Work Structuring and the Feasibility of Application to Construction Projects in Vietnam

Authors: Viet-Hung Nguyen, Luh-Maan Chang

Abstract:

Design should be viewed concurrently by three ways as transformation, flow and value generation. An innovative approach to solve design – related problems is described as the integrated product - process design. As a foundation for a formal framework consisting of organizing principles and techniques, Work Structuring has been developed to guide efforts in the integration that enhances the development of operation and process design in alignment with product design. Vietnam construction projects are facing many delays, and cost overruns caused mostly by design related problems. A better design management that integrates product and process design could resolve these problems. A questionnaire survey and in – depth interviews were used to investigate the feasibility of applying Work Structuring to construction projects in Vietnam. The purpose of this paper is to present the research results and to illustrate the possible problems and potential solutions when Work Structuring is implemented to construction projects in Vietnam.

Keywords: integrated product – process design, Work Structuring, construction projects, Vietnam

Digital Object Identifier (DOI): doi.org/10.5281/zenodo.1331769

Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 1696

References:


[1] Koskela , L. (2000), An Exploration Towards a Production Theory and its Application to Construction, VTT Publications and VTT Building Technology, Espoo, 296 p. (available at http://www.inf.vtt.fi/pdf/publications/2000/P408.pdf, January 2005) 408.
[2] Ballard, G. and Zabelle, T. (2000). "Lean design: Tool and Techniques". LCI White Paper-10.
[3] Kamara, J. M., Anumba, C. J. and Evbuomwan, N. F. O. (2000), ÔÇÿDevelopments in the Implementation of Concurrent Engineering in Construction-, International Journal of Computer-Integrated Design and Construction, Vol. 2, No. 1, pp. 68-78.
[4] Tsao, C.C.Y. (2005) "Use of Work Structuring to Increase Performance of Project-Based Production Systems" PhD. thesis, Univ. of California, Berkeley, USA.
[5] Best, R. and Vanlence, G. de (2002). "Design and Construction: Building in Value." Butterworth-Heinemann, Elsevier, Oxford, UK.
[6] Gleeson, F. and Townend J. (2007). "Lean construction in the corporate world of the U.K. construction industry", University of Manchester, School of Mechanical, Aerospace, Civil and Construction Engineering.
[7] Howell, G. A. (1999). "What is Lean Construction." Lean Construction Institute.
[8] Koskela, L., Howell, G., Ballard, G., and Tommelein, I. (2002). "The Foundations of Lean Construction." Design and Construction: Building in Value, R. Best, and G. de Valence, eds., Butterworth-Heinemann, Elsevier, Oxford, UK.
[9] Ballard, G. (2000b). "Lean Project Delivery Systems." LCI white paper- 8, (Revision 1).
[10] Ballard, G. (1999). "Work Structuring." Lean Construction Institute White Paper-4.
[11] Halpin, D. W., Escalona, A. L., and Szmurlo, P. M. (1987). "Work packaging for project control management." Source Document 28, Construction Industry Institute, Austin, Tex.
[12] Project Management Institute, "A guide to the project management body of knowledge", PMBOK 4th, 2008.
[13] Wilson, P.E., Dell, L.D., and Anderson, G.F. (1993). "Root cause analysis: A tool for total quality management", ASQ Quality Press, Milwaukee.
[14] Ohno, T., (1988). "Toyota project delivery system: Beyond large - scale production." Productivity Press, Portland, Ore.
[15] Howell, G. A., Laufer, A., and Ballard, G. (1993). "Interation between subcycles: one key to improved methods." J. Constr. Eng. Manageme., 199(4), pp. 714 - 728.
[16] Ballard, G. and Howel, G. (1994). "Implementing lean construction: stabilizing work flow." Proc., 2nd Annual Conf. of the Int. Group for Lean Construction, Santiago, Chile.
[17] Ballard, G. and Howel, G. (1995). "Toward construction JIT." Proc., 11th Annual ARCOM Conf., University of York, U.K..
[18] Park, M., and Pe├▒a-Mora, F. (2004). "Reliability Buffering for Construction Projects," J. of Construction Engineering and Management, ASCE, September/October, 130(5), pp. 626-637.
[19] Horman, M., Hewitt, C., Cross, J., Pulaski, M. 2003. "Steel fabricator involvement in project design."Forthcoming Proceedings to the Second International Conference on Structural Engineering and Construction (ISEC-02). Rome, Italy.
[20] Horman, M.J. and Thomas, H. R.h (2005). "Role of inventory buffers in construction labor performance". ASCE.
[21] Alves, T. da C.L. and Iris, D. T. (2003). "Simulation of buffering and batching practices in the interface Detailing-Fabrication-Installation of HVAC ductwork".
[22] Howell, G.A. and Ballard, H.G. (1996) Managing uncertainty in the piping process. RR47-13, Construction Industry Institute, Univ. of Texas, Austin, TX, September, 103pp.
[23] Field, A (2005). "Discovering statistics using SPSS." Thousand Oaks, Calif. : Sage Publications, London, UK.