	%T Project Complexity Indices based on Topology Features
	%U https://publications.waset.org/pdf/3480
	%V 45
	%X The heuristic decision rules used for project
scheduling will vary depending upon the project-s size, complexity,
duration, personnel, and owner requirements. The concept of project
complexity has received little detailed attention. The need to
differentiate between easy and hard problem instances and the
interest in isolating the fundamental factors that determine the
computing effort required by these procedures inspired a number of
researchers to develop various complexity measures.
In this study, the most common measures of project complexity are
presented. A new measure of project complexity is developed. The
main privilege of the proposed measure is that, it considers size,
shape and logic characteristics, time characteristics, resource
demands and availability characteristics as well as number of critical
activities and critical paths. The degree of sensitivity of the proposed
measure for complexity of project networks has been tested and
evaluated against the other measures of complexity of the considered
fifty project networks under consideration in the current study. The
developed measure showed more sensitivity to the changes in the
network data and gives accurate quantified results when comparing
the complexities of networks.