Critical Success Factors Influencing Construction Project Performance for Different Objectives: Procurement Phase
Authors: Samart Homthong, Wutthipong Moungnoi
Abstract:
Critical success factors (CSFs) and the criteria to measure project success have received much attention over the decades and are among the most widely researched topics in the context of project management. However, although there have been extensive studies on the subject by different researchers, to date, there has been little agreement on the CSFs. The aim of this study is to identify the CSFs that influence the performance of construction projects, and determine their relative importance for different objectives across five stages in the project life cycle. A considerable literature review was conducted that resulted in the identification of 179 individual factors. These factors were then grouped into nine major categories. A questionnaire survey was used to collect data from three groups of respondents: client representatives, consultants, and contractors. Out of 164 questionnaires distributed, 93 were returned, yielding a response rate of 56.7%. Using the mean score, relative importance index, and weighted average method, the top 10 critical factors for each category were identified. The agreement of survey respondents on those categorised factors were analysed using Spearman’s rank correlation. A one-way analysis of variance was then performed to determine whether the mean scores among the various groups of respondents were statistically significant. The findings indicate the most CSFs in each category in procurement phase are: proper procurement programming of materials (time), stability in the price of materials (cost), and determining quality in the construction (quality). They are then followed by safety equipment acquisition and maintenance (health and safety), budgeting allowed in a contractual arrangement for implementing environmental management activities (environment), completeness of drawing documents (productivity), accurate measurement and pricing of bill of quantities (risk management), adequate communication among the project team (human resource), and adequate cost control measures (client satisfaction). An understanding of CSFs would help all interested parties in the construction industry to improve project performance. Furthermore, the results of this study would help construction professionals and practitioners take proactive measures for effective project management.
Keywords: Critical success factors, procurement phase, project life cycle, project performance.
Digital Object Identifier (DOI): doi.org/10.5281/zenodo.1338973
Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 2245References:
[1] V. Sanvido, F. Grobler, K. Parfitt, M. Guvenis, and M. Coyle, “Critical Success Factors for Construction Projects,” Journal of Construction Engineering and Management, vol. 118, no. 1, pp. 94-111, March 1992.
[2] A.P.C. Chan, D. Scott, and A.P.L. Chan, “Factors Affecting the Success of a Construction Project,” Journal of Construction Engineering and Management, vol. 130, no. 1, pp. 153-155, February 2004.
[3] S. Toor, and S. Ogunlana, “Critical COMs of Success in Large-Scale Construction Projects: Evidence from Thailand Construction Industry,” International Journal of Project Management, vol. 26, no. 4, pp. 420-430, May 2008.
[4] A.P.C. Chan, and A.P.L. Chan, “Key Performance Indicators for Measuring Construction Success,” Benchmarking: An International Journal, vol. 11, no. 2, pp. 203 – 221, 2004
[5] L. Teeratansirikool, S. Siengthai, Y. Badir, and C. Charoenngam, “Competitive Strategies and Firm Performance: The Mediating role of Performance Measurement,” International Journal of Productivity and Performance Management, vol. 62, no. 2, pp. 160-184, 2013.
[6] H. Yang, J.F.Y. Yeung, A.P.C. Chan, Y.H. Chiang, and D.W.M. Chan, “A Critical Review of Performance Measurement in Construction,” Journal of Facilities Management, vol. 8, no. 4, pp. 269-284, 2010.
[7] W.F. Maloney, “Framework for Analysis of Performance,” Journal of Construction Engineering and Management, vol. 116, no. 3, pp. 399-415, September 1990.
[8] J.F. Rockart, “The Changing Role of the Information Systems Executive: A Critical Success Factors Perspective,” Sloan Management Review, vol. 24, no. 1, pp. 3-13, 1982.
[9] D.W.M. Chan, and M. Kumaraswamy, “An Evaluation of Construction Time Performance in the Building Industry,” Building and Environment, vol. 31, no. 6, pp. 569-578, 1996.
[10] D.K.H. Chua, Y.C. Kog, and P.K. Loh, “Critical Success Factors for Different Project Objectives,” Journal of Construction Engineering and Management, vol. 125, no. 3, pp. 142-150, May/June 1999.
[11] T. Cooke-Davies, “The "Real" Success Factors on Projects,” International Journal of Project Management, vol. 20, pp. 185-190, 2002.
[12] K.C. Iyer, and K.N. Jha, “Critical Factors Affecting Schedule Performance: Evidence from Indian Construction Projects,” Journal of Construction Engineering and Management, vol. 132, no. 8, pp. 871-881, August 2006.
[13] A. Enshassi, S. Mohamed, and S. Abushaban, “Factors Affecting the Performance of Construction Projects in the Gaza Strip,” Journal of Civil Engineering and Management, vol. 15, no.3, pp. 269-280, 2009.
[14] S.H. Park, “Whole Life Performance Assessment: Critical Success Factors,” Journal of Construction Engineering and Management, vol. 135, no.11, pp. 1146-1161, November 2009.
[15] Y.C. Kog, and P.K. Lok, “Critical Success Factors for Different Components of Construction Projects,” Journal of Construction Engineering and Management, vol. 138, no.4, pp. 520-528, April 2012.
[16] M.E. Georgy, L. Chang, and L. Zhang, “Prediction of Engineering Performance: A Neurofuzzy Approach,” Journal of Construction Engineering and Management, vol. 131, no.5, pp. 548-557, May 2005.
[17] R. Atkinson, “Project Management: Cost, Time and Quality, Two Best Guesses and a Phenomenon, Its Time to Accept Other Success Criteria,” International Journal of Project Management, vol. 17, no. 6, pp. 337-342, 1999.
[18] C.S. Lim, and M.Z. Mohamed, “Criteria of Project Success: An Exploratory Re-examination,” International Journal of Project Management, vol. 17, no. 4, pp. 243-248, 1999.
[19] I. Yu, K. Kim, Y. Jung, and S. Chin, “Comparable Performance Measurement System for Construction Companies,” Journal of Management in Engineering, vol. 23, no.3, pp. 131-139, July 2007.
[20] J.A. Gliner, and G.A. Morgan, Research Methods in Applied Setting: An Integrated Approach to Design and Analysis, 6th ed., Lawrence Erlbaum Associates, Mahwah, NJ, 2000.
[21] U. Sekaran, Research Methods for Business: A Skill-Building Approach, 3rd ed., John Wiley, NY, 2000.
[22] D.R. Anderson, D.J. Sweeney, and T.A. Williams, Statistics for Business and Economics, 11th ed., South-Western Cengage Learning, OH, 2011, pp. 599-602.
[23] P.F. Kaming, P.O, Olomolaiye, G.D. Holt, and F.C. Harris, “Factors Influencing Construction Time and Cost Overruns on High-Rise Projects in Indonesia,” Journal of Construction Management and Economics, vol. 15, no.1, pp. 83-94, 1997.
[24] S.A. Assaf, and S. Al-Hejji, “Causes of Delay in Large Construction Projects,” International Journal of Project Management, vol. 24, pp. 349-357, 2006.
[25] K.N. Jha, and K.C. Iyer, “Critical Factors Affecting Quality Performance in Construction Projects”, Total Quality Management & Business Excellence, vol. 17, no. 9, pp.1156–1170, November 2006.
[26] S.M. Ahmed, and R. Kangari, “Analysis of Client-Satisfaction Factors in Construction Industry,” Journal of Management in Engineering, vol. 11, no.2, pp. 36-44, March/April 1995.
[27] D.W.M. Chan, and M. Kumaraswamy, “A Comparative Study of Cause of Time Overruns in Hong Kong Construction Projects,” International Journal of Project Management, vol. 15, no. 1, pp. 55-63, 1997.
[28] E.C. Lim, and J. Alum, “Construction Productivity: Issues Encountered by Contractors in Singapore,” International Journal of Project Management, vol. 13, no. 1, pp. 51-58, 1995.
[29] Y. Jang, and J. Lee, “Factors Influencing the Success of Management Consulting Projects,” International Journal of Project Management, vol. 16, no. 2, pp. 67-72, 1998.
[30] A.U. Elinwa, and S.A. Buba, “Construction Cost Factors in Nigeria,” Journal of Construction Engineering and Management, vol. 119, no.4, pp. 698-713, December 1993.
[31] R. McKim, T. Hegazy, and M. Attalla, “Project Performance Control in Reconstruction Projects,” Journal of Construction Engineering and Management, vol. 126, no.2, pp. 137-141, March/April 2000.
[32] X. Meng, Q. Zhao, and Q. Shen, “Critical Success Factors for Transfer-Operate-Transfer Urban Water Supply Projects in China,” Journal of Management in Engineering, vol. 27, no.4, pp. 243-251, October 2011.
[33] J.I. Alzahrani, and M.W. Emsley, “The Impact of Contractors’ Attributes on Construction Project Success: A Post Construction Evaluation,” International Journal of Project Management, vol. 31, pp. 313-322, 2013.
[34] A. Brown, and J. Adams, “Measuring the Effect of Project Management on Construction Outputs: A New Approach,” International Journal of Project Management, vol. 18, pp. 327-335, 2000.
[35] T.M. Toole, “Construction Site Safety Roles,” Journal of Construction Engineering and Management, vol. 128, no.3, pp. 203-210, June 2002.
[36] T. Aksorn, and B.H.W. Hadikusomo, “Critical Success Factors Influencing Safety Program Performance in Thai Construction Projects,” Safety Science, vol. 46, pp. 709-729, 2008.
[37] J.T. Tweedy, Healthcare Hazard Control and Safety Management, 2nd ed., CRC Press, 2005.
[38] L.D. Nguyen, S.O. Ogunlana, and D.T.X. Lan, “A Study on Project Success Factors in Large Construction Projects in Vietnam,” Engineering, Construction and Architectural Management, vol. 11, no. 6, pp. 404-413, 2004.
[39] M. Laborde, and V. Sanvido, “Introducing New Process Technologies into Construction Companies,” Journal of Construction Engineering and Management, vol. 120, no. 3, pp. 488-508, 1994.
[40] L.Y. Shen, and V.W.Y. Tam, “Implementation of Environmental Management in Hong Kong Construction Industry,” International Journal of Project Management, vol. 20, pp. 535-543, 2002.
[41] A. Makulsawatudom, M. Emsley, and K. Sinthawanarong, “Critical Factor Influencing Construction Productivity in Thailand,” The Journal of King Mongkut’s Institute of Technology North Bangkok, vol. 14, no. 3, July-September 2004.
[42] A. Enshassi , F. Arain, and S. Al‐Raee, “Causes of Variation Orders in Construction Projects in the Gaza Strip, Journal of Civil Engineering and Management, vol. 16, no. 4, pp. 540-551, 2010.
[43] P.F. Kaming, P.O, Olomolaiye, G.D. Holt, and F.C. Harris, “Factors Influencing Craftsmen’s Productivity in Indonesia,” International Journal of Project Management, vol. 15, no. 1, pp. 21-30, 1997.
[44] A. Enshassi, S. Mohamed, Z.A. Mustafa, and P.E. Mayer, “Factors Affecting Labour Productivity in Building Projects in the Gaza Strip,” Journal of Civil Engineering and Management, vol. 13, no. 4, pp. 245-254, 2007.
[45] H.M. Alinaitwe, J.A. Mwakali, and B. Hansson, “Factors affecting the productivity of building craftsmen – studies of Uganda,” Journal of Construction Engineering and Management, vol. 13, no. 3, pp. 169-176, 2007.
[46] A.C. Twort, and J.G. Rees, Civil Engineering Project Management, 4th ed., Elsevier Butterworth-Heinemann, Oxford, UK, 2004.
[47] S.O. Ogunlana, K. Promkuntong, and V. Jearkjirm, “Construction Delays in a Fast-Growing Economy: Comparison Thailand with Other Economics,” International Journal of Project Management, vol. 14, no. 14, pp. 37-45, 1996.
[48] V.T. Luu, S.Y. Kim, N.V. Tuan, and S.O. Ogunlana, “Quantifying Schedule Risk in Construction Projects Using Bayesian Belief Networks,” International Journal of Project Management, vol. 27, pp. 39-50, 2009.
[49] W.F. Maloney, “Construction Product/Service and Customer Satisfaction,” Journal of Construction Engineering and Management, vol. 128, no. 6, pp. 522-529, December 2002.
[50] Project Management Institute, A Guide to the Project Management Body of Knowledge: PMBOK Guide, 4th ed., Project Management Institute, Newtown Square, PA, USA, 2008.
[51] S. L. Tang, M. Lu, and Y. L. Chan, “Achieving Client Satisfaction for Engineering Consulting Firms,” Journal of Management in Engineering, vol. 19, no. 4, pp. 166-172, October 2003.