Identification of the Causes of Construction Delay in Malaysia
Commenced in January 2007
Frequency: Monthly
Edition: International
Paper Count: 32797
Identification of the Causes of Construction Delay in Malaysia

Authors: N. Hamzah, M.A. Khoiry, I. Arshad, W.H.W. Badaruzzaman, N. M. Tawil

Abstract:

Construction delay is unavoidable in developing countries including Malaysia. It is defined as time overrun or extension of time for completion of a project. The purpose of the study is to determine the causes of delay in Malaysian construction industries based on previous worldwide research. The field survey conducted includes the experienced developers, consultants and contractors in Malaysia. 34 causes of the construction delay have been determined and 24 have been selected using the Rasch model analysis. The analysis result will be used as the baseline for the next research to find the causes of delay in the Malaysian construction industry taking place in Malaysian higher learning institutions.

Keywords: Causes of construction delay, construction projects, Malaysian construction industry, Rasch model analysis.

Digital Object Identifier (DOI): doi.org/10.5281/zenodo.1070693

Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 7502

References:


[1] Leong, M. (2010) The Construction Markert in Malaysia. Frost & Sullivan.
[2] KPKT, Kementerian Perumahan dan Kerajaan Tempatan. 2010: Putrajaya.
[3] Murali Sambasivan , Y.W.S., Causes and effects of delays in Malaysian construction industry, in International Journal of Project Management. 2007. p. 517-526.
[4] Tumi, S.A.H., H. Omran, and A.H.K. Pakir, Cause Of Delay In Construction Industry In Libya, in The International Conference on Administration and Business. 2009: University of Bucharest, Romania.
[5] Wa-el Alaghbari, M.R.A.K., Azizah Salim and Ernawati, The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 2007. 14( 2): p. 192-207.
[6] Sadi A. Assaf, S.A.-H., Causes of delay in large construction projects. International Journal of Project Management, 2006. 24 p. 349-357.
[7] Acharya, N.K., et al., Analysis of Construction Delay Factor: A Korean Perspective, in Proceedings of the 7th Asia Pacific Industrial Engineering and Management Systems Conference 2006. 2006: Bangkok, Thailand. p. 883-895.
[8] Sweis, G., et al., Delays in construction projects: The case of Jordan. International Journal of Project Management 2007. 26 p. 665-674.
[9] Ahmed, S.M., et al. Delays in Construction: A Brief Study of the Florida Construction Industry. in ASC Proceedings of the 39th Annual Conference. 2003. Clemson University - Clemson, South Carolina.
[10] Le-Hoai, L., Y.D. Lee, and J.Y. Lee, Delay and Cost Overruns in Vietnam Large Construction Projects: A Comparison with Other Selected Countries. KSCE Journal of Civil Engineering 2008. 12(6): p. 367-377.
[11] Abdalla M. Odeha, H.T.B., Causes of construction delay: traditional contracts. International Journal of Project Management, 2002. 20: p. 67- 73.
[12] Mohd Razaki Abdullah1, I.A.R., Ade Asmi Abdul Azis, Causes of Delay in MARA Management Procurement Construction Projects. 2010.
[13] Arshi Shakeel Faridi and S.M. El-Sayegh, Significant factors causing delay in the UAE construction industry. Construction Management and Economics 2006. 24: p. 1167-1176.
[14] Al-Tabtabai, H.M., Cause of delay in construction project in Kuwait. Engineering Jurnal of the University of Qatar, 2002. 15: p. 19-37.
[15] Drewin, F.J., Construction productivity. 1982, New York: Elsevier. 150.
[16] Osman, S.A., et al., Assessment On Students Performance Using Rasch Model In Reinforced Concrete Design Course Examination, in Recent Researches in Education 2011, WSEAS: Penang, Malaysia. p. Penang, Malaysia.
[17] Ghulman, H.A., AND Mohd Saidfudin Mas'odi Modern measurement paradigm in Engineering Education: Easier to read and better analysis using Rasch-based approach, in Engineering Education (ICEED), 2009 International Conference 2010, IEEE Xplore Digital Libary: Kuala Lumpur, Malaysia
[18] Hamzah, N., et al., Poor Student Performance in Project Management Course: Was the Exam Wrongly Set? , in World Scientific and Engineering Academy and Society. 2011: Penang, Malaysia. p. 154-160.
[19] Ramin Sadri, P.T., Pejman Azarsa and Hedayat Ghavam, Improving Productivity through Mistake-proofing of Construction Processes, in 2011 International Conference on Intelligent Building and Management. 2011: Singapore. p. 280/284.