	%T Two Area Power Systems Economic Dispatch Problem Solving Considering Transmission Capacity Constraints
	%U https://publications.waset.org/pdf/14278
	%V 9
	%X This paper describes an efficient and practical method
for economic dispatch problem in one and two area electrical power
systems with considering the constraint of the tie transmission line
capacity constraint. Direct search method (DSM) is used with some
equality and inequality constraints of the production units with any
kind of fuel cost function. By this method, it is possible to use several
inequality constraints without having difficulty for complex cost
functions or in the case of unavailability of the cost function
derivative. To minimize the number of total iterations in searching,
process multi-level convergence is incorporated in the DSM.
Enhanced direct search method (EDSM) for two area power system
will be investigated. The initial calculation step size that causes less
iterations and then less calculation time is presented. Effect of the
transmission tie line capacity, between areas, on economic dispatch
problem and on total generation cost will be studied; line
compensation and active power with reactive power dispatch are
proposed to overcome the high generation costs for this multi-area
system.