases the cost and time of project. This situation stresses the structural engineers to plan out of the limits of contemporary technology utilizing non-chronological approach with creative ideas. One of the strategies to solve this issue is through structural integrity solutions in a cost-effective way. We have faced several problems in a project worth 470 million USD, and one such issue is crane girder installation with composite steel beams. We have applied structural integrity approach with the proper and revised planning schedule to solve the problem efficiently with minimal expenses.

Keywords: Construction management, delay, non-chronological approach, composite beam, structural integrity.

Digital Object Identifier (DOI): doi.org/10.5281/zenodo.1130103

Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 828

References:


[1] D. McGeorge, and P. Zou, Construction management: new directions, Wiley-Blackwell, Oxford, UK, 2013.
[2] F.J Drewin, Construction Productivity, Elsevier, New York, USA, 1982.
[3] N. Hamzah, M.A. Khoiry, I. Arshad, W.H.W. Badaruzzaman, and N. M. Tawil, “Identification of the Causes of Construction Delay in Malaysia,” International Journal of Civil, Environmental, Structural, Construction and Architectural Engineering, vol. 6, No. 12, 2012.
[4] F. Fugar, A. Agyakwah-Baah, “Delays in building construction projects in Ghana,” Australasian Journal of Construction Economics and Building, vol. 10, pp.103–116, 2010.
[5] R. F. Aziz, “Ranking of delay factors in construction projects after Egyptian revolution,” Alexandria Engineering Journal, vol. 52 no. 3, pp. 387–406, 2013.
[6] Sadi A. Assaf and Sadiq Al-Hejji, “Causes of delay in large construction projects,” International Journal of Project Management, vol. 24, no.4, pp. 349-357, 2006.