Development of a Support Tool for Cost and Schedule Integration Managment at Program Level
Commenced in January 2007
Frequency: Monthly
Edition: International
Paper Count: 32799
Development of a Support Tool for Cost and Schedule Integration Managment at Program Level

Authors: H. J. Yang, R. Z. Jin, I. J. Park, C. T. Hyun

Abstract:

There has been gradual progress of late in construction projects, particularly in big-scale megaprojects. Due to the long-term construction period, however, with large-scale budget investment, lack of construction management technologies, and increase in the incomplete elements of project schedule management, a plan to conduct efficient operations and to ensure business safety is required. In particular, as the project management information system (PMIS) is meant for managing a single project centering on the construction phase, there is a limitation in the management of program-scale businesses like megaprojects. Thus, a program management information system (PgMIS) that includes program-level management technologies is needed to manage multiple projects. In this study, a support tool was developed for managing the cost and schedule information occurring in the construction phase, at the program level. In addition, a case study on the developed support tool was conducted to verify the usability of the system. With the use of the developed support tool program, construction managers can monitor the progress of the entire project and of the individual subprojects in real time.

Keywords: Cost∙Schedule integration management, Supporting Tool, UI, WBS, CBS, introduce PgMIS (Program Management Information System), PMIS (Project Management Information System)

Digital Object Identifier (DOI): doi.org/10.5281/zenodo.1060709

Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 1415

References:


[1] Hyun, C., Hong, T., Son, M., Lee, H., and Ha, S., "Development of the Cost Breakdown Structure Organization Tool for the Planning Phase of Mixed Used Development", Architectural Institute of Korea, vol. 25(8), pp.185-194, 2009
[2] Kim, k. J.,Republic of Korea-class company,wonaenwonbukseu,2008
[3] Yeom, J. W., Kim, D. H., Ahn, B. J., Kim, J. H., and Kim, J. J., "Development of Program Management Information System Prototype to support Urban Regeneration Based on System Requirement Analysis', Journal of Korean Institute of Construction, vol. 9(4),pp.85-92, 2009
[4] PMBOK , 3rd edition, 2004
[5] Dr.PaulSanghera, Program Management Professional Exam Study Guide, SYBEX, 2007
[6] Lee, H. S., and Kim, D. j.,"Integrated Cost and Schedule Management for Construction Projects Based on Earned Value Concept", Architectural Institute of Korea, vol. 42(6), pp.17-19, 1998
[7] Jun, J. G., Im, J. A., Park, Y. D., andKwak, H. S., "Construction Business Process of Management Techniques for Integrated Management of cost and schedule", Civil Institute of Korea, vol 531(24), pp.3648-3650, 2006
[8] Blanchard, B.S., and Fabrycky, W.J., Systems Engineering and Analysis. 3rd ed., Prentice-Hall, Inc., 1998
[9] Lee, D. H., Kim, K. T., Kim, H. B., Jun, J. T., and Han, C. H., "A Study on the Life Cycle Cost Analysis in Light Rail Transit Bridges: Focused on Superstructure", Journal of Korean Institute of Construction, vol. 2, pp.1-11, 2007
[10] Le, Y., Ren, J. S., Ning, Y., He, Q. H., and Li, Y. K., "Life Cycle Cost Integrative Management in Construction Engineering", ICISE-2009, pp.4367-4370, 2009
[11] Jung, Y. S., and Woo, S. K., "Flexible Work Breakdown Structure for Integrated Cost and Schedule Control", Journal of Construction Engineering and Management, ASCE, vol.130(5), pp.616-625, 2004
[12] Cho, K. M., Hong, T. H., and Hyun, C.T., "Integrated Schedule and Cost Model for Repetitive Construction Process", Journal of Management in Engineering, ASCE, vol. 26(2), pp.78-88, 2010
[13] P. H. Chen., "Integration of cost and schedule using extensive matrix method and spreadsheets", Automation in Construction, vol.18(1), pp.32-41, 2008
[14] Project Management Institute, Practice Standard for Work BreakdownStructures. 2001
[15] CCPS, Interface Management: Effective Communication to Improve Process Safety, CCPS Safety Alert, March, 2004
[16] The Human Interface: New Directions for Designing Interactive System, jef Ruskin, 2000
[17] Hyun, C. T., Hong, T. H., Koo, k. j., Yeon, H. J., Moon, H. S., and Cho, K. M., "Development of the Space Cost Breakdown Structure(CBS) for Multi-Family Housing Projects", KICEM, vol. 23(2), pp.75-82, 2007
[18] Choi, H. R., UI considering the development of Web-based multimedia experiences and research on learning materials,Master's thesis, Kyung Hee University, 2003
[19] Kim, C. H., Kwak, J. M., and Kang, L. S., "Business breakdown structure for construction management and web-based application system", ITcon vol. 10, pp.169-191, 2005
[20] Hyun, C. T., Jin, R. Z.,Son, M. J., and Kim, J. H., "User Interfaces of Intelligent Program Management Information Systemfor Urban Renaissance Projects", ISEC-6, pp.157-162, 2011
[21] Dr.Paul Sanghera, Program Management Professional Exam Study Guide, SYBEX, 2007