Drum-Buffer-Rope: The Technique to Plan and Control the Production Using Theory of Constraints
Commenced in January 2007
Frequency: Monthly
Edition: International
Paper Count: 32797
Drum-Buffer-Rope: The Technique to Plan and Control the Production Using Theory of Constraints

Authors: Arvind Bhardwaj, Ajay Gupta, Arun Kanda

Abstract:

Theory of Constraints has been emerging as an important tool for optimization of manufacturing/service systems. Goldratt in his first book “ The Goal " gave the introduction on Theory of Constraints and its applications in a factory scenario. A large number of production managers around the globe read this book but only a few could implement it in their plants because the book did not explain the steps to implement TOC in the factory. To overcome these limitations, Goldratt wrote this book to explain TOC, DBR and the method to implement it. In this paper, an attempt has been made to summarize the salient features of TOC and DBR listed in the book and the correct approach to implement TOC in a factory setting. The simulator available along with the book was actually used by the authors and the claim of Goldratt regarding the use of DBR and Buffer management to ease the work of production managers was tested and was found to be correct.

Keywords: Drum Buffer Rope (DBR), Optimized ProductionTechnology (OPT), Capacity Constrained Resource (CCR)

Digital Object Identifier (DOI): doi.org/10.5281/zenodo.1062694

Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 2533

References:


[1] E.M. Goldratt " The Goal: A process of ongoing improvements", North River Press, 1984
[2] E.M Goldratt " Production The TOC way", North River Rress, 2003
[3] E.M Goldratt " It-s not luck " North River Press, 1994
[4] E.M Goldratt "Theory of constraints " North River Press, 1990
[5] E.M Goldratt & R. E. Fox " The Race " North River Press, 1986
[6] Chakravorty Satya S " An evaluation of DBR control mechanism in a job shop environment " Omega, Volume 29, 2001, pp. 335- 342
[7] Duclos Leslie K, Spencer Michael S " The impact of a constraint buffer in a flow shop" International Journal of Production Economics, Volume 42, 1995, pp. 175- 185.
[8] Chakravorty Satya S, Atwater J Brian " The impact of free goods on the performance of drum-buffer-rope scheduling systems" International Journal of Production Economics, Volume 95, 2005, pp. 347-357
[9] Ribeiro M A, Silveira J L & Qassim R Y " Joint optimization of Maintenance and buffer size in a manufacturing system" European Journal of Operations Research, volume 176, 2007, pp. 405-413
[10] Daniel V, Guide R Jr. " Scheduling with the priority dispatching rules and drum-buffer-rope in a recoverable manufacturing system" International Journal of Production Economics, volume 53, 1997, pp. 101-116
[11] Wahlers James L, Cox James F " Competitive factors and performance measurement: Applying theory of constraints to meet customer needs " International Journal of Production Economics, volume 37, 1994, pp. 229-240
[12] Mishra Nihikant, Parkash, Tiwari M K, Shankar R, Felix T S Chan " Hybrid Tabu- Simulated Annealing based approach to solve multiconstraint product-mix decision problem" Expert systems with applications, Volume 29. 2005, pp. 446-454
[13] Radovilsky Zinovery D " A quantitative approach to estimate the size of Time buffer in the theory of constraints " International Journal of Production Economics, Volume 55 , 1998, 113-119
[14] Gerhard Plenert " Focusing Material requirement planning ( MRP) towards performance" European Journal of Operations Research, volume 119, 1999, pp. 91-99
[15] Michael Umble, Elisabeth J Umble " Utilizing buffer Management to improve the performance in a health care environment", European Journal of Operations Research, volume 174, 2006, 1060-1075W. D.