Application of Artificial Neural Network to Forecast Actual Cost of a Project to Improve Earned Value Management System
Commenced in January 2007
Frequency: Monthly
Edition: International
Paper Count: 32805
Application of Artificial Neural Network to Forecast Actual Cost of a Project to Improve Earned Value Management System

Authors: Seyed Hossein Iranmanesh, Mansoureh Zarezadeh

Abstract:

This paper presents an application of Artificial Neural Network (ANN) to forecast actual cost of a project based on the earned value management system (EVMS). For this purpose, some projects randomly selected based on the standard data set , and it is produced necessary progress data such as actual cost ,actual percent complete , baseline cost and percent complete for five periods of project. Then an ANN with five inputs and five outputs and one hidden layer is trained to produce forecasted actual costs. The comparison between real and forecasted data show better performance based on the Mean Absolute Percentage Error (MAPE) criterion. This approach could be applicable to better forecasting the project cost and result in decreasing the risk of project cost overrun, and therefore it is beneficial for planning preventive actions.

Keywords: Earned Value Management System (EVMS), Artificial Neural Network (ANN), Estimate At Completion, Forecasting Methods, Project Performance Measurement.

Digital Object Identifier (DOI): doi.org/10.5281/zenodo.1080756

Procedia APA BibTeX Chicago EndNote Harvard JSON MLA RIS XML ISO 690 PDF Downloads 2700

References:


[1] C. Bower, B.Arch."New Directions in Project Performance and Progress Evaluation" Property and Project Management, July 2007.
[2] C. F. Gray and E. W. Larson, Project Management: The Managerial Process. 2nd ed., NJ: McGraw-Hill, 2003, pp 419-448.
[3] David S. Christensen, Richard C. Antolini, John W. McKinney," a review of estimate at completion" Journal of Cost Analysis and Management, Spring 1995, pp.41-62.
[4] Morrison, David C. "Deep-Sixing the A-12." Government Executive, March 1991, pp. 30-35.
[5] Parker, Charles W. C/SCSC and C/SSR Cost Performance Analysis Programs. DCAS Residency Harris, DCASMS, Orlando, Florida, 20 October 1980.
[6] Haydon, Joseph J. and Richard O Reither. Methods of Estimating Contract Cost at Completion. ManTech International Corporation: Virginia, 31 January 1982.
[7] Sincavage, John T. Time Series Analysis for the Army Internal Systems Management (TSARISM). Cost Analysis Division. Army Aviation Systems Command, St. Louis, Missouri, 3 October 1974.
[8] Watkins, Harry. An Application of Rayleigh Curve Theory To Contract Cost Estimation and Control. MS. Thesis.Naval Postgraduate School, Monterey, California, March 1982.
[9] Karsch, Arthur O. A Production Study Sequel to the Cost Performance Forecasting Concept and Model. Cost Research Report No. 132. Aeronautical Systems Division, Wright-Patterson AFB, Ohio, August 1976.
[10] Price, James B. An Evaluation of CPRA Estimate at Completion Techniques Based Upon AFWAL Cost/Schedule Control System Criteria Data. MS thesis, AFIT/LSY/GSM/855-28. School of Systems and Logistics, Air Force Institute of Technology, Wright-Patterson AFB, Ohio, September 1985 (AD-AI62282).
[11] H. Iranmanesh, N. Mojir, S. Kimiagari A new formula to "Estimate At Completion" of a Project's time to improve"Earned value management system" International Journal of Project Management, 2007.
[12] D. F. Cioffi "Designing project management: A scientific notation and an improved formalism for earned value calculations.", International Journal of Project Management vol.24, no.2, 136-144, 2006.
[13] S. Vandevoorde, M. Vanhoucke. "A comparison of different project duration forecasting methods using earned value metrics", International Journal of Project Management vol. 24, no.4, 289-302, 2006.
[14] C. F. Gray and E. W. Larson, Project Management: The Managerial Process. 2nd ed., NJ: McGraw-Hill, 2003, pp 419-448.
[15] Zhang, G., Patuwo, B.E., Hu, M.Y., 1998." Forecasting with artificial neural networks: the state of the art". International Journal of Forecasting 14, 35-62.
[16] Kolisch, R., Hartman, S., 2000. Experimental evaluation of state-of-theart heuristics for the resource constrained project scheduling problem. European Journal of Operational Research 127, 394-407.
[17] The MathWorks, MATLAB (Online). Available: http://www.mathworks.com.