Implementing Activity-Based Costing in Architectural Aluminum Projects: Case Study and Lessons Learned
Authors: Amer Momani, Tarek Al-Hawari, Abdallah Alakayleh
Abstract:
This study explains how to construct an actionable activity-based costing and management system to accurately track and account the total costs of architectural aluminum projects. Two Activity-Based Costing (ABC) models were proposed to accomplish this purpose. First, the learning and development model was introduced to examine how to apply an ABC model in an architectural aluminum firm for the first time and to be familiar with ABC concepts. Second, an actual ABC model was built on the basis of the results of the previous model to accurately trace the actual costs incurred on each project in a year, and to be able to provide a quote with the best trade-off between competitiveness and profitability. The validity of the proposed model was verified on a local architectural aluminum company.
Keywords: Activity-based costing, activity-based management, construction, architectural aluminum.
Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 3References:
[1] Tompkins, J. A. et al. 2010. Facilities Planning. 4th ed. Hoboken, N.J.: John Wiley & Sons.
[2] Kissell, J. R. and Ferry, R. L. 2002. Aluminum Structures: A Guide to Their Specifications and Design. 2nd ed., New York: J. Wiley.
[3] Carmody, J. et al. 2004. Window systems for high-performance buildings. New York: Norton.
[4] Allen, E. and Iano, J. 2009. Fundamentals of Building Construction. 5th ed. Hoboken, New Jersey: John Wiley & Sons.
[5] Amoa-abban, K. 2017. An assessment on the use of glass as a curtain walling material in high rise buildings in ghana. International Journal of Advanced Engineering Research and Technology, 5(6), 428–438.
[6] Lee, A. D. et al. 2018. Optimizing the architectural layouts and technical specifications of curtain walls to minimize use of aluminium. Structures, 13, 8–25.
[7] Halpin, D. W. and Senior, B. A. 2009. Financial Management and Accounting Fundamentals for Construction. New Jersey: J. Wiley.
[8] Archibald, R. D. 2003. Managing High-Technology Programs and Protects. 3rd ed. Hoboken, N.J.: J. Wiley.
[9] Rozenes, S., Vitner, G. and Sparggett, S. 2006. Project control: literature review, Project Management Journal, 37(4), 5–14.
[10] Wysocki, R. K. 2013. Effective Project Management: Traditional, Agile, Extreme. 7th ed. Hoboken, N.J.: Wiley.
[11] H’mida, F., Martin, P. and Vernadat, F. 2006. Cost estimation in mechanical production: The cost entity approach applied to integrated product engineering. International Journal of Production Economics, 103(1), 17–35.
[12] Raz, T. and Elnathan, D. 1999. Activity based costing for projects. International Journal of Project Management, 17(1), 61–67.
[13] Chao, L. C. and Kuo, C. P. 2016. Probabilistic Approach to Determining Overhead-cum-markup Rate in Bid Price. Procedia Engineering,164, 243–250.
[14] Arditi, D. and Mochtar, K. 2000. Trends in productivity improvement in the US construction industry. Construction Management and Economics, 18(1), 15–27.
[15] Baykasoǧlu, A. and Kaplanoǧlu, V. 2008. Application of activity-based costing to a land transportation company: A case study. International Journal of Production Economics, 116(2), 308–324.
[16] Zhang, M. and Tseng, M. M.2007. A product and process modeling based approach to study cost implications of product variety in mass customization. IEEE Transactions on Engineering Management, 54(1), 130–144.
[17] Mishra, B. and Vaysman, I. 2001. Cost-system choice and incentives - traditional vs. activity-based costing. Journal of Accounting Research, 39(3), 619–641.
[18] Homburg, C. 2004. Improving activity-based costing heuristics by higher-level cost drivers. European Journal of Operational Research, 157(2), 332–343.
[19] Roztocki, N. et al. 2004. A procedure for smooth implementation of activity-based costing in small companies. EMJ - Engineering Management Journal, 16(4), 19–27.
[20] Elfahham, Y. 2020. Estimation and prediction of construction cost index using neural networks, time series, and regression. Alexandria Engineering Journal, 58(2), 499–506.
[21] Maruvanchery, V., Zhe, S. and Robert, T. 2020. Early construction cost and time risk assessment and evaluation of large-scale underground cavern construction projects in Singapore. Underground Space, 5(1), 53-70
[22] Ahn, J., Park, M., Lee, H., Ahn, S., Ji, S., Song, K., and Son, B. 2017. Covariance effect analysis of Similarity measurement methods for early construction cost estimation using case-based reasoning. Automation in Construction, 81, 254–266.
[23] Cheng, M., Tsai, H., and Hsieh, W. 2009. Web-based conceptual cost estimates for construction projects using Evolutionary Fuzzy Neural Inference model. Automation in Construction, 81(2), 164–172.
[24] Firouzi, A., Yang, W., and Li, C. 2016. Prediction of total cost of construction project with dependent cosy items. Journal of Construction Engineering and Management, 142(12), 1-9.
[25] Amusan, L., Afolabi, A., Ojelabi, R., Omuh, I., and Okagbue, H. 2018. Data exploration on factors that influnces construction cost and time performance on construction project sites. Data in Brief, 17(1), 1320–1325.
[26] Hatamleh, M., Hiyassat, M., Sweis, G., and Sweis, R. 2018. Factors affecting the accuracy of cost estimate: case of Jordan. Engineering Construction & Architectural Management, 25(1), 113–131.
[27] Toh, T., Ting, C, Ali, K, Aliagha, G., and Munir, O. 2012. Critical cost factors for building construction projects in Malaysia. Procedia- Social and Behavioral Sciences, 57, 360–367.
[28] Al-Amri, T. and Marey-pérez, M. 2020. Towards a Sustainable Construction Industry: Delays and Cost Overrun Causes in Construction Projects of Oman. Journal of Project Management, 5(2), 87–102.
[29] Knight, K. and Fayek, A. 2002. Use of fuzzy logic for predicting design cost overruns on building projects. Journal of Construction Engineering and Management, 128(6), 503–512.
[30] Williams, T. and Gong, J. 2014. Predicting construction cost overruns using text mining, numerical data and ensemble classifiers. Automation in Construction, 43, 23–29.
[31] Šiškina, A., Juodis, A. and Apanavičienė, R. 2009. Evaluation of the competitiveness of construction company overhead costs. Journal of Civil Engineering and Management, 15(2), 215–224.
[32] Kim, Y. and Ballard, G. 2001. Activity-based costing and its application to lean construction, Proceedings of the 9th Annual Conference of the International Group for Lean Construction, Singapore, 6-8.
[33] Al-Araidah, O. et al. 2012. Costing of the production and delivery of ready-mix-concrete. Jordan Journal of Mechanical and Industrial Engineering, 6(2), 163–173.
[34] Kim, Y. W. et al. 2011. A case study of activity-based costing in allocating rebar fabrication costs to projects. Construction Management and Economics, 29(5), 449–461.
[35] Ayachit, A. C., Attarde, P. M. and Kulkarni, S. 2014. Activity based costing in construction project. International Journal of Advanced Engineering Research and Studies, 4(1), 9–14.
[36] Foroughi, A. et al. 2017. Activity-Based Costing: helping small and medium-sized firms achieve a competitive edge in the global marketplace. Research in Economics and Management, 2(5), 150.
[37] Kim, Y. 2017. Activity Based Costing for Construction Companies. 1st ed. UK: John Wiley & Sons.
[38] Lere, J. C. and Saraph, J. V. 1995. Activity-based costing for purchasing managers’ cost and pricing determinations. International Journal of Purchasing and Materials Management, 31(3), 25–31.
[39] Horngren, C. T., Datar, S. M. and Rajan, M. V 2012. Cost Accounting: A Managerial Emphasis. 14th ed. Upper Saddle River, N.J.: Pearson/Prentice Hall.
[40] Ghicajanu, M. 2008. Activity Based Management - efficiency method of the management control systems. Annals of the University of Petrosani Economics, 8(1), 219–222.
[41] Partridge, M. and Perren, L. 1998. An integrated framework for activity-based decision making. Management Decision, 36(9), 580–588.
[42] Thomas Johnson, H. 1991. Activity-based management: past, present, and future. The Engineering Economist, 36(3), 219–238.
[43] Turney, P. B. 1989. Using activity-based costing to achieve manufacturing excellence. Journal of Cost Management, 3(2), 23–31.
[44] Cooper, R. and Kaplan, R. S. 1992. Activity-based systems: Measuring the costs of resource usage. Accounting Horizons, 6(3), 1–13
[45] Gunasekaran, A., McNeil, R. and Singh, D. 2000. Activity-based management in a small company: a case study. Production Planning and Control, 11(4), 391–399.