2191 Empirical Study of Correlation between the Cost Performance Index Stability and the Project Cost Forecast Accuracy in Construction Projects

Authors: Amin AminiKhafri, James M. Dawson-Edwards, Ryan M. Simpson, Simaan M. AbouRizk

Abstract:

Earned value management (EVM) has been introduced as an integrated method to combine schedule, budget, and work breakdown structure (WBS). EVM provides various indices to demonstrate project performance including the cost performance index (CPI). CPI is also used to forecast final project cost at completion based on the cost performance during the project execution. Knowing the final project cost during execution can initiate corrective actions, which can enhance project outputs. CPI, however, is not constant during the project, and calculating the final project cost using a variable index is an inaccurate and challenging task for practitioners. Since CPI is based on the cumulative progress values and because of the learning curve effect, CPI variation dampens and stabilizes as project progress. Although various definitions for the CPI stability have been proposed in literature, many scholars have agreed upon the definition that considers a project as stable if the CPI at 20% completion varies less than 0.1 from the final CPI. While 20% completion point is recognized as the stability point for military development projects, construction projects stability have not been studied. In the current study, an empirical study was first conducted using construction project data to determine the stability point for construction projects. Early findings have demonstrated that a majority of construction projects stabilize towards completion (i.e., after 70% completion point). To investigate the effect of CPI stability on cost forecast accuracy, the correlation between CPI stability and project cost at completion forecast accuracy was also investigated. It was determined that as projects progress closer towards completion, variation of the CPI decreases and final project cost forecast accuracy increases. Most projects were found to have 90% accuracy in the final cost forecast at 70% completion point, which is inlined with findings from the CPI stability findings. It can be concluded that early stabilization of the project CPI results in more accurate cost at completion forecasts.

Keywords: cost performance index, earned value management, empirical study, final project cost

Procedia PDF Downloads 127
2190 The Relationship between Ruins and Vegetation: Different Approaches during the Centuries and within the Various Disciplinary Fields, Investigation of Writings and Projects

Authors: Rossana Mancini

Abstract:

The charm of a ruin colonised by wild plants and flowers is part of Western culture. The relationship between ruins and vegetation involves a wide range of different fields of research. During the first phase of the research the most important writings and projects about this argument were investigated, to understand how the perception of the co-existence of ruins and vegetation has changed over time and to investigate the various different approaches that these different fields have adopted when tackling this issue. The paper presents some practical examples of projects carried out from the early 1900s on. The major result is that specifically regards conservation, the best attitude is the management of change, an inevitable process when it comes to the co-existence of ruins and nature and, particularly, ruins and vegetation. Limiting ourselves to adopting measures designed to stop, or rather slow down, the increasing level of entropy (and therefore disorder) may not be enough.

Keywords: ruins, vegetation, conservation, archaeology, architecture

Procedia PDF Downloads 297
2189 A Literature Review on Sustainability Appraisal Methods for Highway Infrastructure Projects

Authors: S. Kaira, S. Mohamed, A. Rahman

Abstract:

Traditionally, highway infrastructure projects are initiated based on their economic benefits, thereafter environmental, social and governance impacts are addressed discretely for the selected project from a set of pre-determined alternatives. When opting for cost-benefit analysis (CBA), multi-criteria decision-making (MCDM) has been used as the default assessment tool. But this tool has been critiqued as it does not mimic the real-world dynamic environment. Indeed, it is because of the fact that public sector projects like highways have to experience intense exposure to dynamic environments. Therefore, it is essential to appreciate the impacts of various dynamic factors (factors that change or progress with the system) on project performance. Thus, this paper presents various sustainability assessment tools that have been globally developed to determine sustainability performance of infrastructure projects during the design, procurement and commissioning phase. Indeed, identification of the current gaps in the available assessment methods provides a potential to add prominent part of knowledge in the field of ‘road project development systems and procedures’ that are generally used by road agencies.

Keywords: dynamic impact factors, micro and macro factors, sustainability assessment framework, sustainability performance

Procedia PDF Downloads 105
2188 Prioritization Assessment of Housing Development Risk Factors: A Fuzzy Hierarchical Process-Based Approach

Authors: Yusuf Garba Baba

Abstract:

The construction industry and housing subsector are fraught with risks that have the potential of negatively impacting on the achievement of project objectives. The success or otherwise of most construction projects depends to large extent on how well these risks have been managed. The recent paradigm shift by the subsector to use of formal risk management approach in contrast to hitherto developed rules of thumb means that risks must not only be identified but also properly assessed and responded to in a systematic manner. The study focused on identifying risks associated with housing development projects and prioritisation assessment of the identified risks in order to provide basis for informed decision. The study used a three-step identification framework: review of literature for similar projects, expert consultation and questionnaire based survey to identify potential risk factors. Delphi survey method was employed in carrying out the relative prioritization assessment of the risks factors using computer-based Analytical Hierarchical Process (AHP) software. The results show that 19 out of the 50 risks significantly impact on housing development projects. The study concludes that although significant numbers of risk factors have been identified as having relevance and impacting to housing construction projects, economic risk group and, in particular, ‘changes in demand for houses’ is prioritised by most developers as posing a threat to the achievement of their housing development objectives. Unless these risks are carefully managed, their effects will continue to impede success in these projects. The study recommends the adoption and use of the combination of multi-technique identification framework and AHP prioritization assessment methodology as a suitable model for the assessment of risks in housing development projects.

Keywords: risk management, risk identification, risk analysis, analytic hierarchical process

Procedia PDF Downloads 82
2187 The Shape Memory Recovery Properties under Load of a Polymer Composite

Authors: Abdul Basit, Gildas Lhostis, Bernard Durand

Abstract:

Shape memory polymers (SMPs) are replacing shape memory alloys (SMAs) in many applications as SMPs have certain superior properties than SMAs. However, SMAs possess some properties like recovery under stress that SMPs lack. SMPs cannot give complete recovery even under a small load. SMPs are initially heated close to their transition temperature (glass transition temperature or the melting temperature). Then force is applied to deform the heated SMP to a specific position. Subsequently, SMP is allowed to cool keeping it deformed. After cooling, SMP gets the temporary shape. This temporary shape can be recovered by heating it again at the same temperature that was given it while heating it initially. As a result, it will recover its original position. SMP can perform unconstrained recovery and constrained recovery, however; under the load, it only recovers partially. In this work, the recovery under the load of an asymmetrical shape memory composite called as CBCM-SMPC has been investigated. It is found that it has the ability to recover under different loads. Under different loads, it shows powerful complete recovery in reference to initial position. This property can be utilized in many applications.

Keywords: shape memory, polymer composite, thermo-mechanical testing, recovery under load

Procedia PDF Downloads 394
2186 Reducing the Negative Effects of Infrastructure Deficit through Continuity in Governance

Authors: Edoghogho Ogbeifun, Charles Mbohwa, J. H. C. Pretorius

Abstract:

Effective infrastructure development scheme planned and executed has positive influence on the quantity of available stock of infrastructure to meet the immediate and expansion needs of an organization, as well as contribute to the overall economic development of a nation, community or the local entity where the infrastructure is hosted. It is noteworthy, however, that infrastructure development scheme spans a long time frame, usually longer than the political life of the administration that initiates the scheme. In the majority of circumstances, execution may start and achieve different levels of completion; at best, only limited numbers are completed and put into functional use during the life of the administration that initiated the infrastructure scheme. When there is a change in leadership, many of the uncompleted projects are usually abandoned. The new administration repeats the circle of its predecessors and develops another set of infrastructure scheme which will suffer similar fate as the ones developed by their predecessors; thus doting the landscape with many uncompleted projects, which leads to infrastructure deficit. These circle will continue unless each succeeding leader sees governance as single continuum. Therefore, infrastructure projects not completed by one administration should be continued by succeeding administration, in order to increase the stock of relevant infrastructure available for the smooth operations organization and enhance the needed developments, as well as reduce the negative effects of infrastructure deficit. The single case study of qualitative research method was adopted to investigate the actions of the administration of three successive Vice-Chancellors, in a higher education institution in Nigeria, over a longitudinal period of twelve years. This is with a view to exploring the effects of each administration on the development and execution of infrastructure projects, with particular interest on abandoned projects. The findings revealed that although two of Vice-Chancellors were committed to infrastructure upgrade, they executed more new projects than completing abandoned ones, while the current leader has shown more pragmatism in completing abandoned projects alongside constructing new ones; thus demonstrating the importance of the continuity of governance. In this regard, there is a steady increase in the stock of infrastructure to accommodate the expansion of existing academic programmes, host new ones as well as reduce the negative effects of infrastructure deficit caused by abandoned projects.

Keywords: abandoned projects, continuity of governance, infrastructure development scheme, long time frame

Procedia PDF Downloads 149
2185 Green Housing Projects in Egypt: A Futuristic Approach

Authors: Shimaa Mahmoud Ali Ahmed, Boshra Tawfek El-Shreef

Abstract:

Sustainable development has become an important concern worldwide, and climate change has become a global threat. Some of these affect how we approach environmental issues — and how we should approach them. Environmental aspects have an important impact on the built environment, that’s why knowledge about Green Building and Green Construction become a vital dimension of urban sustainable development to face the challenges of climate change. There are several levels of green buildings, from energy-efficient lighting to 100% eco-friendly construction; the concept of green buildings in Egypt is still a rare occurrence, with the concept being relatively new to the market. There are several projects on the ground that currently employing sustainable and green solutions to some extent, some of them achieve a limit of success and others fail to employ the new solutions. The market and the cost as well, are great factors. From the last century, green architecture and environmental sustainability become a famous trend that all the researchers like to follow. Nowadays, the trend towards green has shifted to housing and real estate projects. While the environmental aspects are the key to achieve green buildings, the economic benefits, and the market forces are considered as big challenges. The paper assumes that some appropriate environmental treatments could be added to the applied prototype of the governmental social housing projects in Egypt to achieve better environmental solutions. The aim of the research is to get housing projects in Egypt closer to the track of sustainable and green buildings, through making a local future proposal to be integrated into the current policies. The proposed model is based upon adding some appropriate, cheap environmental modifications to the prototype of the Ministry of Housing, Infrastructure, and New Urban Communities. The research is based on an analytical, comparative analytical, and inductive approach to study and analyze the housing projects in Egypt and the possibilities of integrating green techniques into it.

Keywords: green buildings, urban sustainability, housing projects, sustainable development goals, Egypt 2030

Procedia PDF Downloads 93
2184 Assessing Indicators, Challenges and Benefits of Sustainable Procurement in Construction Projects

Authors: Taha Anjamrooz, Sareh Rajabi, Salwa Bheiry

Abstract:

Procurement is a key process in construction project management. The present construction procurement practices have been extensively analyzed for disregarding sustainability in the project life cycle. Currently, there is a gap of information on status-quo of sustainable procurement in construction field. Thus, the aim of this study is to review sustainable procurement practices in the construction field. Disregard of three sustainability pillars is one of the major drawbacks of present construction procurement practices. Sustainable procurement is a developing idea that can enhance procurement practices and improve the sustainability performance of the construction projects. At present, sustainable procurement is still not entirely used in the construction projects. A comprehensive literature review indicated that the construction industry is still not entirely informed about the benefits and challenges of using sustainable procurement, and about important indicators that play major impacts on those benefits and challenges. This study assesses the major indicator, benefits and challenges encountered in applying sustainable procurement in the construction industry. In addition, this study investigates understanding of construction professionals on the benefits and challenges of utilizing sustainable procurement for construction projects through selected indicators that are categorized according to society and community needs.

Keywords: sustainability, sustainable development, sustainable procurement, procurement, construction industry

Procedia PDF Downloads 149
2183 Technology Roadmapping in Defense Industry

Authors: Sevgi Özlem Bulu, Arif Furkan Mendi, Tolga Erol, İzzet Gökhan Özbilgin

Abstract:

The rapid progress of technology in today's competitive conditions has also accelerated companies' technology development activities. As a result, companies are paying more attention to R&D studies and are beginning to allocate a larger share to R&D projects. A more systematic, comprehensive, target-oriented implementation of R&D studies is crucial for the company to achieve successful results. As a consequence, Technology Roadmap (TRM) is gaining importance as a management tool. It has critical prospects for achieving medium and long term success as it contains decisions about past business, future plans, technological infrastructure. When studies on TRM are examined, projects to be placed on the roadmap are selected by many different methods. Generally preferred methods are based on multi-criteria decision making methods. Management of selected projects becomes an important point after the selection phase of the projects. At this stage, TRM are used. TRM can be created in many different ways so that each institution can prepare its own Technology Roadmap according to their strategic plan. Depending on the intended use, there can be TRM with different layers at different sizes. In the evaluation phase of the R&D projects and in the creation of the TRM, HAVELSAN, Turkey's largest defense company in the software field, carries out this process with great care and diligence. At the beginning, suggested R&D projects are evaluated by the Technology Management Board (TMB) of HAVELSAN in accordance with the company's resources, objectives, and targets. These projects are presented to the TMB periodically for evaluation within the framework of certain criteria by board members. After the necessary steps have been passed, the approved projects are added to the time-based TRM, which is composed of four layers as market, product, project and technology. The use of a four-layered roadmap provides a clearer understanding and visualization of company strategy and objectives. This study demonstrates the benefits of using TRM, four-layered Technology Roadmapping and the possibilities for the institutions in the defense industry.

Keywords: technology roadmap, research and development project, project selection, research development in defense industry

Procedia PDF Downloads 146
2182 Study of Causes and Effects of Road Projects Abandonment in Nigeria

Authors: Monsuru Oyenola Popoola, Oladapo Samson Abiola, Wusamotu Alao Adeniji

Abstract:

The prevalent and incessant abandonment of road construction projects are alarming that it creates several negative effects to social, economic and environmental values of the project. The purpose of this paper is to investigate and determined the various causes and effects of abandoning road construction projects in Nigeria. Likert Scale questionnaire design was used to administered and analysed the data obtained for the stydy. 135 (Nr) questionnaires were completed and retrieved from the respondents, out of 200 (Nr) questionnaires sent out, representing a response rate of 67.5%. The analysis utilized the Relative Importance Index (R.I.I.) method and the results are presented in tabular form. The findings confirms that at least 20 factors were the causes of road projects abandonment in Nigeria with most including Leadership Instability, Improper Project Planning, Inconsistence in government policies and Design, Contractor Incompetence, Economy Instability and Inflation, Delay in remittance of money, Improper financial analysis, Poor risk management, Climatic Conditions, Improper Project Estimates etc. The findings also show that at least eight (8) effect were identified on the system, and these include; Waste of Financial Resources, Loss of economic value, Environmental degradation, Loss of economic value, Reduction in standard of living, Litigation and Arbitration, etc. The reflection is that allocating reasonable finance, developing appropriate and effective implementation plans and monitoring, evaluation and reporting on development project activities by key actors should enhance in resolving the problem of road projects abandonment.

Keywords: road construction, abandonment of road projects, climatic condition, project planning, contractor

Procedia PDF Downloads 265
2181 A Preliminary Study on the Effects of Lung Impact on Ballistic Thoracic Trauma

Authors: Amy Pullen, Samantha Rodrigues, David Kieser, Brian Shaw

Abstract:

The aim of the study was to determine if a projectile interacting with the lungs increases the severity of injury in comparison to a projectile interacting with the ribs or intercostal muscle. This comparative study employed a 10% gelatine based model with either porcine ribs or balloons embedded to represent a lung. Four sample groups containing five samples were evaluated; these were control (plain gel), intercostal impact, rib impact, and lung impact. Two ammunition natures were evaluated at a range of 10m; these were 5.56x45mm and 7.62x51mm. Aspects of projectile behavior were quantified including exiting projectile weight, location of yawing, projectile fragmentation and distribution, location and area of the temporary cavity, permanent cavity formation, and overall energy deposition. Major findings included the cavity showing a higher percentage of the projectile weight exit the block than the intercostal and ribs, but similar to the control for the 5.56mm ammunition. However, for the 7.62mm ammunition, the lung was shown to have a higher percentage of the projectile weight exit the block than the control, intercostal and ribs. The total weight of projectile fragments as a function of penetration depth revealed large fluctuations and significant intra-group variation for both ammunition natures. Despite the lack of a clear trend, both plots show that the lung leads to greater projectile fragments exiting the model. The lung was shown to have a later center of the temporary cavity than the control, intercostal and ribs for both ammunition types. It was also shown to have a similar temporary cavity volume to the control, intercostal and ribs for the 5.56mm ammunition and a similar temporary cavity to the intercostal for the 7.62mm ammunition The lung was shown to leave a similar projectile tract than the control, intercostal and ribs for both ammunition types. It was also shown to have larger shear planes than the control and the intercostal, but similar to the ribs for the 5.56mm ammunition, whereas it was shown to have smaller shear planes than the control but similar shear planes to the intercostal and ribs for the 7.62mm ammunition. The lung was shown to have less energy deposited than the control, intercostal and ribs for both ammunition types. This comparative study provides insights into the influence of the lungs on thoracic gunshot trauma. It indicates that the lungs limits projectile deformation and causes a later onset of yawing and subsequently limits the energy deposited along the wound tract creating a deeper and smaller cavity. This suggests that lung impact creates an altered pattern of local energy deposition within the target which will affect the severity of trauma.

Keywords: ballistics, lung, trauma, wounding

Procedia PDF Downloads 136
2180 Temporary Autonomous Areas in Time and Space: Psytrance Rave Parties as an Expression Area of Altered States of Consciousness in Turkey

Authors: Ugur Cihat Sakarya

Abstract:

This research focuses on psychedelic trance music events in Turkey in the context of altered states of consciousness (ASC). The fieldwork that was conducted from 2018 to 2019 is the main source of the research. Participant observation method was followed in 15 selected events. To direct the musical experiences of participants, performances were also presented as a Dj. Ten of these events are open-air festivals. Five of them are indoor parties. The observations made during fieldwork and suitable answers for inference from the interviews with participants, artists, DJs, and volunteers were selected, compiled, and presented. In the result, findings showed that these activities are perceived as temporary autonomous areas by the participants both in time and space and that these activities are suitable areas for expressing themselves as a group (psyfamily) against mainstream culture. It has been observed that the elements that complement the altered states of consciousness in these events are music, visual arts, drug use, and desire to experience spiritual experiences. It is thought that this first academic study -about this topic in Turkey- will open a door for future researches.

Keywords: consciousness, psychedelic, psytrance, rave, Turkey

Procedia PDF Downloads 111
2179 Application of Value Engineering Approach for Improving the Quality and Productivity of Ready-Mixed Concrete Used in Construction and Hydraulic Projects

Authors: Adel Mohamed El-Baghdady, Walid Sayed Abdulgalil, Ahmad Asran, Ibrahim Nosier

Abstract:

This paper studies the effectiveness of applying value engineering to actual concrete mixtures. The study was conducted in the State of Qatar on a number of strategic construction projects with international engineering specifications for the 2022 World Cup projects. The study examined the concrete mixtures of Doha Metro project and the development of KAHRAMAA’s (Qatar Electricity and Water Company) Abu Funtas Strategic Desalination Plant, in order to generally improve the quality and productivity of ready-mixed concrete used in construction and hydraulic projects. The application of value engineering to such concrete mixtures resulted in the following: i) improving the quality of concrete mixtures and increasing the durability of buildings in which they are used; ii) reducing the waste of excess materials of concrete mixture, optimizing the use of resources, and enhancing sustainability; iii) reducing the use of cement, thus reducing CO₂ emissions which ensures the protection of environment and public health; iv) reducing actual costs of concrete mixtures and, in turn, reducing the costs of construction projects; and v) increasing the market share and competitiveness of concrete producers. This research shows that applying the methodology of value engineering to ready-mixed concrete is an effective way to save around 5% of the total cost of concrete mixtures supplied to construction and hydraulic projects, improve the quality according to the technical requirements and as per the standards and specifications for ready-mixed concrete, improve the environmental impact, and promote sustainability.

Keywords: value management, cost of concrete, performance, optimization, sustainability, environmental impact

Procedia PDF Downloads 320
2178 Techniques of Construction Management in Civil Engineering

Authors: Mamoon M. Atout

Abstract:

The Middle East Gulf region has witnessed rapid growth and development in many areas over the last two decades. The development of the real-estate sector, construction industry and infrastructure projects are a major share of the development that has participated in the civilization of the countries of the Gulf. Construction industry projects were planned and managed by different types of experts, who came from all over the world having different types of experiences in construction management and industry. Some of these projects were completed on time, while many were not, due to many accumulating factors. Many accumulated factors are considered as the principle reason for the problem experienced at the project construction stage, which reflected negatively on the project success. Specific causes of delay have been identified by construction managers to avoid any unexpected delays through proper analysis and considerations to some implications such as risk assessment and analysis for many potential problems to ensure that projects will be delivered on time. Construction management implications were adopted and considered by project managers who have experience and knowledge in applying the techniques of the system of engineering construction management. The aim of this research is to determine the benefits of the implications of construction management by the construction team and level of considerations of the techniques and processes during the project development and construction phases to avoid any delay in the projects. It also aims to determine the factors that participate to project completion delays in case project managers are not well committed to their roles and responsibilities. The results of the analysis will determine the necessity of the applications required by the project team to avoid the causes of delays that help them deliver projects on time, e.g. verifying tender documents, quantities and preparing the construction method of the project.

Keywords: construction management, control process, cost control, planning and scheduling

Procedia PDF Downloads 213
2177 Presenting a Model Based on Artificial Neural Networks to Predict the Execution Time of Design Projects

Authors: Hamed Zolfaghari, Mojtaba Kord

Abstract:

After feasibility study the design phase is started and the rest of other phases are highly dependent on this phase. forecasting the duration of design phase could do a miracle and would save a lot of time. This study provides a fast and accurate Machine learning (ML) and optimization framework, which allows a quick duration estimation of project design phase, hence improving operational efficiency and competitiveness of a design construction company. 3 data sets of three years composed of daily time spent for different design projects are used to train and validate the ML models to perform multiple projects. Our study concluded that Artificial Neural Network (ANN) performed an accuracy of 0.94.

Keywords: time estimation, machine learning, Artificial neural network, project design phase

Procedia PDF Downloads 42
2176 Impact of Safety and Quality Considerations of Housing Clients on the Construction Firms’ Intention to Adopt Quality Function Deployment: A Case of Construction Sector

Authors: Saif Ul Haq

Abstract:

The current study intends to examine the safety and quality considerations of clients of housing projects and their impact on the adoption of Quality Function Deployment (QFD) by the construction firm. Mixed method research technique has been used to collect and analyze the data wherein a survey was conducted to collect the data from 220 clients of housing projects in Saudi Arabia. Then, the telephonic and Skype interviews were conducted to collect data of 15 professionals working in the top ten real estate companies of Saudi Arabia. Data were analyzed by using partial least square (PLS) and thematic analysis techniques. Findings reveal that today’s customer prioritizes the safety and quality requirements of their houses and as a result, construction firms adopt QFD to address the needs of customers. The findings are of great importance for the clients of housing projects as well as for the construction firms as they could apply QFD in housing projects to address the safety and quality concerns of their clients.

Keywords: construction industry, quality considerations, quality function deployment, safety considerations

Procedia PDF Downloads 92
2175 Impact of Project Leader's Style on the Success of the Projects

Authors: Saadia Khalid

Abstract:

This paper discusses the various leadership styles of project manager which lead to the success of a project since it is important for a project manager to understand and adopt the skills required to cope up with the modern challenges of any project. A project manager must be able to handle a project effectively and efficiently and be ready to assess the factors effecting success or failure of the project. A project manager must be capable of handling a project by managing, directing and leading the projects with requisite knowledge and skills. In this paper a project manager’s characteristics linkage to project success have been developed and analyzed for three different projects/industries. A web-based survey has also been carried out which revealed that specific leadership styles/traits can lead to better performance and success of organizations. Some basic factors like project complexity, the age, gender and nationality of the project manager and type of project also play a vital role in success of a project.

Keywords: leadership style, project success, project management, project manager

Procedia PDF Downloads 391
2174 Evaluation of Environmental Management System Implementation of Construction Projects in Turkey

Authors: Aydemir Akyürek, Osman Nuri Ağdağ

Abstract:

Construction industry is in a rapid development for many years around the world and especially in Turkey. In the last three years sector has 10% growth and provides significant support on Turkey’s national economy. Many construction projects are on-going at urban and rural areas of Turkey which have substantial environmental impacts. Environmental impacts during construction phase are quite diversified and widespread. Environmental impacts of construction industry cannot be inspected properly in all cases and negative impacts may occur frequently in many projects in Turkey. In this study, implementation of ISO 14001 Environmental Management System (EMS) in construction plants is evaluated. In the beginning stage quality management systems generally reviewed and ISO 14001 EMS is selected for implementation. Standard requirements are examined first and implementation of every standard requirement is elaborated for the selected construction plant in the following stage. Key issues and common problems, gained benefits by execution of this type of international EMS standard are examined. As can be seen in sample projects, construction projects are being completed very fast and contractors are working in a highly competitive environment with low profit ratios in our country and mostly qualified work force cannot be accessible. Addition to this there are deficits on waste handling and environmental infrastructure. Besides construction companies which have substantial investments on EMSs can be faced with difficulties on competitiveness in domestic market, however professional Turkish contractors which implementing managements systems in larger scale at international projects are gaining successful results. Also the concept of ‘construction project management’ which is being implemented in successful projects worldwide cannot be implemented except larger projects in Turkey. In case of nonexistence of main management system (quality) implementation of EMSs cannot be managed. Despite all constraints, EMSs that will be implemented in this industry with commitment of top managements and demand of customers will be an enabling, facilitating tool to determine environmental aspects and impacts of construction sites, will provide higher compliance levels for environmental legislation, to establish best available methods for operational control on waste management, chemicals management etc. and to plan monitoring and measurement, to prioritize environmental aspects for investment schedules and waste management.

Keywords: environmental management system, construction projects, ISO 14001, quality

Procedia PDF Downloads 328
2173 The Efficacy of Contractual Governance on Task and Relationship Conflict in Construction Projects

Authors: Jingya You, Yongqiang Chen, Yuanyuan Hua, Wenqian Wang

Abstract:

Conflict is commonplace in construction projects, and construction projects always involve designing contracts between the owner and the contractor. However, how the contract affects the level of conflict between the owner and the contractor has not been elaborated. The purpose of this paper is to explain the effects of contractual complexity on the level of conflict, including task conflict and relationship conflict, and then to demonstrate the moderating role played by the interdependence between the owner and the contractor. Using data from owners and general contractors in the Chinese construction industry, this research reveals that contractual control will reduce relationship conflict. Contractual coordination will also reduce relationship conflict by the mediating effect of task conflict. Besides, under high joint interdependence, the positive relationship between task conflict and relationship conflict is strengthened, while high interdependence asymmetry has effects on weakening the relationship between task conflict and relationship conflict. The findings provide guidance for contract designers to draft suitable contracts in order to effectively deal with conflict. Additionally, this research implies that project managers should highlight the importance of contract in conflict management.

Keywords: construction projects, contract governance, interdependence, relationship conflict, task conflict

Procedia PDF Downloads 181
2172 Flexibility Cost and Its Application for Construction Projects

Authors: Rashmi Shahu

Abstract:

Flexibility is becoming a more widely accepted aspect of project management. Although contingency theory in project management states that the unknowns are controllable, complexity theory believes that the best way to handle the unknowns would be to have a flexible approach rather than rigidity. Designing a flexible system is a method of managing uncertainty. The present research work aims to evaluate flexibility in the initial design phase of projects taking examples of construction projects. Flexibility in the initial design phase is modeled in order to know the advantage in future. The comparison between the extra cost of flexibility in the initial design phase and the discount that can be achieved in future due to this premium will help the developers in making strategic decisions. This research uses a methodology for valuing flexibility by developing a mathematical formula for predicting future saving of cost. Two case studies were considered in this research to validate the mathematical formula. This research explains three case studies of an educational institution 28 years old for explaining the concept and giving benefits of flexible design for modification/renovation work of building.

Keywords: flexibility, future saving, flexibility cost, construction projects

Procedia PDF Downloads 327
2171 Environmental Issues in Construction Projects in India

Authors: Gurbir Singh Khaira, Anmoldeep Singh Kang

Abstract:

Exposures to environmental pollution remain a major source of health risk throughout the world, though risks are generally higher in developing countries, where poverty, lack of investment in modern technology and weak environmental legislation combine to cause high pollution levels. This paper will tell us about the environment is threatened severely by so many problems, some of which are caused by the activities of Construction Projects. The research reveals major environmental impacts of building construction projects to include environmental pollution, resource depletion and habitat destruction causing Destruction of ecosystem, Desertification, Soil Erosion and increasing Material Wastage. Construction is considered as one of the main sources of environmental pollution in the world, the level of knowledge and awareness of project participants, especially project managers, with regards to environmental impacts of construction processes needs to be enhanced. It was found that ‘Transportation Resource’, ‘Noise Pollution’, and ‘Dust Generation with Construction Machinery’ are the greatest environmental impacts in INDIA respectively. The results of this study are useful for construction managers and other participants in construction sites to become aware of construction processes impacts on the environment.

Keywords: construction projects, environmental impacts, material waste age, awareness

Procedia PDF Downloads 332
2170 The Analysis of Swales Model (Cars Model) in the UMT Final Year Engineering Students

Authors: Kais Amir Kadhim

Abstract:

Context: The study focuses on the rhetorical structure of chapters in engineering final year projects, specifically the Introduction chapter, written by UMT (University of Marine Technology) engineering students. Existing research has explored the use of genre-based approaches to analyze the writing of final year projects in various disciplines. Research Aim: The aim of this study is to investigate the rhetorical structure of Introduction chapters in engineering final year projects by UMT students. The study aims to identify the frequency of communicative moves and their constituent steps within the Introduction chapters, as well as understand how students justify their research projects. Methodology: The research design will utilize a mixed method approach, combining both quantitative and qualitative methods. Forty Introduction chapters from two different fields in UMT engineering undergraduate programs will be selected for analysis. Findings: The study intends to identify the types of moves present in the Introduction chapters of engineering final year projects by UMT students. Additionally, it aims to determine if these moves and steps are obligatory, conventional, or optional. Theoretical Importance: The study draws upon Bunton's modified CARS (Creating a Research Space) model, which is a conceptual framework used for analyzing the introduction sections of theses. By applying this model, the study contributes to the understanding of the rhetorical structure of Introduction chapters in engineering final year projects. Data Collection: The study will collect data from forty Introduction chapters of engineering final year projects written by UMT engineering students. These chapters will be selected from two different fields within UMT's engineering undergraduate programs. Analysis Procedures: The analysis will involve identifying and categorizing the communicative moves and their constituent steps within the Introduction chapters. The study will utilize both quantitative and qualitative analysis methods to examine the frequency and nature of these moves. Question Addressed: The study aims to address the question of how UMT engineering students structure and justify their research projects within the Introduction chapters of their final year projects. Conclusion: The study aims to contribute to the knowledge of rhetorical structure in engineering final year projects by investigating the Introduction chapters written by UMT engineering students. By using a mixed method research design and applying the modified CARS model, the study intends to identify the types of moves and steps employed by students and explore their justifications for their research projects. The findings have the potential to enhance the understanding of effective academic writing in engineering disciplines.

Keywords: cohesive markers, learning, meaning, students

Procedia PDF Downloads 45
2169 Cost Overrun in Construction Projects

Authors: Hailu Kebede Bekele

Abstract:

Construction delays are suitable where project events occur at a certain time expected due to causes related to the client, consultant, and contractor. Delay is the major cause of the cost overrun that leads to the poor efficiency of the project. The cost difference between completion and the originally estimated is known as cost overrun. The common ways of cost overruns are not simple issues that can be neglected, but more attention should be given to prevent the organization from being devastated to be failed, and financial expenses to be extended. The reasons that may raised in different studies show that the problem may arise in construction projects due to errors in budgeting, lack of favorable weather conditions, inefficient machinery, and the availability of extravagance. The study is focused on the pace of mega projects that can have a significant change in the cost overrun calculation.15 mega projects are identified to study the problem of the cost overrun in the site. The contractor, consultant, and client are the principal stakeholders in the mega projects. 20 people from each sector were selected to participate in the investigation of the current mega construction project. The main objective of the study on the construction cost overrun is to prioritize the major causes of the cost overrun problem. The methodology that was employed in the construction cost overrun is the qualitative methodology that mostly rates the causes of construction project cost overrun. Interviews, open-ended and closed-ended questions group discussions, and rating qualitative methods are the best methodologies to study construction projects overrun. The result shows that design mistakes, lack of labor, payment delay, old equipment and scheduling, weather conditions, lack of skilled labor, payment delays, transportation, inflation, and order variations, market price fluctuation, and people's thoughts and philosophies, the prior cause of the cost overrun that fail the project performance. The institute shall follow the scheduled activities to bring a positive forward in the project life.

Keywords: cost overrun, delay, mega projects, design

Procedia PDF Downloads 26
2168 Conflict Causes within Construction Projects; Conflict Interaction across Project Phases

Authors: Abdullah Mohammed Alshehri

Abstract:

The projects in the construction industry have significantly increased, given its contribution to the overall Gross Domestic Product (GDP) of the countries. Reflecting upon the complex nature and involvement of various agents, the study aims to analyze the conflicts cause within construction projects. Therefore, the study strived to come out with understanding the levels of conflict interaction across project phases. However, this conducted by investigating the association between antecedents and apparent conflicts inherent in. The study used a qualitative approach for collecting the data through a quantitative, semi-structured method. Formation of a questionnaire survey has been conducted for over 30 respondents. However, the survey came out with the identification of 25 conflict cause categories, which can take place in different construction project phases, including pre-design phase, pre-construction phase, construction phase, commissioning, and completion phase. For example, conflicts associated with inconsistencies or discrepancies within or between project documents, which took place at tendering time in the pre-construction phase were relatable with the selection of material specifications that should be supplied or used in the construction projects at the construction phase. Its analysis can provide comprehensive understanding, trace the root of the problem, which offers a roadmap to deepen the understanding of the conflict conditions and ‘course of action’ necessary for project management strategy actions toward avoiding or minimizing conflict causes at project life.

Keywords: construction, conflict causes, levels, interaction, phases

Procedia PDF Downloads 141
2167 3D Printing Technology in Housing Projects Construction

Authors: Mohammed F. Haddad, Mohammad A. Albenayyan

Abstract:

Realistically, 3-D printing as a technology has not yet reached the required maturity level to handle construction housing projects for citizens on a country scale. However, potentially, it has all of the required elements for addressing this issue. There are two main high-level elements of this technology that need to be capitalized on in order for the technology to reach its full potential, technical and logistical. This paper aims to cover how 3-D printing can be a viable technical solution for housing projects and describe the impact of 3-D printing technical features on the logistical aspects of completing a housing project. Additionally, a perspective about 3-D printing in Saudi Arabia will be presented in order to give the reader an idea of where the kingdom stands in the deployment of this technology. Finally, a glimpse will be given regarding the potential utilization of this technology for space applications.

Keywords: large-scale 3-D printing, additive manufacturing, D- shape, contour crafting

Procedia PDF Downloads 94
2166 Feasibility Study of a Solar Farm Project with an Executive Approach

Authors: Amir Reza Talaghat

Abstract:

Since 2015, a new approach and policy regarding energy resources protection and using renewable energies has been started in Iran which was developing new projects. Investigating about the feasibility study of these new projects helped to figure out five steps to prepare an executive feasibility study of the concerned projects, which are proper site selections, authorizations, design and simulation, economic study and programming, respectively. The results were interesting and essential for decision makers and investors to start implementing of these projects in reliable condition. The research is obtained through collection and study of the project's documents as well as recalculation to review conformity of the results with GIS data and the technical information of the bidders. In this paper, it is attempted to describe the result of the performed research by describing the five steps as an executive methodology, for preparing a feasible study of installing a 10 MW – solar farm project. The corresponding results of the research also help decision makers to start similar projects is explained in this paper as follows: selecting the best location for the concerned PV plant, reliable and safe conditions for investment and the required authorizations to start implementing the solar farm project in the concerned region, selecting suitable component to achieve the best possible performance for the plant, economic profit of the investment, proper programming to implement the project on time.

Keywords: solar farm, solar energy, execution of PV power plant PV power plant

Procedia PDF Downloads 135
2165 Application of Agile Project Management to Construction Projects: Case Study

Authors: Ran Etgar, Sarit Freund

Abstract:

Agile project management (APM) has been developed originally for software development project. Construction projects seemed to be more apt to traditional water-fall approach than to APM. However, Construction project suffers from similar problems that necessitated the invention of APM, mainly the need to break down the project structure to small increments, thus minimizing the needed managerial planning and design. Since the classical structure of APM is not applicable the way it is to construction project, a modified version of APM was devised. This method, nicknamed 'The anchor method', exploits the fundamentals of APM (i.e., iterations, or sprints of short time frames or timeboxes, cross-functional teams, risk reduction and adaptation to changes) and adjust them to the construction world. The projects had to be structured appropriately to proactively and quickly adapt to change. The method aims to encompass human behavior and lean towards adaptivity rather than predictability. To enable smooth application of the method, a special project management software was developed, so as to provide solid administrational help and accurate data. The method is tested on a bunch of construction projects and some key performance indicators (KPIs) are collected. According to preliminary results the method is indeed very advantageous and with proper assimilation can radically change the construction project management paradigm.

Keywords: agile project management, construction, information systems, project management

Procedia PDF Downloads 97
2164 Appraisal of Transaction Cost in South African Construction Projects

Authors: Kenneth O. Otasowie, Matthew Ikuabe, Clinton Aigbavboa, Ayodeji Oke

Abstract:

Construction project cost are not only made up of production costs. This cost comprises of many other elements such as the preparation of a bidding document, cost estimations, drafting contractual agreements and monitoring that contractual obligations are met. Several studies have stressed the need for transaction costs (TC) to be defined in a way that covers all phases of a project and not only the pre-contract phase. Hence, this study aims to appraise transaction cost in South African (SA) construction projects by assessing what constitutes transaction cost, influencing factors and possible optimisation measures. A survey design was adopted. A total number of eighty (80) questionnaires were administered to quantity surveyors, procurement managers and project managers in Guateng Province, SA and seventy-two (72) were returned and found suitable for analysis. Collected data was analysed using percentage, mean item score, standard deviation, one-sample t-test. The findings show that external technical interaction, uncertainty, human factors are the most significant constituents of TC in SA, while technical competency, experience in similar project type and project characteristics are the leading influencing factors. Furthermore, understanding project characteristics, clear communication and technically competent project teams are most of the significant measures for optimising TC in SA construction projects. Therefore, this study recommends that a competent project team and a clear communication are fundamental to proper management of TC in SA construction projects.

Keywords: construction projects, project cost, South Africa, transaction cost

Procedia PDF Downloads 72
2163 Study on the Key Stakeholders' Perception and Establishment of Sustainability Goals in the Green Building Projects: The Case of Malaysia

Authors: Nor Kalsum M. Isa, Mohd Yazid M. Yunos, Anuar Alias, Mazdi Marzuki, Kamarul Ismail, Mohd H. Ibrahim

Abstract:

Green building is an emerging concept with the ultimate target to achieve sustainable development by integrating sustainability goals and principles into project development. Basically, a green building is a building that is designed, constructed and operated to boost environmental, economic, health and productivity performance over conventional buildings. The buildings have been proven to be successful in contributing towards sustainability and project success. The purpose of this study was to determine the benefits of sustainability application in building projects, looking towards project success from the perspective of Malaysian key project stakeholders. The study also aimed to explore the establishment of sustainability goals in the green building projects in Malaysia. The Triple Bottom Line (TBL) Concept of Sustainability was used as the foundation theoretical framework. Surveys, interviews and multiple case study methods were employed. A sample of 188 Malaysian building project stakeholders was selected for questionnaire surveys, and 15 stakeholders from three award-winning green building projects in Malaysia were involved in the interviews. The study found that the majority of the respondents were less aware that the sustainability integration in the building project can significantly affect cost reduction, schedule effectiveness and stakeholders’ satisfaction with the performance of buildings as at the same level as the quality performance. Of the four sustainability goals, the environmental aspect was given more priority than others in the development of the green building projects.

Keywords: green building, sustainability, project stakeholders, Malaysia

Procedia PDF Downloads 525
2162 Lessons-Learned in a Post-Alliance Framework

Authors: Olubukola Olumuyiwa Tokede, Dominic D. Ahiaga-Dagbui, John Morrison

Abstract:

The project environment in construction has been widely criticised for its inability to learn from experience effectively. As each project is bespoke, learning is ephemeral, as it is often confined within its bounds and seldom assimilated with others that are being delivered in the project environment. To engender learning across construction projects, collaborative contractual arrangements, such as alliancing and partnering, have been embraced to aid the transferability of lessons across projects. These cooperative arrangements, however, tend to be costly, and hence construction organisations could revert to less expensive traditional procurement approaches after successful collaborative project delivery. This research, therefore, seeks to assess the lessons-learned in a post-alliance contractual framework. Using a case-study approach, we examine the experiences of a public sector authority who engaged a project facilitator to foster learning during the delivery of a significant piece of critical infrastructure. It was found that the facilitator enabled optimal learning outcomes in post-alliance contractual frameworks by attenuating the otherwise adversarial relationship between clients and contractors. Further research will seek to assess the effectiveness of different knowledge-brokering agencies in construction projects.

Keywords: facilitation, knowledge-brokering, learning, projects

Procedia PDF Downloads 105