Attentiveness of Building Commissioning in the Malaysian Construction Industry
Commenced in January 2007
Frequency: Monthly
Edition: International
Paper Count: 32797
Attentiveness of Building Commissioning in the Malaysian Construction Industry

Authors: Kho Mei Ye, Hamzah Abdul Rahman

Abstract:

This paper provides some thoughts about the lack of attentiveness of building commissioning in the construction industry and the lack of handling in project commissioning as an integral part of the project life-cycle. Many have perceived commissioning as the problem solving process of a project, rather than the start up of the equipment, or the handing over of the project to the client. Therefore, there is a lack of proper attention in the planning of commissioning as a vital part of the project life-cycle. This review paper aims to highlight the benefits of building commissioning and to propose the lacking of knowledge gap on building commissioning. Finally, this paper hopes to propose the shift of focus on this matter in future research.

Keywords: building, commissioning, construction, delay

Digital Object Identifier (DOI): doi.org/10.5281/zenodo.1061938

Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 2098

References:


[1] A. M. Al-Hammad,. (2000). "Common Interface Problems among Various Construction Parties," J. Perform. Constr. Facil., 2000, 14(2), pp. 71-74.
[2] A.M. Al-Hammad, and S.A. Assaf, "Design-construction interface problems in Saudi Arabia. Build," Res. Inf., 1992, 20(1), 60-63.
[3] J.E. Altwies, and I.B.D. McIntosh, "Quantifying the cost benefits of commissioning," National Conference on Building Commissioning, May 9-11, 2001.
[4] F.A. Al-Yousif, "Assessment of constructability practices among general contractors in the eastern province of saudi arabia," MS thesis, King Fahd Univ. of Petroleum and Minerals, Dhahran, Saudi Arabia, 2001.
[5] F.M. Arain, (2002). "Design-construction interface dissonances," MS thesis, King Fahd Univ. of Petroleum and Minerals, Dhahran, Saudi Arabia, 2002.
[6] F.M. Arain, and S.P. Low, "Lesson learned from past projects for effective management of variation orders for Institutional Building Projects," Proceedings of the MICRA 4th Annual Conference, Kuala Lumpur, Malaysia, 2005a, pp. 10-1 to 10-18, ISBN: 9831002539.
[7] F.M. Arain, S.P. Low, and S.A. Assaf, "Contractors- views of the potential causes of inconsistencies between design and construction in saudi arabia," Journal of Performance of Constructed Facilities, 2006, 20(1), pp. 74-83.
[8] ASHRAE Handbook CD, ASHRAE; 2000-2003.
[9] S.A. Assaf and A.M. Al-Hammad, "The effect of economic changes on construction cost", American Association of Cost Engineers Transactions, Morgantown, W. Va., 63-67, 1988.
[10] E. Cagno, F. Caron, and M. Mancini, "Risk analysis in plant commissioning: the multilevel hazop," Reliability Engineering and System Safety, 2002, 77, pp. 309-323.
[11] P. Danese, P. Romano, A. Vinelli, "Managing business processes across supply networks: the role of coordination mechanisms," J Purchasing Supply Manage; 2004, 10(4-5), pp. 165-177.
[12] N. Djuric, and V. Novakovic, "Review of possibilities and necessities for building lifetime commissioning," Renewable and Sustainable Energy Reviews, 2009, 13, pp. 486-492.
[13] D. Dvir, "Transferring projects to their final users: the effect of planning and preparations for commissioning on project success," International Journal of Project Management, 2005, 23(4), pp. 257-265.
[14] P. Elkington, and C. Smallman, "Managing project risks: a case study from the utilities sector," International Journal of Project Management, 2002, 20(1), pp. 49-57.
[15] H. Friedman, A. Potter, and T. Haasl, "Persistence of benefits from new building commissioning," National Conference on Building Commissioning, May 20-22, 2003.
[16] L.E. Gadde, O. Jellbo, "System sourcing - opportunities and problems," Eur J Purchasing Supply Manage, 2002, 8, pp. 43-51.
[17] J.R. Galbraith, "Designing organizations: an executive guide to strategy," Structure and Process. San Francisco: John Wiley & Sons, 2002.
[18] T. Haasl, and R. Friedmann, "California commissioning market characterization study," Proceedings of the 9th National Conference on Building Commissioning, Cherry Hill, New Jersey, May 9-11, 2001.
[19] P. Haves, D. Claridge, M. Lui, "Report assessing the limitations of energy plus and seap with options for overcoming those limitations," California Energy Commission Public Interest energy Research Program, HPCBS#E5P2.3T1, 2001.
[20] M. Hobday, "Product complexity, innovation and industrial organization," Res Policy, 1998, 26(6), pp. 689-710.
[21] W. Hu, "Information lifecycle modeling framework for construction project lifecycle management," 2008 International Seminar on Future Information Technology and Management Engineering, Leicestershire: United Kingdom, 20 November 2008.
[22] International Council on Systems Engineering: Systems engineering handbook INCOSE-TP-2003-016-02, Version 2a; 2004.
[23] J. Kirsila, M. Hellstrom, and K. Wikstrom, "Integration as a project management concept: a study of the commissioning process in industrial deliveries," International Journal of Project Management, 2007, 25, pp. 714-721.
[24] F. Merchan, "Manual para la Direccion integrada de Proyectos y Obras," CIE Dossat, Madrid, p. 432, 2000.
[25] Oregon Office of Energy, "new construction commissioning handbook for facility managers," Portland Energy Conservation, Inc. (PECI). 2000.
[26] J.K. Pinto, D.P. Slevin, "Critical factors in successful project implementation," IEEE Trans Eng Manage, 1987, EM34, pp. 22-27.
[27] A. Tishler, D. Dvir, A. Shenhar, S. Lipovetsky, "Identifying critical success factors in defense development projects: a multivariate analysis," Technol Forecast Social Change, 1996, 51(2), pp. 151-172.
[28] M.T. Turkaslan-Bulbul, and O. Akin, "Computational support for building evaluation: embedded commissioning model," Automation in Construction, 2006, 15, pp. 438 - 447.
[29] T.E. Uher, and A.R. Toakley, "Risk management in the conceptual phase of the project development cycle," International Journal of Project Management; 1999, 17(3), pp. 161-170.
[30] F.T. Ventre, "Myth and paradox in the building enterprise The Design Professions and the Built Environment," P.L. Knox, ed., Nichols Publishing, New York, pp. 147-174, 1988.
[31] J.E. Woods, "Continuous Accountability: a Means to Assure Acceptable Indoor Environment Quality," Proc. Fifth Int. Conf. on Indoor Air Quality and Climate, D. Walkinshaw et al., eds., 1990, 5, pp. 85-94.
[32] J.E. Woods, and S, Arora, "Continuous accountability for acceptable building performance," Automation in Construction, 1992, 1, pp. 239- 249.
[33] J.E. Woods, G.M. Drewry, and P.R. Morey, "Office worker perceptions of indoor air quality effects on discomfort and performance," Proc. Fourth Int. Conf. Indoor Air Quality and Climate, B. Seifert et al., eds., Institute for Water, Soil and Air Hygiene, West Berlin, 8, 1987.
[34] T. Lyons, and M, Skitmore, "Project risk management in the Queensland engineering construction industry: a survey", International Journal of Project Management, 2004, 22(1), pp. 51-61.