	  title     = {Mathematical Model and Solution Algorithm for Containership Operation/Maintenance Scheduling},
	  author    = {Hun Go and  Ji-Su Kim and  Dong-Ho Lee},
	  country	= {},
	  institution	= {},
	  abstract     = {This study considers the problem of determining
operation and maintenance schedules for a containership equipped
with components during its sailing according to a pre-determined
navigation schedule. The operation schedule, which specifies work
time of each component, determines the due-date of each maintenance
activity, and the maintenance schedule specifies the actual start
time of each maintenance activity. The main constraints are component
requirements, workforce availability, working time limitation,
and inter-maintenance time. To represent the problem mathematically,
a mixed integer programming model is developed. Then,
due to the problem complexity, we suggest a heuristic for the objective
of minimizing the sum of earliness and tardiness between the
due-date and the starting time of each maintenance activity. Computational
experiments were done on various test instances and the
results are reported.},
	    journal   = {International Journal of Industrial and Manufacturing Engineering},
	  volume    = {6},
	  number    = {2},
	  year      = {2012},
	  pages     = {394 - 401},
	  ee        = {https://publications.waset.org/pdf/4573},
	  url   	= {https://publications.waset.org/vol/62},
	  bibsource = {https://publications.waset.org/},
	  issn  	= {eISSN: 1307-6892},
	  publisher = {World Academy of Science, Engineering and Technology},
	  index 	= {Open Science Index 62, 2012},
	}