	%T Renovation Planning Model for a Shopping Mall
	%U https://publications.waset.org/pdf/10001705
	%V 103
	%X In this study, the pedestrian simulation VISWALK
integration and application platform ant algorithms written program
made to construct a renovation engineering schedule planning mode.
The use of simulation analysis platform construction site when the user
running the simulation, after calculating the user walks in the case of
construction delays, the ant algorithm to find out the minimum delay
time schedule plan, and add volume and unit area deactivated loss of
business computing, and finally to the owners and users of two
different positions cut considerations pick out the best schedule
planning. To assess and validate its effectiveness, this study
constructed the model imported floor of a shopping mall floor
renovation engineering cases. Verify that the case can be found from
the mode of the proposed project schedule planning program can
effectively reduce the delay time and the user's walking mall loss of
business, the impact of the operation on the renovation engineering
facilities in the building to a minimum.