Babak H. Tabrizi and Seyed Farid Ghaderi
An Integrated MixedInteger Programming Model to Address Concurrent Project Scheduling and Material Ordering
1960 - 1963
2015
9
11
International Journal of Industrial and Manufacturing Engineering
https://publications.waset.org/pdf/10002980
https://publications.waset.org/vol/107
World Academy of Science, Engineering and Technology
Concurrent planning of project scheduling and
material ordering can provide more flexibility to the project
scheduling problem, as the project execution costs can be enhanced.
Hence, the issue has been taken into account in this paper. To do so, a
mixedinteger mathematical model is developed which considers the
aforementioned flexibility, in addition to the materials quantity
discount and space availability restrictions. Moreover, the activities
duration has been treated as decision variables. Finally, the efficiency
of the proposed model is tested by different instances. Additionally,
the influence of the aforementioned parameters is investigated on the
model performance.